A trigger blocking function  for control cycle in Kanban

Hi,
I wantet to change the status in Kanban. I get this error u201CA trigger blocking function was defined for the control cycle in the replenishment strategyu201D. I don't want to set a period of blocking function. how can I deactivate it.
Thanks

Hi,
Pls. check the following setting :
First in PK13n ( KANBAN Board) check whether X is marked with KANBAN Number e.g. 1X.
If so then replenishment will not be triggered because KANBAN is locked.
To unlock the KANBAN pls do the following :
Go to -
> PKMC ( Control Cycle Maintanance) in Change Mode----> Select Control Cycle -> Go to Display Control Cycle ( Glass Icon)--> on top of details of kanban cycle choose option ---> Display Kanbans ( Spectacle Icon )
Select it and go inside : Inside pop up appearing check first Column : Lkln ( Lock Indicator).
Remove the tick in check box of lock indicator for respective KANBAN for which  you want to trigger replenishment.
Pls. try above settings and revert back if still problem persists.
Reward if problem solved.
Regards,
Tejas
Edited by: Tejas  Pujara on Aug 1, 2008 12:25 PM

Similar Messages

  • Is there a call block function for the iPhone 4S?

    Is there a call block function for the iPhone 4S?  If not, will it be offered in the future?  what else can I do to the phishing calls?

    No.
    Apple has not said.
    Don't answer your phone.

  • Not working Billing Block functionality for Invoicing Plan

    Hi Experts,
    I am using Invoicing plan functionality to purchase materials by using Milestones from Network of Project System. The system is allowing to post Vendor Invoice (MIRO) without removing of Billing Block of Invoicing Plan from PO and the system should give error message because of non removal of Billing block.
    The following configuration was done in Invoicing Plan of PS.
    1. Assigned Date Category to Invoicing Plan Type (30)
    2. Assignment of Invoicing Plan Type to Network Profile
    The following configuration was done in Invoicing Plan of MM.
    1. Assigned default date category to Partial Invoicing Plan type
    2. Maintained Date category to Invoicing Plan type
    3. Assigned Date proposal category to Invoicing Plan Type
    4. Maintained Date Proposal to Invoicing Plan Type
    What are the changes needs to do in configuration or transaction to prevent to post vendor Invoice because of nonremoval of Billing block from Invoicing Plan?
    Please give me the solution.
    Thanks in advance,
    Rao

    Hi Rao
    You need to have the invoicing plan done in Project System (PS) under the project with Milestones and save the plan. On dong this, the system would generate a 'Reference Number'. This can be seen when you again go to the invoicing plan.
    Use this reference number in the MM invoicing plan to link the PS & MM plans. This would create a block automatically in MM which can be lifted only on confirmation of the appropriate Milestone in PS.
    Hope this helps
    Venu

  • Sent control cycles via IDOC

    Hi,
    I want to use the following IDOCs to execute the KANBAN process in an external system.
    Inbound SAP: CONF51 (for Kanban status)
    Outbound SAP: PKHD5 (control cycle) + PKHD5 (kanban) information
    How can I trigger that the outbound information is sent once a day?
    Using a job I guess that is checking what happend the last day in table PKPS. I want to put in 2 fields different information from other tables. How can I do that?
    What must be setup to sent out IDOC information from SAP?
    I already setup for testing via WE19 the following and it worked:
    - Partner system with the relevant outbound message types.
    Cheers
    Mathias

    Hi,
    I have the same requirement.Please tell me how to got it done

  • Error - control indicators for control area do not exist

    Hi All,
    When I am trying to hire a person and entering his personal data, I am getting this error:
    control indicators for control area XXXX do not exist
    Please help

    I'm guessing this error is out of the Coding Block check for Controlling.. ie the function call COBL_EX_CODINGBLOCK_CHECK.. put a break-point inside this function call & verify if any settings are missing..
    ~Suresh

  • BAPI /FM to create /change KANBAN control cycle

    Hi
    Is there any BAPI or FM to create or Change control cycle?
    Thanks.

