Assignment of Material Component

Hi,
To which activity should we attached material component ( Stock and Nonstock)?
Please explain both for Internal Activty as well as external activity.
Muzamil

Hi,
To answer your question To which activity should we attached material component ":
Lets take an example:
Component "A" is being procured and dispatched to the customer. But before dispatching assume that there is a Factory acceptance test (FAT) for this material, so in your project there would be three activities with FS relation ship:
Procurement> FAT> Dispatch or the Shipment
Now you know very well that this material is needed for sure at the end of the procurement activity or at the start of the FAT activity.
1. Either assign this material to Procurement activity with Allign finish date on the general data tab of the Material "A"
or assign it to FAT activity with Allign start date on the general data tab of the Material "A"
2. So when you schedule the proecet the requirement date on the general data tab of the Material "A" is picked up from that particular activity.
Now to explain your question :When to chose the Stock and non stock:
1. If you wish to dispatch the material directly from the vendor to customer, assigne this material component--delete the procurement indicator and enter "N" as item categoty (Based on the configuration in OPS8) you wll have two options so choose third party order.
2. If you wish to dispatch the material after it is received in your own plant then chose "L" as item category and save it..
Hope it is clear now.
Reward point if found useful..Revert back if any more doubts.
Thanks.

Similar Messages

  • G/L is not automatically assigned to material component

    Hi All,
    We use transaction CJ20N in creating a meterial component, non stock item category(N), G/L is not automatically populated. Could you please tell me how does the system in SAP automatically assign G/L account in the material component. I have checked the valuation class for the material group and a G/L is assigned there but it is not assigning in the material component.
    Thanks in advance

    hi,
    yes i have checked the network profile and the g/l account is mandatory, therefore prompting the system for the g/l account to be assigned first
    also, the g/l account is assigned to the valuation class
    Edited by: UserID on Aug 8, 2011 8:09 AM

  • CN01 assign Material Component to internal activity

    Hello gurus;
    In transaction CN01 / CN02 can I assign only one Material Component to internal activity without Bill of Material (BOM)?
    It is possible? How can i do?
    Best regards,
    Mariano

    Virendra;
    Thanks for your response.
    I saw the SAP Help portal in [http://help.sap.com/saphelp_46c/helpdata/es/4c/227a7746e611d189470000e829fbbd/frameset.htm]
    and I must use a Bill of Material to assign material component. There is no other choice
    This is the point where I disagree with SAP, cause the client says that they use Operational Networks, cause it's more simple to assign components to activities.
    Best regards.
    Mariano

  • Bapi assign PO to material component

    Hello
    I am migrating some material components to a new project structure.
    I have created the new material components and the new PO (based on the old ones) but i do not know now how to link the material component to the PO.Is there any BAPI that does this?
    Do i have to first create a purchase requisition for this material component or how can i link the mat component to the PO.
    I have used  bapi's for creating material components and PO,so i would need also some bapi that could do something like that.
    Is there any bapi for changing material component ?
    thank you

    Hi
    before creating material components,we have to set the purchase requisition flag to "immediately" so that a purchase requisition is created immediately after material component creation.
    Afterwards i have read the newly created PR's and gave them as parameter to the bapi for PO creation

  • How to change material component for a Purchase Order?

    How to change material component for a Purchase Order?
    I need FM .
    PLEASE help

    Dear ,
    Create PO with item category L....There in Item detail you will get tab for material.
    There click in component Button, it will take you to the component screen there you can assign and deassign components.
    Hope this helps.
    Regards
    Utsav

  • How to create a Purchase Requisition for a material component in WBS or NW?

    Hello All,
    I have created a project with the following structure:
    Project Defination (Construction of Sub station)
          Main WBS
                   Level 1 WBS
                             Level 2 WBS
                                       Network for level 2 WBS
                                                      Activity  (Procuring Material)
                                                                 Material Component - MATXXX (Stock Item)
    Now in the above structure i have a activity where in i am procuring all the materails required to construct a Substation.
    So under this activity i have assigned all the materials which are needed to build Substaion.
    After i change the status of the project to release, there  a reservation created for the quantity of the material which i have mentioned in the material component under the activity.
    Now my querey is, how should i create a Purchase requisition for the reserved materail quantity in order to bring in the stock against the WBS / network / Project ?
    Awaiting your reply.
    Thanks and Regards,
    Sudarshan.

    Hi Sudarshan,
    In your case you can run Me5J to check the list of PR created against your project.
    Then Create PO and similarly you can check list of PO in Me2J.
    Then followed by GR and check if any GR release exist in MIGO. Then once after doing GR you can check the Material in Stock which will move material from Unrestricted stock to Project Stock which you can check it in MMBE.
    Then you can do the Good Issue in MIGO itself and run MIRO to complete the cycle.
    Regards'
    syed

  • How to activate price tab in material component

    Dear All,
    Actually i need to assign price for my issuing material, but i am not able get the price tab in material component its only showing general data here i able to assign the quantity. I need help for how to activate the price tab.
    Regards,
    S.Suresh.

    Hi,
    if you take non stock material component ( item category as "N") then system allows you to change the price.
    for this click on material component then, click on Purch.data tab...here you can chnage the price.
    But this is not happening with stock material ( item category as "L").According to me this will not happen with stock material.
    sandeep

  • Material component in created status

    Hi,
    The n/w is released also activity is released but the material component assigned are still in created status. PR,PO and GR for the material done but GI not allowed because of this status movement allowed is untick.
    Please suggest.

