Auxiliary Cost Component- report

Dear Experts,
Is there any report available (similar to S_P99_41000111) that show cost component structure based on Auxiliary Cost Component?
Thanks
babu

Dear Babu Bhai
In CK13N when you see the cost details at that point when you click Cost component button as highlighted below screen1 you get a button for CCS as highlighted as screen2 which gives you opportunity to see Aux CCS.
Screen1
Screen 2
Regards
Rajneesh Saxena

Similar Messages

  • Reference to note 434873 - Auxiliary cost component split

    1) We use material ledger. We already have a primary cost component split defined in our system.
    2) We want to activate an auxiliary cost component split.
    3) We read the note 434873, paragraph 2)b) (activating an auxiliary cost component split).
    4) Who can assist us to develop the customer-specific Z program that is referenced in the note?

    Hi to Evrybody,
    I am trying to configure Primary Cost Component Split,, but I am confused what are the technical steps to configure such a structure 
    http://help.sap.com/saphelp_40b/helpdata/en/7e/cb7e8643a311d189ee0000e81ddfac/content.htm
    There are several requirements how to configure in SAP Primary Cost Component Split:
    1)You assign a cost component structure in the CO version in Cost Center and Process cost planning!  Which Cost Component Structure? The Primary Cost Component Structure or the Cost Component Structure?
    2)You determined the prices through planned price iteration!                                                                 We set this indicator in the CO Version itself?
    3)You define a Cost Component Structure for Primary Cost Component Split of Product Cost Planning! How do we define it, via simply checking the check in OKTZ?
    I want to understand when you create Cost Component Structure and Primary Cost Component Structure, which one of these 2 needs to be assigned in the CO version in Cost Center Accounting? And the other thing is I do not make the difference between Cost Component Structure and Auxiliary Cost Component Structure? Could you please shortly describe what is the difference? Other thing is when you create Primary Cost Component Structure and its components, DO THEY INCLUDE ONLY RANGE OF PRIMARY COST ELEMENTS OR IT IS A TECHNICAL STEP ONLY TO CHECK THAT CHECK IN OKTZ FOR Primary Cost Component Split. Let me know, thank you very much for your help and cooperation again!
    Best Regards,
    Georgi Georgiev

  • Cost component report

    this is the z report we are using for cost component report .when run the report for perticular movement type system taking the total value of the one movement type .But when you give two movement type (ex :601 and 602 ) the ststem giving only one moment type total amount not both movement type total .what is the reason for this case .can u please provide the solution for this .i hope i will get the suitable solution for this case
    EX : with movement type 601 cost report total is 5000 .but when run with two movement types (601 and 602 ) the system picking the cost report total is 5000 only that is only movement type 601 total .System does not picking the both movment type totals .what is the reason please hope suitable answer from your end .Thank you...........
    601 -  goods delivery
    602 -goods delivery reverse
    Regards
    Raj

    not answered

  • Is it possible to have Auxiliary Cost Component as Value Fields in COPA

    Respected Gurus,
    Is it possible to have Auxiliary Cost Component as Value Fields in COPA - Please Advise?
    Thanks
    PM

    Hi Praveen ,
    It is possible.. in Transaction KE4R .. we have to specify the cost component structure .. where you map the cost components with value fields..
    Please use your auxiliary Cost Comp Structure in KE4R to achieve your purpose
    Regards
    Sarada

  • Auxiliary cost component splitting issue in CK11N

    Hi Friends,
    We are using primary cost component split for the auxiliary cost component structure for getting more information.  We have a machine cost in the main cost component which is split in three auxiliary cost component i.e. Energy, Maintenance and depreciation. 
    My belief is that with the activation of primary cost component split the costs have to flow from cost center in its primary cost element form to this cost component structure.
    With the current data that we have, the cost component split is seen for all the three cost elements in the auxiliary cost component split u2013 But we are not able to trace the source of this amount as we do not have any splitting structure in place, the plan costs are only for Energy not for Maintenance and depreciation.
    OKES Configuration:
    Selection for assignment:
    Cost Element               GMACHINE (only for Energy)
    Activity Type     MACH
    Splitting rules:
    10                                        21     Equivalence Numbers Planning
    Machine 0.64 is splitting into as follows Depreciation 0.41, Energy 0.12 and Maintenance 0.11
    I am afraid from where splitting happening for Energy and depreciation and there is not receiving   splitting rules.
    Appreciate for quick reply
    Thanks
    Govind

