ATP check with RLT - rescheduling keeps pushing confirmed date out???

In order entry, our availability check is looking only at inventory and RLT... so that if stock is unavailable, the line item gets confirmed for a future date based on the material's RLT. We have noticed, however, that every night when backorder rescheduling runs, the confirmed date is pushed out one day later (assuming that no inventory exists still). So it appears that BO rescheduling is recalulating the confirmed date based on the current date + RLT.
Does this make sense? Is there any way we can make the original confirmed date stick? We don't want to use the Fixed Date & Qty flag on the schedule line screen, because we want to be able to pull the confirmation (and delivery) in earlier if the inventory is available earlier... we just don't want it to keep getting pushed later.

This boils down to a business question.
Say you have a material with a 30 day RLT.
On Day 1, an order is placed - and due to no stock or planned receipt of stock with the 30 days - the delivery date is moved out 30 days based on the RLT.
Now it's day 29, you run the backorder report and there is still insufficient stock / replensihment plan within the next 30 days.
==> Do you want to keep the promised delivery date of day 30 - or is day 59 more realistic?
More to the point, why hasn't stock been acquired or a replenishment plan / order been created in the previos 29 days?
The RLT shouldbe set so that there is a very high likelyhood that the order can be fulfullled ini that time line.
To me, it makes sense to keep pushing out the date. When stock actually shows up in sufficient quantity, the date will be moved back up.

Similar Messages

  • ATP check with including puchase order

    when we create SO with ATP check to reserve the qty of the currenct stock, we also want to know the future qty of purchase orders so that we can clearly know the supply and demand of these materials.
    so we use ATP check with including purchase order, that users can reserve the qty of open GR purchase orders.
    but when the status of that PO changed, the reserved qty before won't have effect, and can't create outbound delivery either.
    there are two examples below:
    1. there is one SO reserved 10 material qty of the open GR PO, which it's scheduled delivery date is 5/15. but this PO still hasn't  goods receipt until 5/17, cause ATP check rule is "Include future receipts only" ( if "Receipts in the past as well as in the future" is set, it will be confused with current stock qty), so these 10 qty won't have effect and the ATP qty is now a negative. we should only reserve again by t-code V_V2, otherwise all the reserved qty can't be deliveried.
    2.there is one SO reserved 10 material qty of the open GR PO, which it's scheduled delivery date is 5/15, but when the delivery date of confirms tab is updated by vendor, these reserved qty before will also be invalid.
    please tell me how to resolve these problems?

    Hi,
    If the business wants to confirm the sales order quantity against the incoming purchase orders, then this always happen. The issue can be resolved only by rescheduling the sales order by running V_V2 everyday.
    Alternatively you can suggest the business to exclude the purchase order from availabilty check(AC)  in t.code OVZ9 and include shipping notification in it. When the vendor sends some materials confirmation, the purchasing can add the shipping notificatoin details in the purchase order and can create Inbound deliveries for goods receipt. By this way, only when the vendor ships the goods, the quantity will be taken into AC.
    Regards,

  • Rule based ATP check with SOA

    Hello,
    We wish to implement ATP check using Ent Services.
    Details:
    Environment : SAP ECC 6.o with Enhancement Package 3/ SCM 5.0
    Ent service used: /SAPAPO/SDM_PARCRTRC :  ProductAvailabilityRequirementCreateRequestConfirmation
    We were able to carry out Product check using the service. However we are unable to carry out rule based ATP check using the same service.
    We have carried out the entire configuration as per SAP's building block configuration guide for Global ATP & SAP Note 1127895.
    For RBA <Rule based ATP check>, we are getting the results as expected when we create Sales order from SAP R/3 (Transaction VA01), however ATP simulation in APO & Ent service does not give the results as expected. When we carry out ATP simulation in APO / Ent service, results are same as Product check & not as RBA i.e. they respect only requested Product location stock & does not propose alternate Product or Location in case of shortages
    Plz share the experience to fix the issue
    Mangesh A. Kulkarni

