XRPM integration with Cprojects

Hi,
can anybody provide the document related to XRPM and Cprojects as well as Msprojects client/server.
Please send it to theemial address bharat_suman20042yahoo.co.in.

It would be foolish to impliment anything on older versions of SAP for the fear of config/customising going forward r/3 wont be suppoted, then anyways u have to upgrade.then what?
Look at this as an opportunity to learn. SDN is there to help u anyways
btw this book below is an excellent resource to have in your case.
http://www.sap-press.com/product.cfm?account=&product=H1906

Similar Messages

  • MS Project Integration with cProjects

    Dear All,
    We are testing the MS Project Integration with cProjects 4.0. We have 1 query.
    While importing the Project from MS Project to cProjects if changes are done then it creates the new project in cProject system.
    Is it the standard MS Project Integration functionality ? We want the system to update the cProject only for the changes after Import is done. Can we get this ?
    Thanks & Regards
    Ashish Kulkarni

    The system will create a new project only if you have cleared the Project ID field (in MS project).
    Else (if you do not change the Project ID field), the system creates a simulation with the standard system provided simulation for the project.
    Once you have the simulation ready (in cProjects), you are supposed to reconcile the operational project (main project in cProjects) with this simulated copy to bring the updates/changes into effect.
    Hope this helps...

  • Accounting Integration with cProjects documentation

    Hi !!
    I am working on cProjects and right now our team is facing issues with Accounting Integration. It would be of great help if we can get some documentation on accounting integration in cProjects. ...
    I've cProjects Implementation Guide.
    e-Mail Id: [email protected]
    Thanks,
    Jyoti

    Take the reference of the Best Practices Configuration Guides, Link to them is
    http://help.sap.com/bp_bblibrary/600/BBlibrary_start.htm
    Refer Building Block P60: Project Management in R&D with cProjects , it can be helpful
    Regards
    Sreenivas

  • Document for account integration with cProjects needed

    hi all
    can I get accounting integration document?
    <b>mail id        [email protected]</b>
    we have cProject 4 and R/3 4.7 which we will be upgrading.
    i want accounting tab in cProject.
    so need documentation @ it
    waiting with points!!
    thanx a ton

    I have sent it to your mail id.
    p.s. reward points if you find it useful

  • MS Project Client Integration with cProjects 4.0

    Hi,
    I am using cProjects 4.0 and trying to import the MS project.
    It is giving errors as follows -
    a) The constraint date is missing for the start constraint   
    b) MS Project Title is initial: Upload not possible.
    Please guide me what steps need to be followed for the MSproject integration.
    Screen shots would be appreciated.
    Mail id - [email protected]
    Regards,
    Amit
    09820502246