    Hi to Evrybody,
    I am trying to configure Primary Cost Component Split,, but I am confused what are the technical steps to configure such a structure 
    http://help.sap.com/saphelp_40b/helpdata/en/7e/cb7e8643a311d189ee0000e81ddfac/content.htm
    There are several requirements how to configure in SAP Primary Cost Component Split:
    1)You assign a cost component structure in the CO version in Cost Center and Process cost planning!  Which Cost Component Structure? The Primary Cost Component Structure or the Cost Component Structure?
    2)You determined the prices through planned price iteration!                                                                 We set this indicator in the CO Version itself?
    3)You define a Cost Component Structure for Primary Cost Component Split of Product Cost Planning! How do we define it, via simply checking the check in OKTZ?
    I want to understand when you create Cost Component Structure and Primary Cost Component Structure, which one of these 2 needs to be assigned in the CO version in Cost Center Accounting? And the other thing is I do not make the difference between Cost Component Structure and Auxiliary Cost Component Structure? Could you please shortly describe what is the difference? Other thing is when you create Primary Cost Component Structure and its components, DO THEY INCLUDE ONLY RANGE OF PRIMARY COST ELEMENTS OR IT IS A TECHNICAL STEP ONLY TO CHECK THAT CHECK IN OKTZ FOR Primary Cost Component Split. Let me know, thank you very much for your help and cooperation again!
    Best Regards,
    Georgi Georgiev

  • Cost component with quantity

    Hi SAP Experts
    My client want material actual cost component report not only with value amount, but also with quantity.
    The material ledger was activated, I know using standard function, we can have material actual cost component report with value amount, like Tcode:MLCCSPD,  but cannot find any quantity information.
    Do anyone have the kind of requirement and how to achieve it ?
    If only customer development method, how to do it. thanks a lot!

    I tested the CKMLQS, it only get the current period BOM quantity, cannot trace to origin component quantity.
    for example:
    Previous Period:  material A  Qty 10 -----produce------>  material B Qty 10
    Current Period :  material B  Qty  7 -----produce-------> material C  Qty 7
    Now, Using report:CKMLQS, it only show material B quantity 7 consumed for material C, cannot see the origin component material A consumed quantity.
    I need to trace origin component(the lowest level of BOM) quantity, like amount value report(Tcode:MLCCSPD). 
    Anyone have suggestions? thanks
    Regards
    Robin

  • Change Analyze cost component split CK80_99 or CK13N.

    HI experts,
    How or where can i change report CK80_99 or CK13N? I don´t know which is it report? I need some summarization row to this report, for example:
    Cost component split:
    10 raw material
    20 wraps
    10-20 material in sum - Summarization
    30 wages
    40 overhead
    10-40 production costs - sumarization
    Thanks a lot, for Your help.
    Gustavo

    Hi,
    CK13N transaction allows you to see information of standard costs in below formts.
    1.Cost itemisation-cost of each item which is responsible for standard cost and summation of all elements in last row.
    2.Cost component-these are configured cost sets based on local cost reporting method.
    3.Costing level with cost component-This replica of your BOM structure with additional information cost for each level.
    Your issue is realated with #2 in the above list.
    I hope following steps will help you to get that information,
    In CK13 transaction call the cost component report.Download this report into excel format and sum up as per your requirement.
    or else if you want configure existing cost components under expected groups in cost component config.
    Hope this helps you.
    Ashok

  • Primary Cost Component Split in CO-PC

    Hi Experts,
    Could anybody define the exact steps to configure Primary Cost Component Split in CO-PC?
    I've tried unsuccessfully to do it:
    1) I've created Cost Component Structure 45 in OKTZ with Components only with PRIMARY COST ELEMENTS and marked this Cost Component Structure as Primary via checking the box in OKTZ.
    2) I've assigned this 45 Cost Component Structure in CO Version and I've also checked that the prices will be PURE ITERATIVE
    3) I've  assigned assigned 45 Cost Component Structure in OKTZ as AUXILIARY Cost Component Structure in OKTZ
    4) I've create Cost Component Structure 44 in OKTZ with Components including PRIMARY COST ELEMENTS and SECONDARY COST ELEMENTS (Cost Component Spli for COGM)
    5) I've assigned Cost Component Structure 44 in OKTZ as a MAIN Cost Component Structure
    6) I've also created TRANSFER STRUCTURE for Cost Components of 45 to Cost Components of 44
    Prerequisites:
    1) I was thinking about having Distribution Cycles in order to see all the Cost Elements in CO-PC
    2) Cost Splitting to put the Primary Cost Elements from CCA into the fixed part of the price
    3) Price Calculation
    Well frineds even though I executed CK11n I still encountered an errors, stating, that the system can not find the Secondary Cost Elements for Labour and Overheads in my Primary Cost Component Structure 45....
    I am really confused now. Could anybody help with this, thanks!