    Hi mangesh
    Check this links , not very sure , but may help you...
    https://www.sdn.sap.com/irj/scn/wiki?path=/display/erplo/availability%252bchecking%252bin%252bsap
    Re: ATP confirmation in CRM
    https://www.sdn.sap.com/irj/scn/wiki?path=/display/scm/rba
    Regards
    Abhishek

  • User Exit called when online ATP check with GATP

    Hi Guys,
    I got requirement as below,
    Manipulate the GR time defined in the unloading point when the ATP confirmation of sales order is done with GATP online.
    I noticed that the online GATP check from R/3 to APO is not going via normal CIF way of communication or at least even i de-registered CIF queue monitoring, the data transfer can still go through properly.
    There are two questions popped up:
    1. Any body knows the background routine how the data are transferred between R/3 and APO when online GATP is done, and how to debug this process?
    2. Which functional module or exit user is called when online GATP check is done from R/3 sales order?
    If anyone knows something you are also welcome to share your expertise!
    Thanks!
    Tony

    hi! Tony
    These are the Exits in online GATP
    EXIT_/SAPAPO/SAPLATPT_001      APO ATP: Set ATP Segment                           
    EXIT_/SAPAPO/SAPLATPT_002      APO ATP: Select Substitutions                      
    EXIT_/SAPAPO/SAPLATPT_003      APO ATP: Initialize ATP Controller                 
    EXIT_/SAPAPO/SAPLATPT_004      APO ATP: Check for the Existence of a Location Alias
    EXIT_/SAPAPO/SAPLATPT_005      APO-ATP: Handling of Data at End of Check          
    Regards
    Vaibhav Sareen

  • ATP check with acknowledged PO 's only

    Dear Experts
    In ATP checking rule A or B my client does not want to consider all Purchase orders but only those which have been acknowledged by Vendor.
    Is there a possibility of this. I do not see any standard setting in configuration to achieve it.
    Regards,
    Neeraj Srivastava

    Hi,
    There is no standard SAP functionality can help your scenario.
    You can try to use exit EXIT_SAPLATPC_001. You can check with an ABAP'er for possibilities.
    Also try to look for OSS notes.
    Regards

  • ATP Check with replenishment time

    Dear All,
    The system behaves, when we use the 02 availability check type in the material master and assign 02 check type to control rule A in OVZ9.In this assignment the no replenishment lead time is not selected;that's the system will take the replenishment lead time into account. But even if there's not enough stock, the sales order quantities are confirmed.
    When I activate/select the "no replenishment lead time in OVZ9, the system confirms what's available in the storage location.
    Is there thing missing in customizing? Is there any OSS note? The client actually requires the replenishment lead time in the availability check but the system also should give the correct confirmation in ATP check.
    What should be else?
    Regards
    J.Black

    Here what the problem is, even if the stock is not enough, the system confirms all the sales quantity in the sales order when the "check without  replenishment lead time" in OVZ9 is not selected. This is wrong.
    But when the "check without  replenishment lead time" is selected, the sales order quantity is confirmed correctly.What is available in the stock is confirmed correcly.This is correct.
    So the client wants the replenishment lead time selection in the OVZ9 and so that forward scheduling should exist but the stock availability check is şncorrect. What should we do now?

  • ATP Check with STOs

    Hi All
    Need your help to resolve the following concern in committed date of STOs
    Scenario:
    When a STO is created for a material where the supplying plant has no stock, then the committed date in the delivery schedule lines comes up as 31.12.9999 and the statistical date comes up as the requested delivery date + planned delivery time!
    I guess this is fine as system considers forward scheduling automatically in this case.
    However this order is not considered by BOP as well!
    Now if the stock is produced / made available even then the STO is not getting picked up in BOP
    So this results in inconsistency (APO/R3) and also when the delivery is generated it comes up with error! (wrong quantity / date or '0' qty)
    Now if I manually do the ATP check in the STO line item, it changes the dates. Still it dosent show up in BOP but  delivery can be created!
    Can you guys please advice me what should be the process for such STOs (which were created when there was no stock in supplying plant). As manually doing ATP check isnt sensible.
    Also why is that BOP is not picking up these STOs (I have already checked the parameters and STO is included)
    Thanks in advance
    RK

