ATD Check Issue in creation TLB Order Manually in Planning Book.

Hi ,
I am facing issue in ATD Check in TLB Interactive Planning while creating TLB Order Manually.
Here goes scenario.
I am creating TLB Order Manually in TLB Planning Book with below Information.
  Demand Date u2013 02.01.2012 ( Todayu2019s date ) & Qty u2013 20
Considering Lead Time of 10 Days to supply from Plant to Depot, Delivery Date in Purchase Order is calculated as 12.01.2012
Now I do outbound delivery for this PO in ECC. As client is not using Routes Transit Times functionalities, Planned Goods Issue Date for Outbound Delivery in ECC is calculated as Delivery Date from PO which is 12.01.2012 minus Transit Time in Route which is maintained as 0. Hence Planned Goods Issue Date in ECC is 12.01.2012.
This is same as Requirement Date for Outbound Delivery. PGI for this delivery is yet to happen. When PGI is done then issue is resolved.
When this Delivery goes in APO, it has requirement date as 12.01.2012 and now when I create TLB Order in Interactive Planning Book manually it allows me to create TLB Order of 20 qty extra before populating below message
u201CThere is only an ATD quantity of XXX available for product GHECP02u201D
In short it allows me to create 20 extra PO as Outbound Delivery is shifted to future bucketu2019s and  hence is not counted in ATD Issues.
I am using Daily Bucket Profile in TLB Planning Book.
If I use Monthly Bucket Profile my issue is solved but again when client is creating TLB Order , by default system picks first date of bucket which client does not want.
Is there any way where in I can avoid this excess PO Creation. When it checks ATD Availability it should consider these outbound deliveries which are of future dates.
Regards,
Sameer

Hi Sameer,
Such kind of issues would come when  master data/transaction data in APO and R/3 are not in sync.
You could go in for some custom development for TLB orders, but it's like opening a pandora's box as you are messing with teh standard working of system. It could create data inconsistencies between APO and R/3 and I would not really advise this. It's best to maintain all the relevant master data/transaction between APO and R/3 in sync.
Better ask your client to maintain the relevant routes as required. Otherwise they should create PO directly in R/3 as required.
Thanks - Pawan

Similar Messages

  • How to see Live cache order number in planning book of APO ?

    I am trying to see the Live cache order number in Planning book by entering getio as T-code while in planning book.
    By this I am not able to see the LC details. Can anyone help me out on the same?
    Edited by: Wilian Segatto on May 16, 2010 2:52 PM

    Dear Rahul!
    Are you using correctly the transaction GT_IO? As per your first reply you are using GETIO.
    Try GT_IO!
    Will

  • How to Create one TLB Order manually with multiple deployed STR's

    Hello,
    We are currently facing an issue when trying to make a TLB manually by right clicking on the deployed STR's.
    APO generates multiple orders for each item.
    Business requirement is to generate one TLB Order.   
    For example there are 10 Confirmed STR's and the  planner wants to choose the deployed STR's manually from the list of 10 products.   When we right cliick and select each product (for either partial or full ) it moves to the TLB order, but generates multiple orders.
    Is there a way to restrict the requested lines to be in one Order?  So that when the order is CIFed to ECC, there's only one STO generated with multiple lines.
    Regards,
    Bhavesh

    Hi Bhavesh,
                   By manual TLB process only you can create stock transfer order with SINGLE line item. because your deployed STRs always will have single line item and you are selection one by one and converting manually. in STD process you can not club items manually...
    Yes it can be very much possible by automatic TLB run. it will take all the deployed orders and converting as TLB order by considering TLB profile where min , max limits maintained. also there is concept if you maintain loading group in product master based on that materials will be grouped together.....
    Clubbing items into one order is done by TLB heuristics.. but when you do manually you are deciding how to do it?....
    You can do one thing... after creation of TLB order with single item..you can edit and include some more items manually. Accordingly you need to delete deployed STRs.......
    If you want to automate this then you need to look out for BADI... not sure possible or not
    Regards
    Thennarasu.M

