MRP keeps pushing delivery schedules out, refusing to firm them (ME33L)

I hope someone has seen something like this before and can let us know where to look.  MRP keeps pushing our delivery schedules out even though it is recommending that they be rescheduled in.  What we'd like to happen is for MRP to leave these schedules alone so that they would move inside the time fence and be firmed automatically.  Here is what is happening:
Part X, MRP type P1, firming type 1, MRP group blank.  Planning time fence 05/07/2007, available quantity -20.
Three schedule lines exist for 05/07/2007, two for 10 and another for 30.
MRP will run tonight.  Processing Key = NEUPL, purch req = 2, sched lines = 3, MRP list = 1, planning mode = 2, scheduling = 2
Tomorrow, the planning time fence will be at 05/08/2007 and the three schedule lines will move out to 05/08/2007.  The won't move inside the planning time fence and firm up.  They SHOULD BE 05/07/2006 and firmed!
We originally thought that we may have to create a release with ME84 before these would firm, but it made no difference.  They still won't firm unless someone manually changes the date on each and every schedule line.
Does anyone know what we can change or run to get these schedules to firm up instead of having them pushed out continually?

Hello Randy,
thanks for the update. I didnt remenber this customizing indicator when posting.
Still wondering why planning matters here. I think it should have the same result for all planning modes. Of course planning mode 3 in general should be avoided for performance reasons.
For interested observers I attach the description for this setting in MRP customizing.
Regards, Martin
Indicator: Only Firm Transmitted Schedule Lines
In this step, you can set an indicator which is used to set only those schedule lines that have been transferred to the vendor.
You can firm schedule lines within the planning time fence (in the same way as planned orders or purchase requisitions) according to the master schedule item firming logic. The planning time fence is a number of days that is calculated into the future starting from the current date. Therefore, the last date of the planning time fence changes every day.
In the firming logic, existing schedule lines are also firmed as soon as they move into the planning time fence.
Schedule lines that lie outside the planning time fence and whose quantity is adjusted in the planning run due to a change of the requirements quantity are firmed with the new quantity as soon as the schedule lines move into the planning time fence.
The schedule lines are transferred to the vendor for the amount recorded in the stock/requirements list at the time of the data transfer.
If you only want to firm the schedule lines in the planning time fence that have been checked and transferred to the vendor, you can use the indicator, Only firm transmitted schedule lines. By selecting this indicator, the system only firms the schedule lines that have been sent to the vendor.
For schedule lines whose quantity has changed and which have moved into the planning time fence, the following occurs if this indicator has been set: if the MRP controller/purchaser does not confirm the procurement plan by sending the changed quantities to the vendor, the schedule line quantities that were sent to the vendor in the previous data transfer are firmed within the planning time fence. This guarantees that the system cannot firm any quantities that have not been checked. It also means that the vondor does not receive any messages for unchecked schedule line quantities.
Activities
Define the indicator per MRP group and allocate this MRP group to the materials for which this indicator is to be valid.
Further notes
The message transfer is a purchasing function. You can find it in the purchasing menu, Outline agreement -> Scheduling agreement -> Messages -> Print/transmit.

Similar Messages

  • ATP check with RLT - rescheduling keeps pushing confirmed date out???

    In order entry, our availability check is looking only at inventory and RLT... so that if stock is unavailable, the line item gets confirmed for a future date based on the material's RLT. We have noticed, however, that every night when backorder rescheduling runs, the confirmed date is pushed out one day later (assuming that no inventory exists still). So it appears that BO rescheduling is recalulating the confirmed date based on the current date + RLT.
    Does this make sense? Is there any way we can make the original confirmed date stick? We don't want to use the Fixed Date & Qty flag on the schedule line screen, because we want to be able to pull the confirmation (and delivery) in earlier if the inventory is available earlier... we just don't want it to keep getting pushed later.

    This boils down to a business question.
    Say you have a material with a 30 day RLT.
    On Day 1, an order is placed - and due to no stock or planned receipt of stock with the 30 days - the delivery date is moved out 30 days based on the RLT.
    Now it's day 29, you run the backorder report and there is still insufficient stock / replensihment plan within the next 30 days.
    ==> Do you want to keep the promised delivery date of day 30 - or is day 59 more realistic?
    More to the point, why hasn't stock been acquired or a replenishment plan / order been created in the previos 29 days?
    The RLT shouldbe set so that there is a very high likelyhood that the order can be fulfullled ini that time line.
    To me, it makes sense to keep pushing out the date. When stock actually shows up in sufficient quantity, the date will be moved back up.