    Well..it seems you did correctly, but try to check if the activity master data is really assigned to same secondary cost element you set in OKTZ. Go for transaction KL03 and check it.
    Regards

  • Difference between cost component structure and cost component split

    can anyone explain me the difference between cost component structure and cost component split with simple example
    thanks
    santosh

    Hi ,
    cost component structure
    Definition
    Number that identifies the structure.
    Use
    In Product Cost Controlling, the cost component structure determines how the results of material costing are updated. The cost component structure groups the costs for each material according to cost component (such as material costs, internal activities, external activities, and overhead). If the material is used in the production of another material, the cost component split (which breaks down the costs according to material costs, internal activities, external activities, overhead, and so forth) remains in the system when the costs are rolled up.
    In the cost component split, you also define the following for material costing:
    Which part of the costs are fixed costs
    Which costs are
    cost of goods manufactured and what are sales and administration costs
    Which costs are relevant for stock valuation, commercial inventory valuation and tax inventory valuation
    When the cost component structure is assigned to the organizational units, you can specify that two cost component splits are created:
    Main cost component split
    This is the principal cost component split, meaning that it is used in the standard cost estimate, which can be used to update the material master. The main cost component split can be a cost component split for cost of goods manufactured or a primary cost component split.
    Auxiliary cost component split
    This can exist in addition to the main cost component split, and is not used in the standard cost estimate. It can be used for analysis purposes, in that it can be displayed with the cost estimate and passed on to Profitability Analysis.
    In Cost Center Accounting, the cost component structure determines how the results of the activity price calculation are updated. The cost component structure groups the costs for each activity type of the cost center according to components (such as material costs and labor costs). If an internal activity allocation is carried out, the cost component split (which breaks down the costs according to material, labor costs, and so forth) is retained at cost rollup.
    If the cost component split is not to be retained, you can create a switching structure for the cost component structure for Cost Center Accounting. In the switching structure, you specify which sender cost component goes into which receiver cost component.
    <b>require a cost component structure to calculate prices using cost component split.</b>
    For each cost component structure you define a component such as energy, personnel, or raw materials. The components combine all costs occuring for a particular cost element area. In this way, you ensure greater cost transparency in activity price calculation when putting together the activity type prices - for example, it becomes easier to find how much of the activity price is taken up by the material costs.
    In activity allocation, the cost component structure remains constant, meaning that the receiver takes on the sender cost elements and that the allocated costs are posted in the same cost components in the receiver as in the sender.
    A cost component structure can have a maximum of 40 defined cost components.
    Cost components are assigned to cost elements. You thereby determine which cost elements go to which rows in the structure, and how these components are updated in price calculation.
    Hope ths helps
    Please rewad points
    Sunil

  • Standard Report for Materials Cost Component Structure - PO Condition Type

    Dear experts,
    We are using below cost component structure (CCS) for materials:
    - Direct materials
    - import duty
    - import handling
    In which, all those above CCS are achieved through below condition type in Purchasing Info Record. When doing the standard cost estimate through costing run, we have successfully grouped all those condition types into their respective CCS. The problem is, while executing the standard report of "result of costing run" (S_ALR_87099930), the sytem groups all those three CCS into CCS "Direct materials" only.
    I have tried different standard layouts, but still got no way to show all those CCS separately in the standard report.
    Please kindly suggest what approach should i take
    Thank you very much
    BR, Erwin
    @edit
    Solved.
    Edited by: Erwin Hartono on Nov 16, 2011 9:16 AM

    Hi
    Check cost elements assigned to structure.  For this go to transaction code OKTZ and select your CCS and double click on Assignment Cost Component-Cost element interval.
    Srinivas

  • Report painter/writer for actual cost component split

    Hello Gurus,
    Any of you guys ever explored possibility of creating a report using report painter or writer that can give both Standard and Actual cost component splits in one report? Is it even possible without custom ABAP involvement?
    Thanks
    RG