  • Creation of Order in DS Planning Board (/SAPAPO/CDPS0)

    Hi all,
    My requirement is i want to create order manually in DS planning board by passing product, location,resource,runlength etc.
    Again i am using PPM to calculate the setup time (between previous order and the current order).
    In order to get the PPM data, i am calling FM "/SAPAPO/DM_PPM_GET_PLAN" and here i pass planid to get the details.
    To get planid, i call FM "/SAPAPO/SOS_FIND" i.e. to get source of supply information which includes planid
    Please tell me
    (1) what is planid ?
    (2) How planid is this linked to PPM ?
    (3) What do we mean by sources of supply? Can't we get the same info from pegid ?
    (4) What is the structure of PPM ? I mean what are activities, components, alternative components etc.
    Regards,
    Deb

    Hi Nandha / Vikas
    Thanks for your input.
    I am summerizing the whole concept, Please correct me and answer my questions in between :-
    In order to create an order in DS Planning board manually, we need information like product,location,resource,quantity etc. (User's input).
    Then we should follow the steps as follows -:
    Step 1 :- Find Sources of Supply
    Since this gives information like how we are going to produce or procure the product. It can be PPM or PDS or Transportation lane.
    For PPM we will get the Plan id (Unique ID for PPM) and then we will get the details of PPM accordingly.
    But, Please mention what about PDS and Transportation lane ?
    I mean from source of supply how can we know that the product can be produced or procured by PPM or PDS or Transportation lane ? Any field indicator is there for PPM or PDS or Transportation lane? Because in my requirement, First i need to check which one is active for the entered product:- PPM or PDS.
    (2) Once we know that the source of supply is PPM or PDS or transaportation lane, then we will call different FMs to get the details.
    For PPM we know how to proceed. I mean using planid we can get the details.
    But for PDS and Transaportation lane please mention the FM name and i/p parameters to get the details like setup group id, production rate etc.
    Thnaks once again for your valuable inputs.
    Deb

  • Inconsistency in Sales Orders Assignment in Planning Book

    Hi Experts
    When i create sales Orders in ECC,sales orders are assigned  to the Planning Book but some times when i change the Quantity for the existing salers Orders , Changes are not getting reflected in the Planning Book Immediatly.
    Some times system is giving pop up like 'sales order does not exist'.
    When i delete existing sales order in ECC, the incomming Qty in Planning book should be changed to zero, but its not reflecting.
    What measures we need to take to prevent such inconsistencies?rds
    Thanks in Adavance
    Regards
    Vasu

    Hi Vasu,
    In general, the above are product allocation consistency checks which
    checks the following
    These will display the confirmation date, quantities, used product
    allocation settings, sales order , product etc.,
    1) Checks if is there any single assignments without an incoming
    orders quantity
    2) Checks if is there any single assignements without a sales order
    due to error
    3) Checks if is there any single assignements without a characteristic
    combination in place.
    SAP recommends to check the affected sales orders again.
    Regards
    R. Senthil Mareeswaran.