  • MRP creating multiple delivery schedule lines in PR

    Hi,
    We have activated MRP (type PD) where Purchase requiesition is auto created by system for requirement quantity. We require to optimize delivery schedule in such a way that entire PR quantity is broken into various delivery schedule based on planned delivery time and requirement.  Scenario can be further explained with following example.
    Material Requirement for a month is say 1,25,000 units
    Closing Stock say 25,000 units
    PR Generated by system for 1,00,000 units. The entire quantity is schdulled with only one delivery schedule line as per planned delivery time. 
    The requirement is to generate multiple delivery schedule lines automatically in Purchase requisition based on planned delivery time so that Purchase orders can be placed with system generated delivery schedule lines.
    How can it be achieved ?
    Regards,
    Nirav Kinkhabwala

    Dear
    Are you dealing with Single vendor  where you want Multiple Schedule Line item through single PR  which should be generated through MRP run ??
    What you will have to do is to set up the Outline Agreement or Info Record for your vendor and material and then create the source record for this vendor- material relationship and make sure that this source record is set as MRP relevant. Once MRP is run, the vendor is automatically defaulted to your PRs. If in your material master, you have defined the same purchasing group for various material numbers, then with Transaction ME59, it is feasible that you can combine various PRs of the same purchasing group by flagging onto the 'Per Purchasing Group' indicator checkbox. Make a trial test and let me know how it goes.
    Or you can use Qouta arrabgement in that case for different vendor .Please refer : Multiple Requisition  line itme for Quota arrangement
    Just check and revert
    regards
    JH
    Edited by: Jiaul Haque on Dec 25, 2010 1:52 PM

  • MRP - Ammending PR/Delivery schedules

    In MRP
    Standard SAP allows to ammend Fixed indicator of PR, we can reset the indicator, change indicator etc
    When it comes to Delivery schdules Standard SAP doesnt allow you to set indicator manually similarly u cant remove indicator manually
    Can some one help on answering above question
    Thanks

    Hi,
    The F1 help for fixed indicator for Schedule line says that
    The indicator is set automatically if:
    You make manual changes to a line of a scheduling agreement delivery schedule that was created via the materials planning process
    You create a schedule line manually
    Check the MRP type and firming type assigned against the MRP type in transaction OMDQ
    Also Refer OSS notes 204153,354164

  • MRP Areas and Delivery schedules

    We have managed to succesfully configure MRP areas, however we still have problems of transferring the MRP results to Scheduling Agreement. We can only set source list at plant level. Now same plant has different MRP areas. Please help.

    Hi TAJUDDIN,
    Let me rephrase my quiry. We have a customer that sends requirements to us, which we then send through to MRP, which gives us the nett requirements, which are then sent to the supplier.
    We have been running this at plant level with no problem as the supplier was seeing all the requirements (from our customers/ subsidaries) consolidated. But now this requirements must be passed to the supplier per individual customer or subsidaries. For implementing this we created a new plant with storage Locations representing each subsidary, each subsidary has to be planned separately and handed to the supplier as individual requirements.
    Hence we looked at MRP areas for this, the other option was to create each subsidary as a SAP plant but this is not neat. Our problem is that we are able to plan with MRP areas but we are unable to pass the MRP results to the agreement that we have with the supplier.
    JUst though to give more infor of the full scenario might help, but in short you've been very helpful. I've learnt quite a lot.
    I hope you'll still be patient with me while I try and understand as well as address the current issue we have.
    Thanks.

  • MRP delivery schedules when sheduling agreement out of validity

    Hi experts!
    Can anyone tell me how to prevent MRP from generating delivery schedules when the scheduling agreement is expired or the item quantity overtaken?
    Thanks.

    Hello,
    Change the following message from warning to Error and then try
    Application - 06
    Message no - 189 - Schedule line date outside scheduling agreement validity period
    Message no - 067 - Scheduled quantity & & greater than target quantity & &
    Regards,
    Shailesh

  • Why GR performed on MRP generated delivery schedule line (unconfirmed)?

