Assigning of PR document types to Network and WBS Element to create auto PR

Dear Experts,
We have created Purchase Requisition document type as ZPRJ for Project system to create a automatic PR. When we run Project Builder the Auto PR will get create for Network by selecting the PR document type ZPRJ. But PR for WBS element instead of selecting ZPRJ it is selecting NB document type. Our requirement is whenever PR generate through Project builder it should create for doc. type ZPRJ.
Please let me know how to assign the ZPRJ PR document type for WBS Element. For both document type NB & ZPRJ we have maintain same number ranges but it should select only ZPRJ document type for WBS element & Network.
Thanks & regards
Dhanu

OPTT will help you.
Regards

Similar Messages

  • Assigning of PR document types to Network and WBS Element

    Dear Experts,
    We have created Purchase Requisition document type as ZPRJ for Project system to create a automatic PR. When we run Project Builder the Auto PR will get create for Network by selecting the PR document type ZPRJ. But PR for WBS element instead of selecting ZPRJ it is selecting NB document type. Our requirement is whenever PR generate through Project builder it should create for doc. type ZPRJ.
    Please let me know how to assign the ZPRJ PR document type for WBS Element. For both document type NB & ZPRJ we have maintain same number ranges but it should select only ZPRJ document type for WBS element & Network.
    Thanks & regards
    Dhanu

    OPTT will help you.
    Regards

  • How to create a new document type for PO and Requisition

    Hi All
    Can you please help me with the steps of creating a new document type for PO and PR. Also the steps that need to be update for the procure pay cycle to work properly. 
    Once the document type is been created. I want to create the PO referecing the new PR and PO document type.I am new in MM.
    Thanks, Ros

    Hi,
    1. You can create new PR and PO docu types at the following path:
    For PR docu type:
    First you need to create number range for docu type or you can use existing number range also. The path for creation of no. range is
    SPRO>Materials Management->Purchasing->Purchase Requisition->Define Number Ranges
    Then create PR docu type at below path and assign no. range to PR docu type here only
    SPRO>Materials Management->Purchasing->Purchase Requisition->Define Document Types
    For PO docu type:
    Follow same procedure as mentioned for PR docu type. Path is
    SPRO>Materials Management->Purchasing->Purchase Order->Define Number Ranges
    SPRO>Materials Management>Purchasing->Purchase Order->Define Document Types
    If you want to create PO referencing new PR docu type, link the PR docu type to PO docu type at below path:
    SPRO>Materials Management->Purchasing->Purchase Requisition->Define Document Types--> Link purchase requisition - document type
    Regards
    Chetan

  • Different Document types for Reciepts and payment-Cash Journal

    Hi Gurus,
    Please tell me how can we make different document types for reciepts and payments in cash journal and where we need to assign it??
    Please revert asap.
    Thank You

    Hi
    While posting the transactions by using FBCJ T.Code u can select the Receipts or Payments or Expenses then the documents will be genereted.  FBCJ02 is the T.Code for no.range there u can assign the no.range intervels.
    Shammi

  • Assign release to document type

    I have made release startegy for PR and PO . I want to now assign it to document type . What is the menu path.

    Hi,
    Go to CL24N 
    and select you release strtagy and here based on your Release stretagy settings like Class,characters and release code assign Document Type for the required characteristics
    check it you will get it
    with regards
    Shrinivas gangoor

  • Assignment of billing document type with accounting document type

    Hi
    I need one information regarding SD Billing Document type assignment with accounting document types.
       Here CRM people asking me where we can see if the Billing doc type is BV( Cash Sale)  accounting document should be RV
    Just go to T.Code VOFA for Billing document types. Based on this only system generate the Accouning documents RV, AB so onu2026u2026.
    But how it is determining this accouning document type they want to know.
    Pls advice

    In VOFA where it says Document type enter the FI doc type they want to post to. Otherwise it defaults to RV.
    pls assign pts to say thanks.