  • Credit check issue in third party order

    Dear all,
    We are facing some issues related to credit management data for one of our customer. I need your valuable inputs for below mentioned queries-
    1. As a genaral question- When we releases a SO through VKM* How the system calculated the " Released Credit Value of the document".
    2- For one of the customers, the FD33 shows a Sales value X USD. As i see the split of this sales value , this X USD amounts to OPEN DELIVERIES. Both Open So and Open billing are zero. We tried to check with no. of tcodes to find out the open values but no such Open delv document is appeared.
    In VC/2, it only shows Open SO, no open deliveries are there.
    So i tried with simulation program RVKRED88, and found 5 third party Sales documents , against which some value is coming under the Open delivery value and it sums up to the value as coming in FD33.
    I have a few questions on this-
    > All the SO in output are Third party SO, against which PO has been created, ( Third party So> PR> PO> MIRO--> billing) and all are in status OPEN, so how come they are showing value in OPEN DELIVERY ?
    --> The value appearing against these third party SO is Not equal to items value/net value, it is a complete different value than appearing in SO. But in SO changes history , the same value is coming AS RELEASED CREDIT VALUE. How is it being calculated?
    For eg- for one of the Third party SO , the value coming in RVKRED88 is 29573.53 USD,
                                                                net value in So= 24,120.00 USD, Qty = 6000 PC , Credit price= 4.02 USD
                                                                Credit value of So in VBAk= 29573.53 USD
                                                               SO created , released on 08.July.2011, confirmed schedule line =08.Oct.2011
    Credit settings- Static check + Credit active Item cat and SO ,  Open So and open delv are ticked in credit settings.
    Kindly help in the analysis.
    many thanks in advance for the inputs.

    Hi Dharmendra,
    1.  When we release a sales order using VKM* transaction S066 information structure and OEIKW field is updated which increases open order value.
    2. If there is mismatch in the values of credit related fields run RVKRED77 (Re-organisation of credit in case of update errors) this will update all the credit data for a Payer customer in real time. RVKRED88 is simulation mode.
    3. Updating of values related to credit is controlled by the update group assigned to credit control area. If system is not able to update  using the assigned update group it will automatically try updating using the next update group. Below is the text of SAP Help.
    If a document cannot be processed with the update group you specify, the system determines the next possible update it can carry out. For example, you select Update group 000012 which, at delivery, reduces the open order value and increases the open delivery value. Assume that one item in the order is not relevant for delivery. In this case, the system automatically determines Update group 000018 for this item. Update group 000018 increases the open delivery value for the order item. The system uses the confirmed quantity of delivery-relevant schedule lines to update the order value
    As you know in OVA8 transaction credit control area, Risk category, credit group and currency are assigned to update group.

  • Manual Creation of Production(confirmed) in Planning book

    Hi Experts,
    I just want to ask if in case I manually enter a production order quantity for a certain material location in Production(Confirmed) key figure, would it automatically populate dependent demand quantity on components?
    I understand that if production order comes from SAP R/3 and CIF to APO, I will have both production order and dependent demand in palnnign book. But in case production order is loaded from an external file or manually entered, would it also gives me dependent demand? Thanks.
    Regards,
    Mylene

    Hi Mylene,
    I agree with Virender (who seems right quite often actually )
    I think you are approaching this the wrong way: you cannot create a SNP production confirm; and will never be able to...
    However, you can create a produciton confirm order via interface; and , providing you do that properly, your order will be visible in SNP, both in produciton confirm and dependant demand.
    I hope it make sense.
    Where you need to concentrate your effort is on this interface.
    You will probalby need interface to create PDS / PPM and to create comfirm order.
    I am not an expert here, but I guess the best is to use bapi (e.g  "PrdDataStructureAPS" (BUS10014) or "ProdProcessModelAPS" (BUS10003 / "ManufactOrderAPS" (BUS10503)
    Thnaks and Regards
    Julien

  • Identify Orders created manually in the planning book (user exit macro?)

    Hello All,
    I am trying to capture the orders created manually in planning book using a user exit macro!!.
    Does anyone have any Idea of how to acheive this. Main aim is to identinfy orders created manually.
    Thanks in advance,
    Regards,
    -Srini

    Hi,
              There are no change pointers like R/3 in APO due to the live cache technology. You can how ever findout if an order is created by system or manually created. Check this [thread|Re: How to identify an order generated by heuristics run or entered manuall]
    Check if you can use the BAPIs to read orders and see if they have "output-firmed".