    RK,
    "Crazy" is a misnomer when dealing with software. The only things in this business that are crazy are the clients.  Unfortunately, they also pay the bills, so you have to live with such insanity.
    According to your error message, you haven't defined 050 / U.  I don't know the entire scenario, but to me this is a red flag that must be addressed regardless of any other steps you take. You must either create these check instructions, or eliminate objects that are calling for this combination.
    I just reviewed my posts, and I don't see any place there where I said I did not create 'U'.  I did say I removed my original BE, which wasn't 'U'.  My original BE for STOs and STPrqs was 'ST'.  I removed this from both R/3 and SCM.  Then I created 'U' in R/3 and 'U' in SCM.
    1.  R/3:  SM30 > view V_441R  Create 'U' Checking Rule.
    2.  R/3: SM30 > view V_441V Create Availability check as necessary using 'U' Check rule and the Availability checks you will be using.
    3.  R/3:  SM30 > view V_161V doc category B  remove your existing check rule and replace with 'U'
    4.  R/3:  SM30 > view V_161V doc category F  Remove your existing check rule and replace with 'U'.
    5.  SCM SM30 > View /SAPAPO/V_ATP02 > Create BE 'U'
    6.  SCM SM30 > View /SAPAPO/V_ATP07 > Remove the existing check instructions for STOs.  Create new check instructions as necessary for STOs, using BE 'U'.
    7.  SCM SM34 > Dialogue /SAPAPO/ATPC04_05 > Remove the existing Check control(s) for STOs.  Add the appropriate Check control items using BE 'U'.
    I don't really know if the 'U' issue is related to your original problem.  I am only responding to the part of your post where you said
    I am getting error:
    Check instruction / U does not exist for location product XXXX / XXXX
    FYI throughout this post, I have been assuming that you have no userexits/BADIs activated, on either side (R/3 nor SCM) nor are you using RBA.  Either of these events would mean additional troubleshooting steps would be required.
    Best Regards,
    DB49

  • HT4864 iCloud has been down all day!!!!!!!!!!!!!!!!  Periodic checks of status window keep pushing out the refresh time!

    Icloud has been down all day!  Periodic checkks of the status page keep pushing out the fix tiime!

    Now you know how Blackberry owners felt after their multi day no-email problem last your.

  • ATP check with EDI orders

    hello all,
    When we create a sales order manually, we get a delivery proposal screen with the options of choosing different dates and quantity. Can I know how this works with an Inbound EDI order?
    Whether the sales order will be created with unconfirmed quantities ? Does user intervention is required if IDOC fails due to availability failure? Can we automate the process for EDI orders so that the order picks up alternate plant or material if it is linked to GATP(APO)?
    regards,
    shan

    closed

  • MRP keeps pushing delivery schedules out, refusing to firm them (ME33L)

    I hope someone has seen something like this before and can let us know where to look.  MRP keeps pushing our delivery schedules out even though it is recommending that they be rescheduled in.  What we'd like to happen is for MRP to leave these schedules alone so that they would move inside the time fence and be firmed automatically.  Here is what is happening:
    Part X, MRP type P1, firming type 1, MRP group blank.  Planning time fence 05/07/2007, available quantity -20.
    Three schedule lines exist for 05/07/2007, two for 10 and another for 30.
    MRP will run tonight.  Processing Key = NEUPL, purch req = 2, sched lines = 3, MRP list = 1, planning mode = 2, scheduling = 2
    Tomorrow, the planning time fence will be at 05/08/2007 and the three schedule lines will move out to 05/08/2007.  The won't move inside the planning time fence and firm up.  They SHOULD BE 05/07/2006 and firmed!
    We originally thought that we may have to create a release with ME84 before these would firm, but it made no difference.  They still won't firm unless someone manually changes the date on each and every schedule line.
    Does anyone know what we can change or run to get these schedules to firm up instead of having them pushed out continually?

