Work Center Hierarchy and Capacity
Hello SAP friends,
Can someone please help me with the following scenario?
I have 3 Work Centers
MAQ00 - (Capacity 10:00 x 2)
MAQ01 - 8:00 -- 18:00 (Capacity 10:00)
MAQ02 - 8:00 -- 18:00 (Capacity 10:00)
I have a hierarchy
HICY01
MAQ00 - Root of hierarchy
|_ MAQ01
|_ MAQ02
Then, I have a routing
10 - PP01 - MAQ00 - 1H
20 - PP01 - MAQ00 - 2H
If I go to CM01 for Work Center MAQ00 I can see the capacity and requirement, where:
Capacity: 10:00 x 2
Requirement: 3:00
But if I go to transaction CM21 for Work Center MAQ00 the capacity and requirement is not correct. Can someone please help me with this?
Thanks in advance,
Adelmo Silva
Hi,
CM01 will give the cumulative requirement as 3 hrs but CM21(Gradhical View) shows the individual spread of oprn. 10 and 20 as 1H and 2 H resp.
Does the above help you?
-Thaila Shree
Similar Messages
-
Work Center Hierarchy and Routing
Hi,
I would like to know what exactly Work Center hierarchy mean?. Where is it used. In Routing, we maintain Sequence of operation along with workcenter where this operations are performed . Would like to know does work center hierarchy is linked to sequence maintained in Routing?. ThanksHi,
Any one can explain me the use of Workcenter Hierarchy?. In Routing, we maintain the sequence of operations. Does Routing and Workcenter Hierarchy has relation?. If Yes, what is the relation between these 2.
Thanks in advance -
Dear Gurus,
How can I use work center Hierarchy for Capacity Planning.
I have 5 Lathe machines. How can I use Work Center Hierarchy?
I also need Work Center Wise confirmation.
Please guide me. Also let me know how should I maintain data in work center as well as in routing.
Thanks in advance
RGCreate a new WC (in CR01) as category 0004. This will be the top level WC in your hierarchy. <BR sab="44">Create a hierarchy (in CR21). <BR sab="46">Add your 5 lathes and the newly created top level WC to the hierarchy (in CR22). This can be tricky: the WC you just created must be the top level, the other 5 must be under it. <BR sab="50">Pull the capacity data (in CM01) for the hierarchy: go to settings, hierarchy, check the cumulation of requirements and capacities and type the hierarchy name. <BR sab="54">Route things as before, to the original 5 lathes.
-
Capacity cumulation in work center hierarchy
Hello
Does anyone uses workcenter hierarchies to cumulate capacity requirements ?
I've created a hierarchy but in the capacity evaluation transaction cm01,
the capacity requirements are not cumulated from the underlying work center.
Instead a capacity requirement of zero is shown on the hierarchy work center.
Is there any specifics to cumulate the capacity requirement to work center hierarchy header
Best regards
PascalHi,
In the transaction CM01, choose the pull-down menu Settings-> General. In the pop-up screen, under the "Herarchy" tab, select the check boxes "Cumulation of reqmts" and "Dyn. capacity cumulation", choose the "Hierarchy" and "Plant" and click on "Continue".
Now the "Available Capacity" will be as per hierarchy setup and Rem. avail cap = Reqmts-Available capacity.
Hope this solves the requirement.
-Thaila Shree -
Capacity planning at Work center Hierarchy level
Hi,
I have created Work center Hierarchy, now want to see the cumulative capacity of subordinate work centers at Superior Work center level, but using cm01- std overview, i can't see.
Can anybody tell me , what-ever is missing?
with thanks,
Rasika
9869028103HI Mangalraj,
Thanks for your reply. I had tried that , even though there is no cummulation done.
System is showing same error ,as 'There are no capacity requirements for the
selection and settings'.
what i have given input is Superior Work Center, Plant and Planner group.
I didn't mentioned the capacity at superior WC.
PLEASE HELP.
Rasika. -
Work center design and operation confirmation
Hi All,
In my scenario im grouping the similar m/c to a work center
say for ex. 4 lathes m/c into a single work center as LatheALL and also the indiv cap as 4
my customer wants the traceability in which m/c the job is done
So i had designed in such a way that
1 LatheALL -4 cap(this will be additional wc)
2. lathe1 - 1cap
3.lathe2 - 1cap
4.lathe3-1cap
5.lathe4-1cap
in the routing only latheALL will be given., this will help customer in planning
when going for operation confirmation i will give confirmation for that operation and will confirm as lathe1or lathe2 or etc.. this will help prodn dept for traceability in which m/c the work is done
this is method i have informed to client .,
pls advice is this approach is correct ?
also suggest by giving confirmation for another work center will the capacity for the original work center will be reduced
Regards
Anand SrinivasanHi Anand,
this is method i have informed to client .,
pls advice is this approach is correct ?
yes, during confirmation time to enter the orginal actual work center, this suitable for your client requirement, do the settings for OPK0 - change the confirmations parameters (0410 or 0420)
Regards,
Sankaran -
Maintaining work center list in Capacity Planning: Selection List in CM01
Hi,
Where can find the config route in SPRO for maintain work center into the Capacity Planning: Selection List in CM01?