  • Show Sales orders, STOs, & Deliveires in SNP planning book by Shipping Poin

    We are using ECC 6.0 and SCM 7.0.
    We have a requirement to model the Shipping point as a location in SNP. By this functionality we want to show Sales orders, STOs, & Deliveires in SNP planning book by Shipping Point in addition to Delivering Plant which is default now.
    When I create Sales Orders in ECC system always perform shipping point determination and passon to APO per schedule line via CIF. These Sales Orders always show up in SNP under delivering plant/location. We also want to show them under Shipping Point location.
    Here is what I have done so far:
    1. I have created a CIF integration model for all required shipping points and CIFed over to APO. These locations are showing up in SNP planning book.
    2. I have created Sales Orders and verified the shipping points are determined correctly and sent Sales Orders to APO successfully.
    3. I see all the Sales Orders in SNP planning book at delivering plant/location.
    4. But I don't see any sales orders under shipping point. They also don't show in RRP3 screen.
    5. If I create a forecast in RRP3 at Shipping Point location they show-up in SNP planning book at Shipping point location.
    Any idea how to model shipping points in SNP for planning?

    check what the ATP order type is of these orders are (from RRP3)
    then check what ATP group these order types are assigned to (from SPRO)
    then in the SNP Planning are make sure the Keyfigure you want to see them in refers to the ATP group from above
    Which planning book are you using? Is it a standard book/ copy of a standard book? What KF are you expecting to see it under... the standard book has KF for planned production that will be same as your PPDS planned orders

  • Warranty return order type availabilty check issue

    Hi,
    I am using a special order type (ZZZ) in SD for the warranty returns. When I create the order type ZZZ I assign an order number and the items to be return.
    Issue:
    For the items that in the original order where confirmed by a RBA Check logic, I am having problems with the ZZZ order type. For example:
    Original order
    Product A  10 PC order - I got 5 of B and 5 of C confirmed (product substituions)
    Order ZZZ
    When I select the order and item above I got 10 PC of product A confirmed; and B and C nothing confirmed.
    Note: Order ZZZ should work as the original one. What can be wrong?
    Thanks a lot.

    Hello,
    Usually ATP check is disabled for returns order and hence whatever quantity is enterd in order will usually get confirmed since ATP check cannot happen at customer level. You can verify this with item categories and scheduline categories for ZZZ order type.
    If ATP check is enabled then it there may be some change in scope of check for these orders.(user exits).
    Regards
    AP

  • ATD check in TLB does not consider the SNP checking horizon

    Hello
    I would like to know which BADI or Exit is available to change the available to deploy check logic when the TLB is run.
    I would like to take into account the SNP checking horizon.
    Thanks
    Virginie

    Hello Virginie,
    I know this post is very old but I chanced upon this thread in SCN and am
    interested in your solution to add a Macro in a specific planning view tor a specific location to force ATR to 999999 and ATI to 0.  Would you be kind enough to tell me the steps to do this?
    Will this require me to create 2 new key figures with a Fixed value (example ATRF with a fixed value of 99999 and ATIF with a fixed value of 0) and then in the planning view, create a macro and set ATR key figure = ATRF key figure and ATI Key Figure = ATIF key figure?
    Can I just go to the specific planning view and fixed the value of ATR there to 99999 and ATI to 0 without having to create new key figures or macro?
    Again, will appreciate if you can provide me the step by step of how to achieve this.
    Thank you in advance!
    J

  • Hard Check During Delivery Creation

    Hello Experts,
    Need your advice. I am stuck up in a enhancement issue during delivery creation. i am working for passenger vehicle company.
    Back ground Info.
    the company procures chassis from vendor & builds bus body over it. there are various types of chassis & each is uniquely identified in SAP by Material No. & also mentioned in BOM created for bus. when chassis is received , equipment is created using T-code IE01. After this one more equipment is created for bus which is called BBD Serial No. The equipment for BBD serial no holds chassis serial no. My issue is at the time of creation of delivery using T-code VL01N the user puts the BBD Serial No manually in a dialog box provided, This BBD Serial No is not capturing in the importing structure IT_XLIPS of BADI "LE_SHP_DELIVERY_PROC" Method "Delivery_Final_Check".
    I have to put a check during delivery creation for consumption of Chassis , if the Chassis is consumed during production phase a Mat Doc will be generated with movement Type 261. As such we don't knew the Mat Doc for Chassis Serial no Consumed during prod phase. so to derive chassis no in the BADI against which we have to check for it's consumption. The user provide BBD Serial no in a standard dialog box in VL01N.
    Can we use Field Exit for this or any other BADI Should work.
    Best Regards
    Priyesh Shah