    Check
    BAPI - BAPI_KANBANCC_ADDEVENTDRKANBAN
    Short Text
        Create Event-Driven KANBAN for Control Cycle
    Functionality
        With this method you can procure a material quantity for a control cycle. To procure this material quantity one or more kanbans are created in the control cycle and set to status EMPTY.
        The essential entry parameters are:
        o   Control cycle (if the function module is called as a method for the object kanban control cycle, this parameter is not available, but given by the object.
        o   Material quantity
        Information about the status change is issued.
        COMMIT and ROLLBACK WORK: the function module does not carry out any COMMIT work. Command off. This must be ensured by the initiator after ending the function module. Each time the function module is called, a COMMIT WORK must take place. It is not permitted to call this FM several times and to post the result with a COMMIT WORK. If, during the process,
        the FM comes across an error, in some cases the command ROLLBACK WORK wil be carried out. In these cases the kanban is either set to ERROR status, or in the parameter RETURN an error message is given.
    Hope this helps.
    Regards
    Vinayak

  • Enable Dual control function for FBZ2

    Hi,
    Its related to Dual control functionality for vendor master data.  I got a issue, if I change the sensitive fields for a vendor master and run F110, then it shows exception that vendor master not yet confirmed.
    IS it possible to post outgoing payment through transaction FBZ2, in this case?
    I have seen some transactions where the clearing document was posted by transfering the payable amount to intercompany or offsetting account and making payment later, without getting any exception, eventhough vendor master change not yet confirmed.

    hello, anisha.
    like you, i have also wondered what the payment block in the customer master is for.  after reading the documentation and asking an FI consultant, i gather that this block is apparently used to prevent automatic payment transactions for a customer.
    again, why anyone would want to automatically post payments for a customer is an issue i wish to explore.  perhaps this applies to scenarios where very many customers pay the exact invoice amount or have the payments guaranteed?  or perhaps to prevent automatic offsetting of a customer/vendor account?
    regards.
    Edited by: jonathan y on May 6, 2009 10:23 AM

  • User Exit for PKMC (Kanban Control Cycle)

    Dear Gurus,
    I need to know if there is a user exit in PKMC (kanban control Cycle) to create a extra tab next to the print control tab in the bottom.
    Best Regards,
    Kumar

    List of exits available.
    Enhancement/ Business Add-in            Description
    Enhancement
    MPKR0001                                Customer fields in kanban control cycle
    MPKP0002                                Customer-Specific Fields Call Interface
    MPKP0001                                Customer Defined Display in Kanban Board
    MPKD0001                                Kanban output as EDI
    MPKCCY02                                Customer Error in SumJC Control Cycle
    MPKCCY01                                User-Defined Fields in Kanban Control Cycle (PKMC)
    MPKC0001                                User exit for kanban calculation
    MPKB0002                                Customer defined display in kanban board
    MPKB0001                                User's own functions in the Kanban processing
    Business Add-in
    BADI_PVBE_UPDATE_APO      PVB Publish Changes to the APO
    MPKC_REQ_SELECTION           BAdI for Requirements Selection for Kanban Calculation
    PK_CALL_INTERFACE              Customer-Specific Fields Call Interface
    PK_CCY_SELECTION               Selection for Maintaining Control Cycles
    PK_REVERSAL                          BAdI during reversal of Kanban

  • Creation of control cycles for lean WH

    Hi All,
    Is it possible to create control cycles (backflush) for LWH, if so how?

    HI ,
    There is one more way to create control cycle.
    1. PK05 - create supply area ( earlier explained the procedure)
    2. PKMC - enter plant - go to change mode ( click on change icon ) - in the right hand window - you can see the create / copy icon.
    3.click on create icon
    4.select option - classic Kanban or event driven kanban
    5.enter material/ plant/ supply area.
    6.enter no of kanban / qty.
    7.In replenishment strategy - select appropiate option ( in our case it is stock transfer)
    8.enter - the tab will change from replenishment strategy to stock transfer.
    9.enter storage location.
    10.enter destination- storage type- bin
    11.enter if any additional data required to enter.
    12. save- control cycle will get generated.
    thanks
    Om

  • Vendor Master- Mass change to set block function 02 for selected PurchOrg

    Hello,
    We are using SAP 4.7.
    We want to do Vendor Master- Mass change to set block function 02 (T code- MK05 in block for quality reasons) for selected Purchasing Organizations to approximately 2000 number of vendors. I tried this using mass maintenance (T code XK99), but in this case block function of all purchasing organisations gets changed. We want it for certain purchasing organisations only. Kindly suggest the solution.
    In case I have to go for a development can you please suggest any functional module/ BAPI?
    Can I achieve this using mass maintenance functionality (XK99)?
    Waiting for your expert openion,
    Regards,
    Milind Dumbre

    Using the block function in XK05 will block the vendor for all purchasing organizations (as mentioned in the documentation of the field). What you can do is to use purchasing block for the selected purchasing organization.
    The field is LFM1-SPERM, and this can be done via mass maintenance using XK99.
    Hope this helps.
    Regards,
    Aroop

  • Control cycle for production staging SAP WM

    We currently have control cycle for kanban purchase orders. Do I need to create new control cycle production staging. Actually I will be using fixed bin for production consumption. Kindly confirm whether existing control cycle of purchase order can be used.