    Hi Amit/Shiv,
    Try the following settings in the customization for import to cProjects:
    PDMP Project Definition (MS P Client) - MAR Project Role Link (MS P Client)
    FINISH PBCP Task Link (cProjects) END_DATE
    START PBCP Task Link (cProjects) BEG_DATE
    WORK PBCP Task Link (cProjects) WORK_EFFORT
    WORK_UNIT PBCP Task Link (cProjects) WORK_UNIT
    PDMP Project Definition (MS P Client) - MAT Task Link (MS P Client)
    FINISH PECP Task Link (cProjects) END_DATE
    START PECP Task Link (cProjects) BEG_DATE
    WORK PECP Task Link (cProjects) WORK_EFFORT
    WORK_UNIT PECP Task Link (cProjects) WORK_UNIT
    PDMP Project Definition (MS P Client) - MC Checklist (MS P Client)
    NAME PCCP Checklist (cProjects) DESCRIPTION
    TEXT10 PCCP Checklist (cProjects) NUMBER
    TEXT21 PCCP Checklist (cProjects) CLH_TYPE
    UID PCCP Checklist (cProjects) CHECKLIST_ID
    PDMP Project Definition (MS P Client) - MCI Checklist Item (MS P Client)
    FINISH PICP Checklist Item (cProjects) FINISH_DATE_FIX
    NAME PICP Checklist Item (cProjects) DESCRIPTION
    TEXT10 PICP Checklist Item (cProjects) NUMBER
    PDMP Project Definition (MS P Client) - MP Phase (MS P Client)
    FINISH PPCP Phase (cProjects) FINISH_DATE_FIX
    NAME PPCP Phase (cProjects) DESCRIPTION
    START PPCP Phase (cProjects) START_DATE_FIX
    TEXT10 PPCP Phase (cProjects) NUMBER
    TEXT20 PPCP Phase (cProjects) PHA_TYPE
    PDMP Project Definition (MS P Client) - MR Resource (MS P Client)
    FINISH PLCP Project Role (cProjects) END_DATE
    NAME PLCP Project Role (cProjects) DESCRIPTION
    START PLCP Project Role (cProjects) BEG_DATE
    TEXT10 PLCP Project Role (cProjects) PARTICIPANT_ID
    TEXT3 PLCP Project Role (cProjects) PARTICIPANT_ROLE
    TEXT4 PLCP Project Role (cProjects) ROLE_FUNCTION_ID
    WORK PLCP Project Role (cProjects) WORK_EFFORT
    WORK_UNIT PLCP Project Role (cProjects) WORK_UNIT
    PDMP Project Definition (MS P Client) - MT Task (MS P Client)
    FINISH PTCP Task (cProjects) FINISH_DATE_FIX
    MILESTONE PTCP Task (cProjects) MILESTONE
    NAME PTCP Task (cProjects) DESCRIPTION
    PERCENT_COMPLETE PTCP Task (cProjects) COMPLETION
    START PTCP Task (cProjects) START_DATE_FIX
    TEXT1 PTCP Task (cProjects) TSK_TYPE
    TEXT10 PTCP Task (cProjects) TASK_ID
    WORK PTCP Task (cProjects) WORK_EFFORT
    WORK_UNIT PTCP Task (cProjects) WORK_UNIT
    PDMP Project Definition (MS P Client) - PDMP Project Definition (MS P Client)
    CATEGORY PDCP cProjects Project Definition PRO_TYPE
    FINISH_DATE PDCP cProjects Project Definition FINISH_DATE_FIX
    NAME PDCP cProjects Project Definition DESCRIPTION
    NAME PDCP cProjects Project Definition PROJECT_ID
    START_DATE PDCP cProjects Project Definition START_DATE_FIX
    Regards,
    Reema.
    <i>Reward all useful answers.</i>
    Message was edited by:
            Reema Shahbazkar

  • Cproject Integration with BW ( Querys )

    Hi gurus,
    In Cproject i could get detailed information of a particular project by the status Report, but as i mentioned it´s only for a particular project.
    I´m testing with  BW integration but i´m dealing with some problems.
    When i execute a standard querys eg. 0CPR_C01_Q0006, i get incomplete information because the phase and the task of every proyect are with '000000000000000000000' (empty), but the project name / description / responsible resource appears.
    Can anybody help me with this?
    Thanks for all.
    Regards,
    Diego

    Hi Diego,
                  I am interested in BW integration with cProjects. But as of now i dont have much understanding on how it is working. Can you explain the way it is working. I am not able to find anything related to this. What is the transaction code to view/execute the queries available.
    regards,
    rajesh.

  • Accounting Integration in cProjects

    Hi,
    I am working on cProjects and right now our team is facing issues with Accounting Integration. It would be of great help if we can get some documentation on accounting integration in cProjects. If any one has something please email it to [email protected]
    Thanks and regards,
    Ankur
    9820997870

    Hi Reema,
    Could you please help me in acct integration with cProjects.
    We are doing like ,1. Creating PS WBS structure manually in ECC 6.0
    2. Trying map the cProject phase and task to manually created WBS to the structure in cProject.
    I have done config as per the SAP document.
    i am getting error costing data not valid, do you have any document to handle this type of multi level controling in cproject, please forward.
    Bijaya my email is [email protected]

  • CProjects and xRPM integration

    Hello Friends,
    I am working on portfolio management(xRPM ABAP), i want to integrate capacity management & cost with cProjects.
    Could you tell me the settings i needed to do for my reqirement.
    Thanks.
    Regards,
    Senthil.