    Hi Raghu,
    After your reply, I am getting a doubt..
    Have you Activated Material Ledger? When you say Actual Cost Component Split, are you talking about it what you get in Actual Costing/Material Ledger?
    If yes, then you can map your cost compnents for Actual Costing in the path SPROControllingProfitability AnalysisMaster Data Valuation--Setup Valuation using Material Cost Estimate -- Define Access to Actual Costing / Material Ledger
    Further, there are no standard reports available in COPA. Try to build a report comprising two columns, 1st column with the value fields which are mapped for Standard Cost Components and 2nd column with the Value Fields which you have assined for Actual Costing under the above path.
    You will be able to get the comparison...
    Pls don't hesitate to call me for further assistance....
    Srikanth Munnaluri

  • Cost component structure in CO-OM Reporting

    Hi there,
    we want to run cost center reports, that show us the balance on a cost center per primary cost element, after we have allocated some of the costs from the cost center into production orders.
    I thought this can be achieved by having the tariffs we use for the internal activity allocation been broken into their cost component structure so that on the cost center, the respective primary cost elements are debited by the activity allocation.
    However, this is not happening in my system. While the activity tariffs are correctly calculated with a component split (according the 1SKS-001 report), the standard cost center report still shows the debit on the cost center with the secondary cost element of the activity.
    Does this mean I cannot see the component split of my activities in normal OM reporting?
    Thanks
    Kai

    Hi
    Make cost splitting structure and assigne to Production Cost Center.
    Run Cost splitting KSS2 for cost splitting according to activity types.
    bukhari

  • Cost component structure in copa report

    HI Gurus
    1We are doing REM Process and costing variant "PREM"
    2. We are going for moving average price for all Material type there is no standard cost estimate
    3. My client want to see the  cost component structure in copa reports like
      sales
      exice
      ram material
      packing material
      labour
      overehad
      selling and distributioh overhead
    I have done all necessary setting in costing key
    I have done pa trasnfer structre also
    But Cost component spill is not happening in copa report
    Can we get cost component struture in copa report with moving average price if yes
    Please advice  me how to geneate the report
    Thanks & Regards
    KISHORE

    Hi Aravind
    Thanks for your reply, But in our  business process there is not Standard cost estimation,bcoz, Price control in material master is MAP. Can we get cost component strudcture in copa  if we are going for MAP in MM.
    I have done all the Setting IN KE4R also. But i am unable to see the values in COPA report
    Thanks
    KISHORE

  • How to get Cost element for a component in co03 cost analysis report

    Hi,
    I'm using table COSP to find the quantity for a production order component.  However, I need to identify the cost element first to get the unique data.  In CO03 cost analysis report, there is cost element for the component.  Does anyone know how to get it ?
    Thanks.

    CSKA stores the basic info about the cost element
    There is no data in CSKB.
    I'm trying to use different tables to get the cost element.
    AUFK, AFKO, AFPO, RESB, ...but no luck...

  • Report for cost component wise standard cost

    Dear All,
    I can view cost component structure wise breakup of cost for materials through various options in controlling.
    But, I can view that only material wise, I am unable to find any report which can allow me to view cost component structure wise breakup for say 1000 odd materials at one go.
    Kindly let me know if there is any report which allows me to view cost component structure wise breakup for mutilple materials.
    Regards
    SM

    Hi
    Refer S_P99_41000111 ... If that helps.. It does not provide cost componnets
    Most of companies develop their own report using tables KEKO, KEPH, MARC, MBEW,etc.. there is no Std report in SAP which can give you Cost Comp Wise view for multiple materials due to technical limitations
    refer Note 149261 - Problems with customer reports tables KKBC, KKBE. ..., which confirms the same point
    br, Ajay M

Maybe you are looking for

  • Looping a query with text fields

    I need to loop a query (fields: FName,LName,Phone) in textboxes. List all textboxes in one form and be able to update the db with all changes at once. <cfloop query="ListMembers"> <input type="text" name="FName#MemberID#" value="#FName#"> <input type

  • How do i import photos from iPhoto into LR5?

    how do i import photos from iPhoto into LR5?

  • I want to buy iPhone 4 on-line

    hi, sorry i'm a newbie. i'm from Philippines and I want to order it abroad. i checked the website and it says iphone 4 can be sold from $199. my question is, if i want to order and ship it to Philippines, what would be the exact price? sorry, because

  • Can't use genius with iTunes Match?

    I signed up for iTunes Match today and on my iPhone I can no longer find the option to make a genius playlist. The icon is no longer in the center of the song bar. Help please.

  • Revoke Release Strategy (Reverse Steps)

    Hello Experts Please help with following revoking issue: In Release Strategy, every release code is authorized for its own release, however revoking of release can be done by any release code available in hierarchy on above level. Example: Release Gr