    Material Staging Indicator for Production Supply
    The material staging indicator defines the method of how needed materials can be supplied for production with the assistance of the Warehouse Management system.
    As with the location coordinates (warehouse number, storage type, and storage bin), the system files this indicator in the control cycle.
    The following staging types are supported:
    "1": Pick parts
    These materials are picked according to the required quantity specified in the production order.
    "2": Crate or kanban parts
    These materials are always removed from the warehouse in full cases. These can be ordered, for example, as soon as a case of needed parts is emptied in production.
    "3": Release order parts
    Release order parts are scheduled individually and the quantities are supplied manually to replenishment storage bins based on the requirements of production orders and the stock levels in the scheduled production supply areas.
    "4": Manual staging
    Materials are staged manually. For example, you can transport individual components using manually created transfer orders, or you can use the bypass method to transport them directly from the goods receipt zone to production. In goods receipt posting, postings are made to the production storage bins from the control cycles.
    "0": Not relevant to WM-PP
    These materials are not relevant to WM staging. They cannot be requested using the WM system.

  • Function for column validation in SQl Loader control file.

    Hello Gurus,
    We have an requirement to create a function to validate all date and number columns in control file, and return 0/1 accordingly to valid_column which is last column . I have developed the function which accepts the number and date type columns as parameter and return Y/N. My question is, is there any way so that the function could be created without passing any parameter to it?
    If yes, then how to call the function in control file?
    I have been searching since a while on Google to find out any solution but could find out.
    Using Oracle 11g Enterprise Edition Release 11.2.0.1.0
    Thanks!
    Edited by: Sush on Jul 5, 2012 2:23 AM
    Edited by: Sush on Jul 5, 2012 4:16 AM
    Edited by: Sush on Jul 5, 2012 7:28 AM

    Hi Srini,
    I have gone through this document and i couldn’t find out any solution. That’s why i was seeking help from you Gurus.
    Thanks for your help, i think i have learnt few new things abt SQL Loader by studying this document :)
    Thanks!

  • Trigger outbound IDOCs for EDI - CONTROL & APERAK messages

    Hello All,
    We have a scenario that customer transmits their EDI - ORDERS message and upon receipt of ORDERS, requires us to forward CONTROL and APERAK for any issues with ORDERS message. Checked different outputs and did not find suitable one. WIll appreciate, to know, the corresponding message/idoc types for CONTROL and APERAK and how to trigger.
    Thanks in advance,
    Renu

    Hi Nikhil,
    I tried the following Message Control settings for Message Type - PORDCR1 / Partner - SNC Logical System:
    a. Application = EF; Message Type = BAPI; Process Code = ME10 ; Change Indicator = Checked
    b. Application = EF; Message Type = BAPI; Process Code = ME11 ; Change Indicator = Checked
    c. Application = EF; Message Type = BAPI; Process Code = ABI_AIDN_OUT (the only option available in dropdown) ; Change Indicator = Checked
    I tried chnaing an existing PO after saving each of this setting. There is not outbound Idoc that is getting trigerred.
    Regards,
    Bharath

  • Control cycle for KANBAN.

    I want to cosume componenets using my KANBAN BINS.
    I maintained my supplying areas.  and when coming to the control cycle. Do I have to maintain control cycle for each component that I use in maufacturing against each supply area?  or is it only for FERTS

    Hi,
    1. When you tell consume compoenents means you are talking about Goods issue.
    2. Kanban needs to be done for a Inhouse prodcued material or externall procured material
    3. In both cases it does a Goods receipt and relevant goods issue posting.
    4. so if you only need to do consumption it is not possible.
    5. Genearlly it can be maitained for the FERT or halbs which has  bom, routing releavent master data
    6.For the inhouse manufacture kanban below is the highlevel step
    7. and wehen you do status cahnges like full to empty a planned order or prod order will be created.
    8. when you change status empty to ful then GR will be posted and GI will be done immediatelly ( based on the control cycle)
    9. Kindly refer the attached link for further details.
    [KANBAN|http://sap-pphelp.blogspot.com/2010/01/kanban-inhouse-production.html]
    also let me know if you have any specific querry
    Reg
    dsk

  • Customer block VD05, for SO customized partner function

    Dear all,
    Good day!
    I was trying to block customer using VD05, to ensure this customer will not be used in SD Transaction, SO, DO, Billing.  It works for the Sold to party, Ship to party partner function in documents, but doesnt work for the customised partner function for eg ZC - Consignee.
    Is there anyway to make blocked customers, cannot be used in customized partner function as well?
    Thanks in advance
    Kevin

    Hi,
    In your case, I would use userexits to check it in customer updation, SO documents, invoices and so on.
    I hope this helps you,
    Regards,
    Eduardo

Maybe you are looking for