    Hi,
    yes, the integration is permanent.
    For Example....
    During transfer of work centers from Project System to xRPM, teams are created in xRPM for each of the work centre being transferred to xRPM. One can do this from SAP PLM PS by running the report RPM_WRKCNTR_UPLOAD,
    which transfers work centers to SAP xRPM and uses them to create team master data. The team name in xRPM is generated using a combination of plant and work center, because the work center ID is only unique within a plant and can be used again in a different plant.
    The resources assigned to the work center are used to create the resources assigned to teams in SAP xRPM. The employee IDs of resources in SAP PLM PS are used to search for business partners in SAP xRPM with identicalemployee IDs.
    If a match is found, the business partner is added to theteam.
    If the SAP PLM PS work center is created using organization units, the employees in the organization unit are derived during the transfer of the work center and used as the basis for creating teams. If new employees are added to the organization after you have run the report, these employees are not included in SAP xRPM system unless you run the program again. For
    this reason, you should run the program regularly (for example, weekly) or schedule it for background.
    Hope it helps you.
    Thanks
    Arbind

  • Integration of cproject with PS.

    Dear all,
    can anyone send me config document related integration of CPROJECT with PS.
    its very urgent
    fullpoints will be rewarded .
    my email id : [email protected]
    thanks
    amit dhar

    Hello Sunil,
    Kindly send it to me also, I have to initiate the cP & PS integration.
    Thanks in advance,
    my email id : [email protected]
    with Regards
    Rahul Sharma
    Edited by: Rahul Sharma on Feb 22, 2008 6:03 AM

  • Integration of PS with Cproject

    Dear all,
    can anyone send me config document related integration of PS with CPROJECt.
    very urgent
    fullpoints will be rewarded .
    my email id : [email protected]
    thanks
    amit dhar

    hi
    can we select a record from table *dpr_task depending on task name.
    *we know the task project element name how can we select the task_id as there is no task_name field in dpr_task table.

  • FI/CO integration with PM, PS, MM modules

    Hello,
    Any body have information about ' FI/CO integration with PM, PS, MM modules
    Could you please some explore above topic
    Thanks,
    Alex

    HI Luciano,
    It works as designed because of the following reasons:
    1. The WBS ID in ERP system must be unique.
    2. The phase-id in the cProject is NOT unique, you have e.g. same phase-id for two phases.
    That is why the replication does not use the phase-id to create the WBS ID.  The internal ID of phase is (default ID during creation of a phase) is used for replication
    Though there is a Badi method let you change the the WBS ID, but I would not recommend you to do it because of above reasons.
    Kind regards,

  • Tool cFolder with cProject

    Hello to all,
    I am proving the integration of the tool to cFolder with cProject. We have been able that from the eyelash “Collaborations” of cProject to connect with cFolder by means of one collaboration.
    Hay some other form to synchronize to cFolder with cProject?
    Can be connected to cFolder with km Portal with WebDav?
    I have given permissions of reading to a user on a folder of a collaboration in cFolder and it does not work, since it allows him to copy, to write… etc.
    Best Regards,
    Jennifer Lohan.

    Hi
    check the roles you have given...
    Do not give Cfolder admin role to user.
    You need to give only 1 role i.e. cfx_User
    Then you give authorizations from particular Folder... which should be Read then send a notification to user. thru notification the user will be in position to enter the specific folder where you have given auth.
    About KM, you can have cFolder in KM via iViews....
    In cProject, you can have cFolder thru Collaboration link only... At least as standard feature...this can be controlled by SPRO> cPro> Structure>project type settings...
    Explain the scenario in detail....
    Niranjan
    Award points if useful !!!

  • Problem in Accounting Integration in cProjects 4.0

    Hi,
    I am trying to customize the Accounting Integration in cProjects 4.0 with R/3. The  problem comes when I try to replicate the Cost/Revenue rates to the R/3 system. I get the following error: "<i>Cost/revenue rate PM01: organizational unit 40000582 does not exist</i>"
    The "organizational unit" is set in the cost/revenue rate as organization responsible. Why is that error poping up? Where can I create those organization responsibles? Do I have to create the data in my R/3 system?
    Thanks in advance!
    Best regards,

    Thank you very much for your info, but I am still having the same trouble.
    Apart form the former one I got two more customizing problems:
    The point "Make settings in ERP systems" returns in an error
    In the point Define Controlling Scenario in R/3 I don't have to option to choose Multilevel Controlling (can I customize those options?)
    Thanks again,
    Best regards,