    Hi Priyesh,
    Below steps may help you to get the value of the standard dialog box provided in the screen.
    1. Find the field name of the standard dialog box provided in the the screen for BBD Serial no.
    2. Implement below code in the BAdI "LE_SHP_DELIVERY_PROC" method.
    FIELD-SYMBOLS: <fs> TYPE BBDFIELDTYPE.
    ASSIGN ('(SAPMV50A)BBDFIELDNAME') TO <fs>.
    Now the field symbol <fs> will hold the value passed in the dialog box.
    Please try and let me know if it is working or not.
    Thanks
    Gangadhar

  • Automatic Service Order creation and OBD line item creation - Repair Order

    Hi ALL,
    I tried to run the Repair process based on the help document of SAP:
    Configs Followed:
    1) In Material master MRP3 view, strategy group is assigned as 84 (service orders). By default this str.grp is linked with Requirement type SERA and Requirement class 203.
    2 ) Requirement class is assigned with appropriate Service order type.
    SPRO>Sales and Distribution>Basic Functions>Availability Check and Transfer of Requirements>Transfer of Requirements-->Define Requirements Classes (OVZG)
    Actual Assignment:
    Reqt. Class Service Order Type
    039 SM01
    203 SM01
    3) Task list is assigned to your Service material - Service product - OISD
    Actual Assignment:
    Service Pdt Work Centre Plant B Area Gen TL Group Counter Task List Type
    R-1001 PC-SERV 1200 8000 62 1 A
    4) Check the Requirement class setting indicator for configuration (cnfg)
    Actual Assignment:
    = mandatory
    5) SPRO>Sales and Distribution>Basic Functions>Availability Check and Transfer of Requirements>Transfer of Requirements-->Define Requirements Classes --> Determination Of Requirement Types Using Transaction
    Actual Assignment:
    Item Category Reqt class Reqt. Type
    IRRS 039 SE
    IRRE 203 SERP
    IRRP 203 SERP
    IRAL 040 KE
    6) Sales and Distribution>Sales>Sales Document Item-->Assign Item Categories for determining the item category based on usage
    Actual Assignment:
    Sal. Doc. Type Item Cat. Group Item Usage H. L . Item Cat Item Category
    RAS NORM IRRS
    RAS NORM R101 IRRS IRRE
    RAS NORM R102 IRRS IRRP
    RAS NORM R103 IRRS IRAL
    Errors Faced:
    1. Service Order is not getting created automatically.
    Error in SAP - IDES :"A service order has not been found for action 'Repairs'"
    2. Also im not getting the automatic creation of the 4th line item(Item Category - IRAL) in the repair order, which in turn stops me from creating the Outbound delivery.
    Please HELP !
    Regards

    Hi PeteA,
    Sorry, here it is...
    Let me explain the process that has been followed:
    1) Initially to start with Service Notification was created with IW51 T-code.
        In that, Sold to party and material # were entered. Then from there directly i go for Create Repair Order from the Action Box.
        Order type for repair order - RAS, and when i save both Service Notification and the Repair gets saved.
        Now, in the repair order, two line items were getting created automatically and the requirement Types for those line items are:
        Line Item I : SE
        Line Item II: SERP
    2) After that i take the material in with the help of t-code VRRE.
    3) Then, i do the acceptance of the stock ( Technical Check) with t-code QA11.
        Once i do that, i get the Third line item in the Repair Order and the requirement Type for that line item is:
        Line Item III: SERP
    Now my query is, Once i do the QA11 transaction i need to get a Service Order automatically but thats not happening.
    Also if i create a Service Order manually, and do the repair and do the technically completion of the service order, then i need to get a third line item (IRAL) in the repair order automatically and thats also not happening.
    Regards