    Hello Randy,
    thanks for the update. I didnt remenber this customizing indicator when posting.
    Still wondering why planning matters here. I think it should have the same result for all planning modes. Of course planning mode 3 in general should be avoided for performance reasons.
    For interested observers I attach the description for this setting in MRP customizing.
    Regards, Martin
    Indicator: Only Firm Transmitted Schedule Lines
    In this step, you can set an indicator which is used to set only those schedule lines that have been transferred to the vendor.
    You can firm schedule lines within the planning time fence (in the same way as planned orders or purchase requisitions) according to the master schedule item firming logic. The planning time fence is a number of days that is calculated into the future starting from the current date. Therefore, the last date of the planning time fence changes every day.
    In the firming logic, existing schedule lines are also firmed as soon as they move into the planning time fence.
    Schedule lines that lie outside the planning time fence and whose quantity is adjusted in the planning run due to a change of the requirements quantity are firmed with the new quantity as soon as the schedule lines move into the planning time fence.
    The schedule lines are transferred to the vendor for the amount recorded in the stock/requirements list at the time of the data transfer.
    If you only want to firm the schedule lines in the planning time fence that have been checked and transferred to the vendor, you can use the indicator, Only firm transmitted schedule lines. By selecting this indicator, the system only firms the schedule lines that have been sent to the vendor.
    For schedule lines whose quantity has changed and which have moved into the planning time fence, the following occurs if this indicator has been set: if the MRP controller/purchaser does not confirm the procurement plan by sending the changed quantities to the vendor, the schedule line quantities that were sent to the vendor in the previous data transfer are firmed within the planning time fence. This guarantees that the system cannot firm any quantities that have not been checked. It also means that the vondor does not receive any messages for unchecked schedule line quantities.
    Activities
    Define the indicator per MRP group and allocate this MRP group to the materials for which this indicator is to be valid.
    Further notes
    The message transfer is a purchasing function. You can find it in the purchasing menu, Outline agreement -> Scheduling agreement -> Messages -> Print/transmit.

  • Storage Location level ATP check with CRM

    Hi:
    I am on an implemenation where the integration is between CRM, EWM and GATP. So, consider the situation where the sales order check is done through CRM and a call to GATP is made.
    Some background on supply
    EWM would like to receive the goods into storage location ROD (Received On Dock) and then do a movement type to move it to storage location AFS (Available For Sale). The sales orders should consider only the supply from storage location AFS and not ROD.
    First question is, is it possible to do a storage location level determination in CRM? I don't think so but wanted to confirm. The reason is because even a plant determination is not possible in CRM when you integrate with GATP (the plant is determined through Rules).
    Now, suppose that we have determined the storage location called AFS (in gATP through enhancement) and will do an ATP only at that level in GATP. Suppose that the first plant that will be checked is Plant A and then based on the location determination procedure, the next plant that will be checked is Plant B. When the system checks supply at Plant B, then the question is this: will it still check only at storage location AFS in Plant B or will it check at the plant level? The requirement will be to check at the same storage location level (which means that whatever process we used to determine the storage location at Plant A has to be followed for Plant B also).
    One option that can be considered is to check at the Storage Location MRP Area level (there seems to be better support for RBA and Storage Location MRP Area than just storage location). See SAP Note 412314. But this is also complicated.
    Another option is to not check at the storage location level but represent the various stocks with stock types (stock type ROD and stock type AFS) and only the stock type AFS will be used in the list of ATP categories.
    Please share any experience that you may have in this.
    Thanks,

    Hi Satish,
    In my project also we had this requirement to determine the correct Storage location after plant has been determined by using rules.
    What we did is as follows:
    - We created a Z table which had entries for all plants and preferred storage locations for those plant (only one entry per plant) in your case it will be like:
    Plant A - AFC
    Plant B - AFC
    Plant C - AFC
    - We used a ATP user exit in APO to get the storage location of source plant ( which was determined in APO via rules) from the Z table.
    I hope this helps.
    Please let me know if you have any questions.
    Thanks,
    Anupam
    Edited by: Anupam Sengar on Dec 20, 2011 12:03 AM

