hi,
I am using the 2lis_02_scl datasource and I am looking for delivered qty field in this datasource. Can any one tell me which field provides Delivered quantiy information.
Regards,
Raghu

The PO or scheduling agreement schedule (requested) quantity, depending if you have scheduling agreements with your vendors,  would be sourced from the same field (BWMNG), where the BWVORG is:
001 - Normal Purchase Order Schedule Quantity
004 - Normal Scheduling Agreement Schedule Quantity
005 - Normal Purchase Order Schedule Return Quantity
011 - Stock Transport Order Schedule Quantity
014 - Stock Transport Scheduling Agreement Schedule Quantity
015 - Stock Transport Order Schedule Return Quantity
021 - Cross-Company Order Schedule Quantity
024 - Cross-Company Scheduling Agreement Schedule Quantity
025 - Cross-Company Order Schedule Return Quantity
041 - Normal Scheduling Agreement Schedule Return Quantity
051 - Stock Transport Scheduling Agreement Schedule Return Quantity
061 - Cross-Company Scheduling Agreement Schedule Return Quantity

Similar Messages

  • Proposed delivery quantity in inbound delivery vs purchase schedule line

    Hello all
    I have got a doubt when creating inbound delivery for an item of purchase schedule line. I want to know how to get the proposed delivery quantity equal to the quantity of all schedule lines until today.
    For example I have got 4 schedule lines for a material and today is 28.10.2011
    20.10.2011 11ud
    28.10.2011 13ud
    03.11.2011 17ud
    05.11.2011 15ud
    when I execute VL31N with date = 28.10.2011, I want to proposed delivery quantity = 11+13 = 24ud.
    However, what I got is always the total quantity of all pending schedule lines = 111317+15=56ud.
    Do you know how can I achieve my propose?
    thank you in advance

    Hi Alan
    Thank you for your reply.
    In some cases (depending on vendor) we are using vendor ASN by EDI. In other cases (when there is no EDI conection with vendor) we use manually VL31N. So in these cases we need a proposed quantity by system in order to know if the quantity that we receive is coherent. Maybe we will try to implement the inbound delivery user exit.
    Thanks again!

  • Schedule lines generated on wrong date

    Dear Experts,
    In my scenario I am creating a Sales schedule & running MRP to generating Purchasing Schedule lines for the Brought Out parts(BOP).
    Here Planned delivery time is =10 days (MRP2).
    There is dependent req. for a BOP u201CXu201D as per below given daily figure,
    Day 1   1500
    Day2    1500  etc u2026u2026u2026u2026u2026u2026..
    ( available stock of BOP = 100, including  Safety stock = 50 )
    Schedule line must be generated on DAY1 but it is generating 10 days after the date of requirement (Here 10 days are Planned delivery time , Here MRP type = PD ,  Lot size = daily lot size , Special procurement= 20 , Availability check = 1  Etc. )
    But I need Schedule line must be generated 10 days before the requirement, so that material can be procured and received before the requirement date.
    Please let me know How can it be done ?
    Please help
    Ashutosh

    Dear Sir,
                   Please increases the Gr time.System will take care the requirement. Put the plannned delivery time as "0".Also make changes in the GR time, make it "09: and see the impact.This will full fill your requirement.Goto OPPR,maintain MRP Group,Select the external procurement , de-select the sechduled the info-record/Agreemnet.So it will consider the planned delivery time maintained in the material master.Yopu could do the same thing yhrough OPPQ,-Externakl Procurement.De-select the Planned delivery time.
    Note-After doing this, if you maintain the GR time as "0". then the sechduled line will be generated as on today.if "1", it wsechduled line will be created a day befor e requirement.So in you case the put the GR time as "10 days". so the sechduled line will be generated 10 days before the production date.
    Say Cheers
    Regards
    Bhupendra Singh

  • Schedule line consumption

    Hi Guru's,
    Its bit urgent!!
    I have balance receipts up to today against schedule lines say 100nos. These MRP generated schedule lines are of past dates.Alos there are schedule lines in future dates. Today I wants to receive more than 100nos.(say 200nos.) In MB01 I can receive any quantity by selecting "suggest zero lines". If I do so, the extra 100 nos. quantity is consumed against the immediate available schedule line, whether it is firm or non-firm.
    My requirement is, I wants to consume this extra quantity from firmed lines.
    How can I do this and what is the consumption logic.
    Thanks.
    Suresh

    Hi Suresh,
    Now your question is clear. As per my working knowledge about purchased schedule lines your requirement is not possible.
    Whenever you make GR then first available scheddule line will be reduced (consumed) and then next till the last availabe one. If stock GR stock increases then no schedule line will come automatically from MRP but you can create manaully.
    Firming will come only if create schedule lines quantity manually or changed this after MRP...This is also possible if you use MRP types P1 to P4.
    Firming has no effect on the consumption logic, this only restrict the automatic changes of quantites in MRP run..if you want you can change manually.
    If you are doing extra GR...compare to the schedule lines quantity then next schedule line quantity will reduce. You cannot restrict this.
    Hope this is clear. Any question then please inform with rewarding suitable points.
    Regards
    TAJUDDIN