    Hi Gurus,
    Need some advice from you all, I have a scenario here which MRP generated the delivery schedule lines for material A on 10.08.2011 - 124 KG.
    User review the MRP result and didnt confirm the line, but she added in manual line on 11.08.2011 - 124KG.
    On 11.08.2011, warehouse performed GR on the delivery schedule lines. It's found that GR was actually updated into the delivery schedule line generated by MRP (10.08.2011) and not the manual line confirmed by user. (11.08.2011).
    User is questioning now why the GR able to be performed on MRP generated line which had not been confirmed? Any guru can share with me the fact and good note regarding this on MRP? Thanks!
    Michelle

    Hi,
    Since we are talking here about schedule lines, these are open for GR when the delivery schedule is send to the vendor.
    In your case you had a quantity open for 10/08/2011 generated by MRP, then the user added manually another line on 11/08/2011. After this the user will have transmitted the delivery schedule which makes that both the items where marked as transmitted and thus open for GR.
    Now when the goods come in the system will post against the first open schedule line that is found until this is fulfilled and then switch to the next open line at the moment of GR. So this is why the GR was put against the MRP generated schedule line as this one was the one with the earlier date.
    Regards,
    Peter

  • MRP delivery schedules vs scheduling agreements

    Hi experts!
    Can anyone tell me how to prevent MRP from generating delivery schedules when the scheduling agreement is expired or the item quantity overtaken?
    Thanks.

    hi,
    the data you need from master data are:
    customer: KNVV-EIKTO, supplier account at customer
    customer inforecord: correspondance between customer material and your material number
    Roberto

  • Delivery date in Delivery Schedules

    Dear Experts,
    We run MRP in MD02 to gerenarate delivery schedule lines.
    How the delivery date in delivery schedule is calculated?
    Is it possible to setup so that irrespective of MRP run date, all delivery dates should be Monday OR Friday in Delivery Schedules?
    Awaiting a reply from the experts.
    Regards,
    Shahsidhar

    Dear Experts,
    The purpose here is to consolidate all deliveries on one day.
    When MRP is run, delivery schedules lines should be created with delivery dates as only Monday/Wednesday.
    How can we achieve this? Any suggestions are welcome
    Regards,
    Shashdihar

  • Creation of delivery schedules OMDT

    Hi Experts
    After MRP run automatic Scheduling lines to be generated.
    Does OMDT Schedule lines 1,2,3 to be set ?
    Please advise how this works.
    regards
    MM

    Hi,
    To create schedule lines automatically after MRP run, maintain source list for the material in the plant entering validity period (same as that of scheduling agreement) & scheduling agreement number / line number with MRP indicator as 2.
    1) Delivery date in PR lies within the validity period of the Scheduling Agreement.
    2) Account Assignment in Scheduling Agreement is same as that in PR.
    3) Quota Arrangement if maintained, does not point towards another vendor as valid / preferred source.
    4) In source list, you have not maintained another vendor as Fixed source.
    5) In source list, you have not blocked the scheduling agreement.
    6) Scheduling agreement has pending open quantity equal to or greater than quantity in PR.
    7) Scheduling Agreement is released.
    8) Check your MRP parameters for Delivery Schedules. If it specifies No Schedule lines, then also schedule lines will not be generated.
    After MRP settings done can do MD01 or MD03.

  • Reg LPA Delivery schedules - MRP

    Hi
    Delivery schedules got created via MRP - LPA document type
    We haven't released to vendor [JIT or Forecast]
    When i manually change quantity in generated delivery schedule, Firmed indicator is ticked as expected
    i am unable to uncheck this indicator when go there change mode it is grayed out
    Please suggest

    SAP Help says 'You can only change it from the planning result. To do this, double-click on the schedule lines in the planning result.'
    Planning result ??
    How do i make changes to firm indicator, Please help

  • Order of delivery schedule line counter at schedule agreements from MRP run

    Currently we are using schedule agreements for our long term external suppliers, but we are facing a problem with the order of new delivery schedule lines created during MRP run.
    Because of master data settings like, lot size, rounding value, plan delivery time and planning time fence to set as firm new requirements, multiple schedule lines are created with no order for schedule line counter.
    Does anyone is aware of a BADI, user exit or customizing control to have this schedule line counter in order?
    Thank you
    Daniel Guillen
    IT
    Skyworks Inc.