  • Order Processing - Capacity and ATP check with planned order

    Dear all,
    is it possible to block the creation of a sale order based with PP strategy 81 (or similar) if missing components for planned order are given?
    Is also possible to block the creation of a sale order with PP strategy 81 (or similar) if no alllowable capacity for planned order is given in the scheduled dates?

    Luca,
    is it possible to block the creation of a sale order based with PP strategy 81 (or similar) if missing components for planned order are given?
    Not in Standard SAP ERP.  You can block confirmation in 81 or 82.
    Is also possible to block the creation of a sale order with PP strategy 81 (or similar) if no allowable capacity for planned order is given in the scheduled dates?
    Not in standard SAP ERP.  It is possible to generate a notification popup during the capacity check.
    The functionalities you seek exist in APO using either CTP or MATP
    http://help.sap.com/saphelp_scm70/helpdata/EN/25/b0c23ba6af1855e10000000a11402f/frameset.htm
    Best Regards,
    DB49

  • Availiility check without RLT

    Hi,
    the system always confirms stock in sales order when availibility check is with RLT since it assumes it will have stock at the end of RLT
    what happnens when availibility check is done without RLT in sales order. does it confirms stock in sales order. if yes then how it confirms.
    regards
    sachin

    Hello, thanks for ur reply to my previous question on Availibility check without RLT. can u pls answer the follwoing.
    I have a scenario where i make a sales order for 100 pcs on 23.8.08. the delivery date to customer is 01.09.08 and the material availibity date calculated by system is 28.8.08(01.09.08 less transit time less pick pack time).
    when the system does the availibilty check for the material on 23.08.8, it found no stock. yet my system confirms the schedule line for delivery date of 01.09.08.( obviously it is becasue availibility check includes RLT). what is the relevance of the scope of ATP check, i.e. opening stock, incoming purchases and outgoing sales orders. what happens when we check incoming PO and outgoing sales orders in scope of atp check. if my opening stock is 50 pcs and  incmoing stock is 60 pcs and outgoing sales  order (excluding this one i have used as an example) is 10 pcs, i think 100 pcs of my sales order can be confimred. if this is so, what is the point of having a check with RLT, since the system uses the above incoming PO+outgoing SO for atp check
    is there any connection between checking the incoming PO and GR processing time in material master ?
    i think the stock which gets confirmed in sales order, the stock is locked for that sales order. and if a new sales order is made, then the availabl qty  for this new sales orders gets reduced beaucse there is a check in atp for the outgoing sales orders. ami i right ??
    even if the required stock is already available in plant and the the schedule line is confirmed in sales order, do the sales order is being shown in MD04 or the sales order is shown in MD04 only for those quantities which requires production
    how the information is transferred to production department that material should be ready by 28.08.08.( material availibity date). what if the production department is not able to produce the material by 28.08.08
    when the production manufactures the material, how it is attached to the sales order
    what is the point of doing availibity check in deliveries.
    regards
    sachin

  • Custom ATP Check

    Hello All
    We have custom ATP(Material Check) functionality built in ECC. And we are in position to use this custom FM to carrier out ATP in CRM and show some additional information on the Order.
    Please advice on the following:
    1. Should we have disable the standard ATP configuration in CRM since we have a custom logic built in ECC
    2. Is their any BADI available for carrying custom ATP check(regardless of Configuration) and bring additional data from ECC?
    3. How can we use standard fields that holds Confirmed Quantity and date to hold the same data but from custom ATP FM
    Cheers
    RJ