  • COGS issue in the sales order

    Need your help to resolve below issue.
    A sales order is created with multiple line items. The user created delivery and invoice document for one of the line item in the sales order. The line item cost was active in the sales order and invoice document. The value was determined from the material master record.  The user then created delivery document for other line items in the sales order, but invice document creation ends with an error message that "Sales order is incomplete so billing can not be carried out" VF 069
    The first invoiced item has become inactive in the sales order now and the sales order goes into incomplete status. The system is blocking the invoice document creation for rest of line items. Could you tell me why the line item cost became inactive. Also tell me how to resolve this issue.

    I dont think,
                   There is any problem with Cost in Sales order line item.
    Cost copied from MMR is statiscial & always in display mode.
    Goto VA02- key in order no n press entere.
    now from menu bar- Goto- Edit - Incompletion log ( Cntrl + F8).
    if any field is missing , then maintain the field  to complete the sale sorder.
    incompletion log will be maintaiend @ order n item level. check in Item category for the incompletion procedure & check the fields maintained in incompletion procedure in Tx: OVA2.
    Regards,
    Reazuddin MD

  • Issues with printing purchase order

    Dear friends,
    I'm having some issues with printing purchase orders.
    Normally when I create a purchase order via ME21N and then when I save the purchase order it then gets automatically printed.
    Suddenly it is not anymore working. I have created a purchase order this morning and it did not get printed. I get the message "frontend is not available"when i check the spool in SP01
    The funny think is if i call up the spool nr via SP01and then do a reprint then i'm able to reprint.
    What can be possibly the issue that I can't print the purchase order when I create the purchase order via ME21 when I save the purchase order? Can you help me with any guide on where I need to check why the PO is not printing immediatelly when i create the PO via ME21N?
    kind regards,
    Camilla

    hello all,
    thanks so far for your reply.
    i have checked today my user settings and that shows that my prints should go to LOCL (local default printer)
    The output conditions fpr purchase order have also LOCL (local printer)
    The weird thing is that I can print other reports to the default printer without any issues. The issue arise when I create a purchase order via ME21N. Normally when I save the PO it automatically prints. So no manual print instructions are required from my side. Because if I give manual instructions then I'm able to print the purchase order.
    Is it possible that the automatic printing is switched off and that it only prints when I hit manually the print button?
    Is the automatic printing something that is maintained in SPAD?
    kind regards and thanks for your help sofar

Maybe you are looking for

  • Adobe Illustrator CC not smooth on MBPR hi-end

    Hey, I just bought a MBP Retina 15" high-end (i7, 16GB RAM, SSD 512, GeForce GT 750M 2GB) perfectly clean install with Photoshop and Illustrator CC updated. This is terribly choppy (scrolling / navigation / zoom / unzoom), even when creating a new do

  • Letter case in SAP import manager

    Hi, We are facing a strange issue with SAP import manager. we have the value 'n' for a field in XML file. when we tried to open the XML file through import manager, in map/value fields tab, the value is showing up as 'N' for that field where as it is

  • Problems attaching an external style sheet to several HTML files created with a template

    Hello All; I've been working on a task that should have taken me a few minutes but instead, it's been taken all day. I am creating a site using a template and out of the template, I've created about 6 html files each of which is a different page off

  • DEP error on CS2 in Vista

    I've done some googling and troubleshooting but can't seem to find a fix for this. We've recently "upgraded" to Vista at work. We run Photoshop CS2 (with unfortunately no plans of upgrading in the very near future). Installation of CS2 appeared to be

  • What do I do if I forgot my answers to my security questions??

    What do I do if I forgot my answers to my security questions??