Thanks a lot!
MinMandy,
Couple of combinations you should check,
1. First try to identify "Selection Profile" which is used. In "CM01" go to menu Planning->Profiles->Selection Profile.
2.Check the defination of this profile using transaction "OPA2". Here you need to look for "Work center Set" which is assigned.
3. Now look at the defination of the workcenter set using transaction "CMS3", here is were we define as how the list is to be fetched.
Hope this helps....Reward your points and close the thread if so,
Regards,
Prasobh -
Profit center hierarchy and cost center hierarchy
Hi
What are the things we have to consider to create Profit center hierarchy and cost center hierarchy and what is the need to assign profit center hierarchy to profit center and cost center hierarchy to cost center. What levels does this fall into? Can some one please guide me.
Thanks.As you would for any other infoobject
Activate the business content hierarchy datasources on R3 for cost centre and profit centre
Go into BW - replicate the metadata
Then just connect via transformations or transfer rules the datasources to yoru infosources or master data objects
Create an infopackage per hierarchy!!!!! - press the button available hirachies from OLTP - click the one you want on the left - fire it off
Then repeat new infopackages for all hierachies -
Regarding work center hierarchy
Hi all,
I have 2 work centers liked to a superior work center in a hirarchy.
Is it possible to do capacity planning at the superior work center level.
The scenario is like this - I will get planned order at a superior work center level. I will convert the planned order into 2 production orders with child work centers in respective order.
Now I want that, when I see the capacity overview for the superior work center, it should be full. That means I want to link the capacities of the child work centers to the parent work center.
Please let me know if it is possible ?
Regards,
YogeshHi,
Work center hierarchies are used in capacity planning to cumulate available capacity and capacity requirements. You can cumulate available capacities from subordinate work centers to a superior work center level in order to determine the total available capacity for the superior work center.
In your situation, I think you need to create two planned orders with the two work centers and after this you will be able to see the capacity requirements cumulated at the superior WC.
Regards
Datta -
Upload/ download Work Center Hierarchy
Hello All,
I need your help with this one. Therefore thanks in Advace:
Is there a way to download and upload work center hierarchies?
The idea ist to download a complex hierarchy to a file and then upload it to another system/ client.
Thanx
RafHi Daniele,
I just tried the way you suggested:
- RCRAPDX1 downloaded a txt to presentation server with data.
- changed only the plant in file.
- run RCRAPDX2
unfortunately result is that ths system try to maintain the work centers within the file,
(which are already maintained).
The hierarchy structure won't be maintained.
So what I look for is a manner to transport the complete hierarchy structure...
regards
raf -
CO11N work center mandatory and without default
Dear guru,
i need to make work center mandatory in CO11N and without any default
from production routing.
I donu2019t want to use SHD0.
Do you suggest any exit to obtain this ?
Thanks in advanceHi,
I believe the user-exit which you should look at is:
CONFPP03 PP order conf.: Cust. specific check after op. selection
or
CONFPP05 PP order conf.: Customer specific enhancements when saving
Check with your abaper if the above can meet your need.
Regards,
Vivek -
Buyer Work Center performance and persoanlizations
Hi All,
we are currently on R12.1.3 and we've few issues with the way the Buyer Work Center is working
1) The performance of BWC is very slow. Navigating from one field to another field takes at least 5seconds. For fields like project, task, org etc the form takes 10seconds also. Combining all this, creating a PO with 10 lines takes about 10-15mins for our users. Is this normal? Are there ways to improve the performance?
2) There are multiple screens to navgiate. First the users start off with header then to line summary and then to line details/schedules/distributions etc. Is there a simple way to make all information available in one single page so that the users do not have to spend time navigating from one screen to another screen? This will be really helpful for users creating POs with more than 10lines. I'm thinking of persoanlizing the PO line summary screen and make POET available there. Has anyone done any customizations to the PO line summary screen?
I'm sure you must have faced similar issues with your clients. Please let me know if you handled these issues.
Thanks,hadimulam wrote:
2) There are multiple screens to navgiate. First the users start off with header then to line summary and then to line details/schedules/distributions etc. Is there a simple way to make all information available in one single page so that the users do not have to spend time navigating from one screen to another screen? This will be really helpful for users creating POs with more than 10lines. I'm thinking of persoanlizing the PO line summary screen and make POET available there. Has anyone done any customizations to the PO line summary screen? Same question was asked by my client, I recommended them to go directly to the "Distributions" tab and search for the PO. Actually most of the key fields from the header, lines, shipments and distributions are available at the distribution tab and you can add many more fields by clicking on the "Add Another" field. Moreover, you can save the final view for future reference so that you don't need to add the same fields again.
Yes, it is a workaround, as you will see repeated lines for multi shipment and distribution scenarios but single shipment - distribution scenario will be OK.
Thanks,
PS. -
Profit center hierarchy and closure transactions
Hi fellows,
My company is reorganised.
As the annual closure will last several months, I will need to run 2 profit center hierarchies at the same time.