    Hi,
    Thanks for your reply ..
    the material component status in cj20n is created not released where as the activty is released. Procurement for the material is allowed but since the material is in system status created movement allowed is untick and hence GI not allowed.
    Regards

  • Assignment of material to sub-operations

    Hi friends,
    Please tell me whether we can assign a item from the BOM to a Sub-operation?
    I tried to assign it but it is getting assigned to the main operation only?
    please throw some clarity on it.
    regards
    Ramesh

    Hi,
    A sub-operation is used when a detailed planning of the process to be done in an (main) operation is required. The material component is assigned to the first operation by default.If you want to assign the component to a different operation then you can use component allocation tab.
    Hence, there is no need to assign the material to a sub-operation since the main operation is already assigned a material.
    Hope this helps.
    Regards,
    Senthilkumar

  • How to Assignment between Material and Account Assignment Group

    Hi,
    When we are creating a sales order with material ABCD, then in material line item -->under Billing Document Tab --> in Accounting screen, there is field Acct asgnmt grp (Account Assignment Group).
    From where we can assign between Material and Account Assignment Group, after that it automatically pick in sales order creation.
    Please guide..

    Please refere to below link it may help.
    Re: how to configure new account assignment group of material
    Thanks Dev.

  • Need to restrict view of DIRs assigned to material, vendor, and customer

    Hello,
    SAP standard, version ECC 6.0. Different plants in use with requirement for differnt authorizations.
    I know that DIRs can be assigned to material master. However, the problem is that it's client level data. Now there is a need to implement DMS with materials, vendors, and customers.
    Problem is that company operates in different countries and with different plants. One material/customer/vendor is created and then extended to cover different plants.
    Material 1111 has a specification assigned to it, e.g. document type ZSP with DIR 1000001111, this document is at client level.
    Person A from plant 1000 can display and maintain it (1000001111) but person B from 2000 must not see this, she has DIR 10000011113 instead (and person A should see this).
    If person A has authorizations which are limited by the plant type because of the usage of MM already, do these restrictions apply also to DMS? I haven't found a definite answer for this.
    I cannot set a authorization object based on document type and maintaining different uthorization groups is the last option because of the vast number of  users.
    The same question is for customer. if there is e.g. a contract assigned to customer, can the view be restricted by distribution channel or another field provided by SD (standard solution).
    Vendor master is the 3rd major issue. How to limit access to documents?
    Help is highly appreciated.
    Thanks in advance,
    Pia

    Hi,
    Can you please elaborate what is the object you mean. I have serious problems with system and cannot check it.
    Thanks,
    Pia

  • Use of field "design documents assigned" in material master

    hi,
    kindly help me to use the field "design documents assigned" in material master. whenever i creat material master (MM01) in basic data2 view this field comes with grey/black No Link indicator. how to use this and for what .
    regards
    roshan s.

    Hi Roshan,
    Insted of using this field u can assign Document directly to the Additional Data tab.
    TO attach the document to Material Master go to Additional data ---> Document data, assign Document.
    You can confirm it by pressing F1 key by selecting that Field.
    Regards,
    Dhaval
    Edited by: Dhaval Choksi on Jul 10, 2008 3:26 PM

  • Material component

    HI All,
    I selected a material component with item category "L" and procurement type "Third party requisition for WBS element" and then created PR from project builder. then created  a PO and rreceived the material into stock.
    now i can see the material in stock with the corresponding WBS Element.
    when  i tried to create a delivery through CNS0 then the material (line item) in the delivery becpomes not relavent for GI and could not issue out the material to customer. I checked the delivery and found that the movementnt type 281 was not copied into the delivery, so i could not issue the material.
    my question here is, whether the combination item cat "L" and procurement type "Third party requisition for WBS element" is correct?..if not then in CJ20N system should not have allowed me to select this combination.
    i assume the "N" with "Third party requisition for Network" is correct. But i would like to know reason for my earlier issue.
    is there any solution for this? please help.
    Thanks
    Diva

    Hello
    Do you get unrestricted project stock in MMBE once you make GR?
    In CNS0 you make a delivery from project for goods to the customer and unrestricted project stock is mandatory.
    For this you need to create reservations in the project for the materials which you want to deliver.
    I'd suggest to try for item category L and "PR+Reservation" scenario.
    Hope this will help you
    Regards
    Ashish

  • Cost of Material Component

    Hi experts,
    I am not able to view the cost of material component in Structure overview report...but i am able to see the cost of the activity , WBS element...I wanted to see the cost of material component also..pls tell me what is to be done?

    Hi ,
    Go to the network header select Control tab , In selection tab Costing put following parameters,
    Costing sheet PP-PC1,Costing varian plan PS02 costing variant act. PS03,Plan cost calc 2.determine plan cost.
    save the project and reopen and check for planned cost.System will get material cost from material master.
    Rgds

  • "No valid material component found" when Routing upload using LSMW RCPTRA02

    I want to upload routings through LSMW RCPTRA02 incluing routing headers, sequences, operations and component allocations. But systems appears error CM 101 "No valid material component found" . Does anybody occurs the same error before?
    The materials truly exists in BOM component.
    Sincerely thanks,
    Alina

    Hi,
    What is the status of the BOM? There should not be any problem if the material BOM exists.
    Regards,
    Krishnendu.