    Yes. I am planning to make expilict call to ECC.
    <If you are not big on any integration benefits that might come with the standard, you can as well "disable" the standard call.
    There is no BAdI for what you are asking for. But still try CRM_AV_CHECK_R3_01 and CRM_AV_CHECK_FC_01*
    Once you have got the values from your custom RFC, check BAdI - CRM_SCHEDLIN_BADI >
    I checked this BADI CRM_AV_CHECK_R3_01 but it looks to me that this has the capability to change only the Destination.
    I am unsure about this badi CRM_AV_CHECK_FC_01* and when this would be called during the Order Processing.
    Could you please let me know more details about the badi CRM_SCHEDLIN_BADI ?
    I need to save custom obtained Confirmed Quantity and Date(from RFC) into the standard fields.
    Cheers
    RJ

  • ATP check for component materials

    Hello experts,
    The ATP check was initially designed for a kitting process. BOM Material would be kitted in the distribution center(DC) and sent to a garage. Sales orders are created with BOM materials for a garage and there is a multi- level GATP process in place. Since BOM materials do not  exist at a garage the check would be performed at a DC for components after BOM explosion. The existing configurations in R3 and APO are for a make to order process(Strategy  group of 50 for BOM's  and 40 for component).
    We are now introducing new materials for an existing material and have the need for product substitution on the sales order, if the existing material is out of stock at the DC. To enable this functionality we are having to perform an ATP check for the sales orders at the distribution center, though the sales order is   created for a garage. To improve on the response times during the ATP check our design approach, is to convert the BOM materials in the sales order to component  materials with material determination(one BOM material is tied to one component material) and performing the ATP check with components at the DC.
    While testing we are facing the following issues:
    1)Sales order placed on a garage is substituted with the DC after product substitution.  This does not occur when product substitution is carried out with BOM's.
    2)During the order create, the ATP checks for check mode u201845u2019 and business event u2018AEu2019 for a given material in a DC shows zero stock. While for the same material,location and business event AE the product availability check in APO reflects stocks available.
    Is it feasible to do ATP checks for component material in a sales order which was initially designed to work with BOM materials? Am I missing some configuration settings in either APO or R3?
    Regards,
    Anil DeSouza

    Hi Anil,
         Yes it can be done.
    1) For finished product & garage combination -
    activate RBATP in the check instructions.
    2) in the location substitution maintain 'location determination sctivity'. Here you maintain different check mode & business event -- ( this is nothing but check instruction --- in thsi you maintain 'MATP').
    Hope this anws your first qus.
    To addressing your 2nd question....follow below steps.
    1) Do ATP from sales order, get onto results screen, click on product availability & check for 'scope of check' (check control) and look for the stock types that are included. Based on this your receipts are consdiered for ATP confirmation.
    Best Regards,
    Deepthi

Maybe you are looking for

  • IPhoto imports QT with wrong time from Panasonic FX7

    IPhoto does not correctly import the time for audio comments recorded with my Panasonic FX7 camera. Does anyone know of a fix (including an Automator program)? These comments are saved as QT movies (with a still picture naturally, not moving) and are

  • Web pages down load at snail speed

    So, after years of dreaming about it I finally get to spend nearly $1400 on a new MacBook. I got her home, set her up careful as heck to follow instructions, no problems, everything is going ok and I'm up and running. However, it doesn't take long to

  • Elements 5.0 slideshow to VCD

    I created a great slide show using Photoshop Elements 5.0. I clicked on output to burn to a CD and everything looked good and it said the project was completed. When I try and play it back on my computer and/or DVD player it does not play. When I cli

  • How to use iPhone to sync Outlook with Google calendar?

    This is a bit of a convoluted question, but I think there may be an answer using the iPhone as a go between. Here is the issue, I cannot get my google calendar and my Outlook calendar to sync with each other.  I'm using Outlook 2011 on a macbook pro

  • Satellite C670D-10W - Task manager shows 100% CPU usage

    My brand new laptop with factory installed windows 7 and all programs by Toshiba nothing addded shows 100% processor usage in task Manager and works pretty slow. The sum of 80 odd processes shown in task manager never reaches more than 30-50 % but bo