I will copy the standard hierarchy 2009.
The standard hierarchy 2009 will be modified and used for 2010.
The copy will become an alternative hierarchy used to close 2009 accountancy.
Do you see any problems to run 2 hierarchies at the same time?
Is it possible to make the annual closure with an alterative hierarchy for transactions (KKAJ, KSII, KB15N...)
Thanks a lot
VeroHi
You can maintain as many number of hierarchies as possible.
There is absolutely no problem to maintain any alternative hierarchy but you can't maintain multiple standard hierarchies.
Profit Centre Standard Hieararchy T.Code is KCH1 - Create, KCH5N - Change, KCH6N - Display
Profit Centre Group (Alternative hierarchy) T.Code is KCH1 - Create, KCH2 - Change, KCH3 - Display.
Regards.
Chandrasekhar Ponugumati -
Hi Friends,
I have A REAL URGENT REQUIREMENT as far as activity type and assignment to Work Center is concerned.
I work for a client who is a manufacturer of Paint equipment. I'm responsible for capturing the cost of an assembly activity of spray guns, which is the last step of routing. However, there are 4 processes/steps of routing which are outsourced to the subcontracting vendors. we recieve the facbricated, anodised guns which are assembled in our factory.
I need to get the cost of assembly, which I have created as an actvity type in KL01 and planned for the same using KP26. However the system is throwing up errors related to costing, and I'm not sure about the assignment areas in work center.
And above all I'm not sure of various fields in KP26 like capacity field and what do we assign.
can anybody help me with the series of steps for me to be able to pick up the cost. or if there is any sort of material in this regards, plz mail it to: __ email removed by moderator
regards
sandhyaHi,
You need to do the following:
1) Create an Activity type for the Assembly activity.
2) Define a Work Centre in PP (T-Code CR01) which represents the location where the Assembly is carried out.
3) Define a Cost Centre corresponding to the above Work Centre.
4) Plan for the Activity quantity for the combination of the Cost Centre and Activity type (KP26)
5) Plan for the Overhead Costs which are incurred on this Cost Centre which need to be included in the Standard cost of the Assembly.(KP06)
6) Assign the Cost centre & Acivity type to the Work Centre in CR02.(This is possible only after you do 5 above)
7) Execute the Plan price calculation (T-code KSPI)
After you do all of the above, when you do the Costing Run, all the relevant costs will be picked.
Ofcourse all the relevant master data for PP like BOM, Routing with the relevant assignments of materials to operations, etc should be in place.
Regards,
Assign points if useful -
Function Module to get a work center's capacity requirements (load) within a given period
Hi all experts,
Currently I’m doing a capacity summary report similar to CM01, but with a summarized capacity availability and loading for a period.
Selection Parameters: Work center range from and to, Period from and to
List Format: Work Center, Avail Capacity, Loaded Capacity, Free Capacity, Load %
I have found a standard function module (FM) to get work center's available capacity for a period, but still facing the challenge to find a FM to get a work center’s capacity requirements (load) in a period.
I have read through all the related threads from the web, and tested the recommended FMs, but still cannot get a right result.
Please help to provide some leads for a FM or the logic.
Best Regards
PhilipHello Philip
The following function modules should be useful:
- CY_PRIMARY_SELECTION - Function module for selection of orders for the work center
- CY_SECONDARY_SELECTION - Check for additional criteria
- CR_CAPACITY_AVAILABLE_PERIODS - Reads the available capacity from work center
- HR_PERSON_READ_TIME_INFO - Reads the available capacity from person (modification)
- CY_GET_PART_CAPACITY - used only for the first period to read backlog
- CY_LOAD_DISTRIBUTION - Distribution key
Please observe that these are simple function modules, not BAPIs, That means, they were developed to be used on the SAP internal programs and they are not supported by SAP when used in custom programs.
BR
Caetano
Maybe you are looking for
-
My iPhone is not active. please help!
I use iphone 3gs ios 4.1 version. I have update to iOS 6.0. but not activated! expect your company to help me. I am very grateful! Now I do not remember the series of air compressors can provide.
-
What is wrong if you insert a disc to download and it spits it out and says it is untitled
I am trying to download Office Mac 2011 to Macbook and it spits it out and says it is untitled. This is the second disc I have got. DVD's are playing find.
-
Hi All, I have a scenario where i need to use XSLT mapping, I would like you to provide docs/links from where i can get info abt XSLT mapping. Thanks in advance Shiva
-
Connecting iPod to car radio - USA-Spec
Just installed the USA-Spec adapter to connect my iPod to the factory radio in my Toyota via the CD changer (no factory iPod connector). This is by far the best sounding and most elegant solution I have found - since it's a direct connection and ther
-
Can't view a report connecting through ODBC(RDO) to DB with InfoView (CMC)
Environment : Crystal Reports machine : OS : Windows Server 2008 64-bit Crystal Reports Developer 2008 SP0 Crystal Reports Server 2008 DB Server: Windows Server 2003 32-bit SQL Server 2000 SP3 What is going on: All the reports connecting through ODBC