  • Retriggering Release strategy for PR with Document Type, Company Code and Price Range as Characaterstics

    Hi Friends,
    I have a issue to fix. The issue is releated to PR.
    There are some PR's in the system which has wrong release strategy picked up or wrong approvers picked up due to some congif change. now that the config changes are rectified correctly, we need to find a solution to correct the PR's which got affected due this.
    I have to retrigger the release strategy for all the affected PR's.
    The characterstics which we have consider for release strategy is Document Type, Company Code and Price Range.
    Can anyone suggest how can we retrigger the PR in bulk or individual to all the affected PR's, so that it picks up correct release strategy as per new config changes.
    Regards,
    Manjunath K

    Hi,
    Refer the discussion to triggers release again on release code addition/change in release strategy.
    release code is changed on PR release strategy - old PR can´t be approved
    Regards,
    Biju K

  • Overview fields used per document type in MM and FI

    Hello All,
    iIs there a possibility to get an overview of all fields used (mandatory, optional etc.) for each document type in MM and FI? I want to create a list which fields per document type are used in both MM and FI and which are only used in MM or FI.
    Thanks in advance for answers!

    Hi,
    You can point out all the fields with
    1) At the time of defining Screen lay out for purchasing (NBF) in MM for GR-IR Control.
    2) or you can tally which tables are conjugated with MSEG from SE11.
    Might this will clear you.
    regards,
    Ninad

  • Mapping of invoice document type in SRM and Backend

    hi,
    I need to map invoice document type in SRM and backend. We are in SRM5.0.
    e.g. when we create no PO invoice , we need to select document type from drop down  and that document type should be replicated to backend invoice document type.
    1. There is no list in drop down of invoice document type ( RE/RN)
    2. How it will be replicated to back end document type when enter document type instead of selection?
    If anyone came across this, pls let me know.
    regards,
    Rahul Mandale

    Dear Poster,
    As no response has been provided to the thread in some time I must assume the issue is resolved, if the question is still valid please create a new thread rephrasing the query and providing as much data as possible to promote response from the community.
    Best Regards,
    SDN SRM Moderation Team

  • Table for Cost Center and WBS Element.

    Hi Experts,
    i done the creation of Servcie Contract with account assignment category as Cost Centre "K"  & Project "P". Now i'm trying to take the report for this document.
    Plz help me, in which table the Cost center data and WBS Element data is stored.
    Regards,
    sudhakar

    hi!
    check the table T163K and the field is KNTTP.
    Reward if useful.
    Yuvi.

  • Down payment  request concept, Network or WBS element is mandatory?

    Dear All,
    To use down payment  request concept, Network or WBS element is mandatory? And without milestone billing can't use down payment?
    Regards,
    Srikanthraj

    dear
    it is not mandatory to have the Network or WBS for the billing plan .
    we will use Billing plan manually in the sales order with relevent Billing rule 4 /5 for milestone.
    regards

  • Report Painter Request - Cost Center and WBS Element

    Hi Everyone,
    Currently, my company settles all project related expenses through to a cost center by way of an internal settlement cost element (category 21).  The issue with this is that when the expense gets to the cost center, they lose all visability as to where the expense originated, such as salaries or travel expense (category 1 cost elements).  We can't switch the settlements to the originating cost element from wbs to cost center just because of the additional data/volume that will cause.  My thought was to create a report painter that can run by cost center but also show the wbs's that settle to that cost center and group the expenses by primary cost element (cat 1).  I'm assuming that there is a way to marry a cost center and wbs element by way of the wbs settlement rule but how would that be done for reporting purposes?  I've seen it done before by way of a nightly job that created sets based on the combination of cost center and wbs but I'm not sure how that was done.  Any advise and examples?
    Example:
    Cost Center:  IT
    WBS: A.0017.01.01 (settles to cost center IT)
    Postings made:
    1.  CC IT and CE 552000 "salaries"..............................$20,000
    2.  WBS A.0017.01.01 and CE 552000 "salaries"........... $5,000
    3.  Settlement of WBS to CC (expenses flow through to CC IT by way of CE 985000)
    I want to run CC IT and see that the account 552000 really shows $25,000 and can be broken down by cost object (CC and WBS by the amounts above)
    Thanks,
    Pete

    Hi Peter,
    I had a similar requirement and used report painter report group 1SHK-002 (in library 1VK).
    I took a copy of the standard and ameneded it slightly, I switched the explode so it occured on the cost center not cost element.
    The report runs so that direct costs on the cost center are shown at primary cost level. And values settled to the cost center are shown on the partner object. In your case i guess WBS Elements (Partner ObjType WBS).
    Now in my case I didnt need cost element breakdown on partner level, just on cost center so effectively I have(sorry for text alignment but I hope you get the idea):
    GL1   .............  100
    GL2   .............  250
    + Cost center1 total ....350
    GL3 .............   50
    GL4 ............. 100
    + Cost center2 total.... 150
    Primary Cost Total ..... 500
    X-YZ-1.200 .............   50
    X-YZ-1.400 ............. 100
    + WBS total ............. 150
    IO 1............. 100
    IO 2  ............. 100
    +IO total  ............. 200
    Partner Total............. 350
    Overall total .............  850.
    Its not exactly like your requirement but it might be a good report for you to work with to get what you need.
    Elaine