  • How to delete the old schedule line release in apo

    How to delete the old schedule line release (from current date) in apo which is having schedule  firmed?
    Please suugest.
    Sunil

    How is it possible to delete old purchasing schedule lines in APO (that do not exist in R/3)?
    Though used successfully before, /SAPAPO/CCR will not reconcile our discrepancy in this case.
    Thanks in advance,
    Jim

  • Using MD42 purchase requisitions creating instead of schedule lines

    Hi PP Guru's
    Can any one help while using MD42/MD43 purchase requisitions generating instead of schedule lines.
    MRP Type :M0
    what are the required settings for this..?
    please help me to solve this issue.

    Hello
    This is a link to a note and you need to have access to SAP service marketplace.
    Please ask your system admin/basis and he will be able to provide you an user.
    The following information from the note should be relevant for you:
    If the flag "SC Vendor" is checked on the scheduling agreement, this source list entry will only be considered on a third-party order processing scenario with MRP areas.
    If you are not using MRP areas, this source list entry will not be considered and the vendor/schedule agreement will not be selected. This setting can be found on transaction ME32, on the menu path "ITEM" - "MORE FUNCTIONS" - "DELIVERY ADDRESS". See note 214298 for more details.
    BR
    Caetano

  • BAPI for schedule lines (purchase scheduling agreement)

    HI
    Is there a BAPI available to create schedule lines in purchase scheduling agreements?
    Is there any other way of creating schedule lines in purchase SAs via program?
    Thanks in advance
    Sriram

    Dear Sriram,
    Please check BAPI_SAG_CREATE with SE37.
    Regards,
    w1n

  • Purchase Requisitions created instead of Schedule lines

    Hi Experts,
    When I run MRP for materials with mrp type as PD, MRP creates Purchase Requisitions instead of Schedule lines
    I have Scheduling agreement in place.
    Kindly let me know what could be the possible reasons for this
    Thanks & regards,
    Shashidhar

    Hi
    While running the MRP, Check the input parametrs.
    Check the MRP control Parametrs
    Delivery schedules - ensure that Schedule lines has been created.
    Check it out.
    Raman

  • Converting Multipule Reqs to a Purchase Order with Delivery Schedule Lines

    Is it possible to convert a multiple Purchase Reqs for the same items to a PO that has one line but multipule deliver dates in the Schedule lines - Where the Purchase Reqs have been generated by MRP
    Example
    I have an SAP Contract 46***** that runs via MRP and creates 3 Reqs for item number 12345. All from the same vendor
                 Req 1 delivery date 2/4/10  QTY 50
                 Req 2 delivery date 6/4/10  QTY 20
                 Req 3 delivery date 10/4/10 QTY 30
    Aim is to have 1 PO with line 1 having a QTY 100 but the Delivery Schedule Tab to show the three seperate delivery needs
                date 2/4/10  QTY 50
                date 6/4/10  QTY 20
                date 10/4/10 QTY 30
    Any Help?

    When i try that the QTY in line one does not alwasy update to the total qty of the reqs and infact the qty on the req doesnt always appear in the schedule line....
    This works for me perfect, I never encountred that the item quantity was not updated if I added a new requisition to the schedule.
    ME59N should work, do not select per requistion and per delviery date in the New PO section in the selection screen. But set a flag into box create schedules.

  • Issue on Purchase order creation with Delivery schedule line items per PR

    Hi
    Note->Developed inbound FM to create PO's in SAP through IDOC.
    We are creating purchase orders from vendor which is coming from Inbound IDOC. Here we are using as BAPI_PO_CREATE1
    to create PO's. before that i am passing all the inbound data of the IDOC and getting some Purchase requisions for plant and material wise from EBAN table where we have open PR's and split the inbound line item qauntity as per Open quantity in Purchase requisions. Problem here we are modifing schdule line data as per purcahse requisitions and post the all the shehduline data into above functional module, we are using creation date as delivery date in the scheduling line for each line.
    Set1- If we have multiple requisions for each material and plant in the inbound IDOC item , while creating PO using  above BAPI
    creating PO with delivery date is taken from Purchase requesion date, this only will happend in the first schudle line item always, second line scheulde has taken correctly from creation data as delivery date.
    Set2-If we have one requisition for each line item, it will creating correctly for schulding line item as with correct delivery , whcih is not taken from requstion delivery date.
    Set 2 is working correctly, but Set1  has problem with delivery date  in the scheduling lines particulary for first schduling line item.
    Please help me on this issue.
    Advance wishes

    Hi Satish
    Thanks for the reply.
    I checked the parameters and it is creating 2 PO when the Indicator Ordering address is set.If I uncheck this Indicator then only one PO is created.
    But now my question is from where is the Ordering address taken because for both line items Vendor is same and ordering address is also same.
    Then why the system is creating new PO?
    Regards
    Vaibhav Mahajan