    Hi,
    Pls put this query in SD fourms  and get immly help because this is technical fourms.
    Anil

  • *MRP unable to create Delivery Schedule Lines in MM Scheduling Agreement*

    Hi Experts,
    I need your help...
    The issue is, in-spit of maintaining Source List with an u201CScheduling Agreement with item No.u201D & u201CSource List Usage in MRPu201D as 2 (Record relevant to MRP. Sched. lines generated automatically), MRP run does not generate Schedule Lines, instead PRs are created.
    Please help me to understand such behavior and fix the issue as the requirement is to generate Schedule Lines only.
    Thanks,
    Pratap

    Hello
    Please check
    1) Source List maintained properly in terms of Material # ; plant # ; proper POrg ; Schd Agr # and line item# ; proper validity date & MRP relevant indicator
    2) Please also check Quata arrangement if you are using. whether % is maintained correctly against the vendor
    3) MD03 , Delivery schedules- should be 3
    4) check your planning horizon whether it is NETCH or not
    5) check material master -MRP2 view, Procurement type is F- external procurement, schedule margin key if you are using
    if everything above is set, then I feel it should work
    Also please verify-
    lot size, safety stock and the corresponding prod volume for MRP input v/s the stock available in MMBE
    example.
    MD04, we can see the open del lines.
    if SS = 50 , prod volume is 150
    1) if MMBE shows 200 then it wont generate any schedule.
    2) if MMBE is 180 and your lotsize is 40, then after MD03, you will have a schedule line of 40 (provided if everything is set properly)
    Please ensure there are NO open delivery lines . if you find such in MD04, then please close open delivery lines
    in calculation of MRP, system considers such open delivery lines are going to receive and no additional schedule line generated even after MRP run
    thanks

  • PO print out of delivery schedule

    Hi,
    Suppose I am generating a PO , in some cases I will be giving delivery schedule for some items in item details.
    I want this to come in the print out.
    But its not coming .
    Please advise.
    regards,

    Hi
    You can include logic with the help of Developre, If information is there in EKET for Purchase order ask him to include in print.
    regards
    Srinivas

  • The delivery schedule lines don't get created automatically on MRP run.

    Hi All,
    The delivery schedule lines don't get created automatically on MRP run for subcontracting material.  I have maintained source list as follow eg.
    Valid from | Valid to | Vendor | Porg | PPI | Agreement | Item | Fix | MRP | MRP area
    02.11.2009 | 31.12.2999| XYZ | XY01|     |AA0000XYZE |10 | X |2 | ABC
    Could you please help me about this issue
    Thanks in advance.

    Hi Amit,
    Please ensure the value of Special procurement key in the MRP2 view for the material. It should be maintained as 30 - subcontracting.
    Thanks and Regards,

Maybe you are looking for

  • OBIEE EXECUTE PHYSICAL sql as Data Model Query

    The following SQL was generated using OBIEE. I'd like to use it as the SQL query for my data model. It works fine it I hard code all of the values into the where clase. However when I attempt to pass parameter values (:ACCOUNTING_PERIOD & :FISCAL_YEA

  • How do I delete multiple stamps or fields done in version 7, but now I have in Acrobat Pro 9

    Most of our files were done printed in PDF with version 7. We have inserted a stamp in version 7. But when I open this file in Version 9, these stamps have become field and the usual action in deleting multiple of these was to just go to navigation t

  • Content not appearing after first time

    I could really do with some help on this one. I have a screen (State) in my application that displays some custom mxml components using a repeater. The first time I come to this screen, all the data appears correctly. However if I navigate away from

  • Problems since Mobile me

    Hey all since the mobile me switch I'm experiencing some funky things. 1. Can not open a new web gallery. It goes through the motions then simply dispapears. No gallery. All the .mac galleries are posted but I can't change them. I am logged into mobi

  • No working adapter engine

    Hallo, after installation there are only one entry in the adapter monitor (JPR). We are missing the other adapters (file, jdbc etc.) Can anyone help me. Thanks in advance, Frank