  • Relationship between tables milestone and wbs element

    Hi  Guys,
    1.I have taken two tables in my source code retieving milestone number(mlst_zaehl), usage(mlstn),and wbs element(pspsnr)
    from TABLE MLST and the other table is PRPS(WBS ELEMENT TABLE, and the fields are psphi(project) , and pspnr(wbs elemrnt,
    The problem is i am not getting the project (psphi)  FROM PRPS TABLE and the link field is PRPS-PSPNR = MLST-PSPNR.
    2.Other requiremnt is  in the same program, iam getting reservation quantity and also DELIVERY QUANTITY
    if delivery qty equal to reservation quantity then exit  and if the reservation qty is NOT equal to delivery qty,
    i need to UPDATE the corressponding USAGE , MILESTONE TEXT, AND QTY in milestone table MLST.
    please let me know any function to update milestone or BAPI or i sahll use BDC.
    Reagrds
    subbara

    Hi
    I think you want to link MLST and PRPS tables to get the milestone fields...
    From Table MLST - Mile stone number - MLST_ZAEHL and WBS element - PSPNR, link the WBS elements with PRPS table - WBS element - PSPNR and for project - PSPHI (Current Project Number).
    For project number you can take from PRPS - PSPHI or from PROJ table
    - Pithan

  • How to block reusage of archived Project definition and WBS element numbers

    Dear All,
    We have archived our projects using the TC SARA and the Project definition and WBS elements numbers no more exist in tables PROJ and PRPS etc.. When I now try to create a new project, the system proposes the next open number or allows to enter a number which is the same as one of the archived projects. But in our organization we cannot reuse the Project definition and WBS element numbers (even if it is archived) as a rule.
    Can anybody guide me what are the possibilities to block or avoid the reusage of the numbers of archived project definition and WBS elements in a fool-proof way? 
    Thanks and regards

    One Workaround:
    Use T code OPSJ and lock the project coding mask. Doing this you can not use this mask any more.
    But you want to continue using the mask but with different numbers. Not sure how this can be acheived. lets wait for others view
    Regards
    Sreenivas

  • How to do budgeting at activity level and WBS element level in project syst

    Dear GURU's,
    Can any one please suggest me how to do budgeting at activity level and WBS element level in project systems, friends please I required set by step process.
    I need how to do this configuration to map this scenario.
    Regards,
    Bhanu

    Hi Bhanu,
    Use this link :
    http://help.sap.com/saphelp_45b/helpdata/en/86/98853478616434e10000009b38f83b/frameset.htm
    after page opens , click on BUDGET MANAGEMENT , There you will find each and every step you want .
    Thanks ,
    Dhruv Kumar Malhotra

Maybe you are looking for

  • Audigy 2 ZS Platinum won't work with Windows XP Pro 64

    My system has both normal Windows XP Pro & Windows XP pro 64bit installed. The problems is that I can't get any sound on WinXp 64. The device manager has given me a "Code 39" on the "Creative Audigy Audio Processor (WDM)" device. This hasen't happene

  • Clearing a customers account.

    Clearing a customers account.  Is there any affect from not performing a clearing of the customers account?  Can this cause a block in the billing or block in the sales order creation?

  • Trim marks query urgent

    Hi all I have an assignment with the following dimensions flat 325mmx225mm includes trim size of 15mm at the bottom and 3mm on the RHS...how should I represent this in my artboard when exported to pdf to make sure they are visible? Thanks

  • Redeeming a voucher in a different country.

      I am British but have lived in Korea for the past eight years. I have an iphone 3gs so i installed iTunes on my wondows PC in Korea and listed my country as 'USA' to make sur eitunes displayed in English. Now I am back in England and I installed it

  • Controlling window size and positioning in RH8 WebHelp

    Evening all, I've seen a post before about controlling the size and/or positioning or RH WebHelp windows, but I haven't been able to find it again. I'm generating WebHelp in RH8 and at this point am using the default skin and whatever default tri-pan