  • MD04 - Delivery Date shown as per 1st schedule line in Purchase order

    HI ,
    we have an issue in one of our client related to Purchase order .see detials below.
    we have maintained the configuration " E " under STO configuration with the combinaiton of Purchase order type , Delivery type ,Checking Rule .
    SPRO = Material Management = Purchasing = Purchase order - Setup stcok stransfer order - Assig delivery type to checking rule
    we have assign the E = Display the delivery proposal with dailog box under feild " Rules adoption for ATP check "
    it means that when you create the Purchase order with Qty then system will propose an new screen with delivery proposal.
    we need to select one which would like.
    once you select it system will display to schedule line items for line item in Purchase order.
    first schedule line item delivery date will be calcualted based on the Planned delivery time
    second delivery date will be calculated based on the Route determiantion ( Note this functionaity will be avialble in Ecc 6 and may be in 4.7ee also )
    so now issue is when we see MD04 system is showing first schedule line delivery date in MD04, it was suppose to show the second scheduline delivery , but it is not happening .
    why ?  is it STD behaviour ?
    pls check it and suggestme

    Hello,
    We are also experiencing this issue in ECC 6.0 with the first schedule line showing as the delivery date in the receiving plant in MD04.  In our case, we have sales orders that are placed on the distribution centers, and that triggers an STO to be generated for shipment from the Source plant to the DC to fulfill the Sales order demand.
    We have also noticed that in CO09 for the receiving plant, the committed dates are not displayed, so ATP is incorrectly calculated at the distribution center when rescheduling changes the committed dates in the STO due to a change in material availability.
    Has anyone been able to find any solutions or additional findings to workaround this issue?  I see that SAP development will be taking a look at this but that was last updated in May of 2011.  I have not been able to find any other additional information on OSS that addresses this issue.
    Thank you,
    Tina
    Original Post from pentakota srini:
    "HI,
    We have an issue in one of our client related to Purchase order .see details below.
    We have maintained the configuration " E " under STO configuration with the combination of Purchase order type , Delivery type ,Checking Rule .
    SPRO = Material Management = Purchasing = Purchase order - Setup stock transfer order - Assign delivery type to checking rule
    we have assign the E = Display the delivery proposal with dialog box under field " Rules adoption for ATP check "
    it means that when you create the Purchase order with Qty then system will propose an new screen with delivery proposal.
    we need to select one which would like.
    once you select it system will display to schedule line items for line item in Purchase order.
    first schedule line item delivery date will be calculated based on the Planned delivery time
    second delivery date will be calculated based on the Route determination ( Note this functionality will be available in ECC 6 and may be in 4.7ee also )
    so now issue is when we see MD04 system is showing first schedule line delivery date in MD04, it was suppose to show the second schedule line delivery , but it is not happening .
    why ? is it STD behavior ?
    pls check it and suggest me"

  • Schedule line item data missing in Purchase order form in ECC6.0

    Hi All,
    We are doing ECC6.0 upgradation project . I am trying to print Purchase order in ECC6.0 , all data is coming fine in PO except schedule line item data is missing.
    Same print program and form works fine in 4.7E but schedule line item data missing in ECC6.0.
    Print program is a copy of standard SAP program SAPFM06P and layoutset is a copy of MEDRUCK.
    If anyone knows if there is any OSS note for the standard print program or any solution please let me know.
    Thanks,
    Sonali.

    Resolved on own.

  • Purchase requisitions to schedule lines conversion

    hi,
    Is there a way to mass convert purchase requisitions to schedule lines directly?
    The material for this scenario would have a scheduling agreement and source list defined but i am unable to use ME59 to do this. All the indicators for auto PO have been checked.

    Hi,
    For creating schedule lines automatically, you have to maintain at source list the vendor & schedule agreement number & mark at MRP column as 1 (MRP relevant). Then system will generate the schedule lines from MRP
    Regards,
    Prashant Kolhatkar

  • Purchase Requsition Conversion to Schedule lines

    Can any body reply me with the table/view where i can link with the purchase requsition Number and
    Schedule line Agreement number in APO.

    Data is stored in livecache so no direct table .
    you can use FM/BADI to get the details :
    BAPI_POSRVAPS_GETLIST3
    also check structure :/SAPAPO/RRPIO
    Manish

  • Converting Purchase Requisition to Schedule Line

    Dear all,
    I am trying to decide how to create schedule lines in R/3 using the plan generated by APO.
    I have not transferred scheduling agreement to APO. I have created the purchase requisition in APO, with no source of supply, and transferred it as purchase requisition to R/3. Can I create schedule line using this purchase requisition in R/3? Or do I have to transfer scheduling aggreement as an external procurement relationship in APO to create schedule lines in R/3?
    Thanks in advance,
    <i><b>Ergul</b></i>
    Message was edited by:
            Ergul Taslacioglu

    Hi Ergul ,
    Did you get the solution , i have the same requirement.
    Can you please share it.