  • SD Integration in cProjects

    Hello,
    I am using cProjects with hierarchical accounting. The point I am not getting is the SD Module.
    The workflow is using cProjects to make the projects structure and then the PS structures is generated automatically by cProjects with the PS template. Now I am recording times with CATS/ESS.... everything is clear to this point.
    The point is the SD module.
    I have seen one scenario using a normal standard order with the DP90...
    - Is it possible to use the same standard order with the DP90 several times for billing different time periods or do I have to create a standard order for everytime I want to run the DP90?
    - Is it possible to use a service order instead of the standard order? If yes, where can I maintain the connection between the PSP-element and the order?
    - How are you using the integration between cProjects and CO to SD. How deep is this integration? What is it able to do?
    It would be nice if someone could bring the light into the darkness...
    Thx a lot,
      Vanessa

    Hi Everyone,
    although Vanessa found her answer, I though this might interesing for whole community I asked my local DP90 expert. And this is what he has to say:
    Is it possible to use the same standard order with the DP90 several times for billing different time periods or do I have to create a standard order for everytime I want to run the DP90?
    If standard order is a sales order created via VA01, than it works in the following way: You call transaction DP90 and the system determines all confirmations created for the time period entered in selection screen and checks if the cost records selected were already billed. If there are open amounts/quantities you can bill them. So, you can use the same sales order over and over again.
    Is it possible to use a service order instead of the standard order? If yes, where can I maintain the connection between the PSP-element and the order?
    No, it's not possible to use a service order created via IW31 in standard. If you have to use a service order you can use enhancements within Dynamic Item Processor ( see also attachment to note 301117 ) to provide this.
    How are you using the integration between cProjects and CO to SD. How deep is this integration? What is it able to do?
    You can create an inquiry with cProjects planned costs using DP81 (see SAP Best Practices D50 and D83, too).
    Additionally, you can use the functionality which is possible in ERP Project System if you have got a PS Project linked to the project in cProjects (multi-level controlling) like budget.
    I hope others having similar questions find these answers usefull.
    Best regards,
    Thomas

  • Integration with cFolders

    Hi all,
    How to integrate cFolder with Microsoft Windows File Explorer Practically.
    I used transactions CFI01 , CFE01  for Back-end Integration since i don't know how to create a cProject and cFolder i cant proceed can anyone help me to come out of this problem.
    Thanks in advance.

    Hi Shounak
    As I have a problem regarding the integration with windows explorer and C folders, I have taken this chance to enter this conversation.
    First of all I have done the acticities that you have stated:
    1. Activate the SOAP handler in the SAP Web Application Server, by activating the
    /sap/bc/soap/rfc node in transaction SICF.
    2. Execute the Specify URLs for Windows File Explorer Integration activity in Customizing
    for Collaboration Projects.
    The activity is also relevant to cFolders.
    3. Assign the users who are to work with the Windows File Explorer the appropriate RFC
    authorization in the user profile.
    Function group CPRO_API
    Authorization object S_RFC
    4. Activate the function in your personal settings as the user and execute the installation
    file:
    The only thing, that I haven't been able to do os to assign the function group CPRO_API. I have asked my authorization contacts, but they couldn't help me.
    Can you tell me how to do this?
    Furthermore I have a problem when trying to upload a document from my windows explorer. Even though it says that the upload has been succesfull, no update is happening when I look in the C folders application.
    Thanks for your help in advance
    Maria

Maybe you are looking for

  • I'm getting really annoyed with the Mac.

    Don't mean to offend geniune Mac fans here, but I'm just getting really annoyed with the Mac. I purchased my Mac mini (late 2012) in May of 2013 - so it's about 4 months old. I don't have a lot of software on it, mainly the Adobe Creative Suite, and

  • What are the limitations of the free 30-day InDesign trial?

    What are the limitations of the free 30-day InDesign trial?

  • How to use Page to type fraction?

    I don't know how to type fraction, can anyone help me? I need the verticle style, not 1/2. Thanks in advance.

  • Mac OS X 10.7

    Model Name: iMac   Model Identifier: iMac6,1   Processor Name: Intel Core 2 Duo   Processor Speed: 2.16 GHz   Number Of Processors: 1   Total Number Of Cores: 2   L2 Cache: 4 MB   Memory: 4 GB   Bus Speed: 667 MHz   Boot ROM Version: IM61.0093.B07  

  • Adobe reader does not respond

    Just updated to Adobe reader 11 and it hangs when opened.  Error says not responding.  Running Windows 7.  Have uninstalled and re-installed multiple times.