BOM Material Status in PS activities

Hi Experts,
I just want to know tht,
actually iam assigning one BOM to one activity in PS.
Thr is option to view the status of WBS,N/W  and Activity,
ok,but now here i want to view the status of the BOM with respect to that particular activity.
pls help me....
Thanks in Advance..
--Prakash

Dear R.Brahmankar,
I had followed your instruction to check. It is very helpful.
when I check program in CO41 (saplcoup), I found that it only check material  status (FG) on top level of BOM .
Its don't check component material.
Function CO_ZF_CHECK_MATSTAT_POS  component item in BOM , the program will not check item plant status.
When I use TX: CO40 to test. I found that CO40 with Program LCOSD1J - CHECK_MATSTAT_COMP have component material status check.
I'm not sure is that genic CO41 don't have component material status check?
ths alot
Marco

Similar Messages

  • Material Status Report

    Hi Gurus,
    Is there any standard report for Material status.
    we are maintaining the status in OMS4.
    which we are using in Material Master like
    Blocked for procment/whse
    Blocked for task list/BOM
    These statuses for a particular material, i would like to know from any standard report.Pls suggest me.

    Hi
    The material status tells you whether a material is subject to restrictions, and what they are. For example, a material may be a part under development or one to be discontinued. The use of a material can be restricted in a number of ways:
    The material can be blocked for use in certain business activities by assigning one or both of the following material statuses to it:
    <b>Plant-specific material status</b>
    In the standard material master, this field appears on the Costing screen, MRP screen, Production Resources/Tools screen, Purchasing screen, Quality Management screen, and Work Scheduling screen.
    <b>Cross-plant material status</b>
    In the standard material master, this field appears on the Basic Data screen. It is valid for the whole client.
    <b>There is no standard report available for Material status display.You need to develop new report for this.Simple you can copy MM60 program RMMVRZ00 and this field in the same develop new program</b>. or
    You can get details from the table level.
    For cross plant status (Client level)
    Field: MMSTAE  and Table MARA
    For Plant specific
    Field: MMSTA and Table: MARC
    Regards
    Ramakrishna

  • Material status at plant level

    Dear Guru's,
    Please suggest the material status or any other solution for blocking material for planning i.e. there should be no PR, planned order or sales order. But that status should not create problem while mass level changes for BOM, Routing, DMS.
    Status 90 in MRP 1 creating problem while applying mass level changes. Also tried 00 & 01 but they are allowing to create sales orders.
    Regards,
    SAP CONS

    Hi,
    Go to OMS4 & check the statuses & their values. Choose the one which meets your need. If none suits, then create one.
    You can prevent a material from being part of MRP run, while allowing to be in BOM by setting B & blank or A respectively.
    Revert if you face any issues.
    Regards,
    Vivek

  • Material status in master data set not allow create production order. but..

    Dear All expert.
    There is one case I don't understand,  the component material within BOM had been set material plant status which it is not allowed to create Production order ( Porder header Msg & PO/Network item msg = B in OMS4).
    If user use tx:CO01 for create production order, the error message block production order can't be created. It is good .
    However, when user is using Tx: CO41 to convert planned order to production order with that material ( status which not allowed to create production Order) . it is successfully without any error message ..  User successfully create production order without limit.
    Therefore,  is there any configure in IMG was wrong?
    thanks for reading.
    Marco

    Dear R.Brahmankar,
    I had followed your instruction to check. It is very helpful.
    when I check program in CO41 (saplcoup), I found that it only check material  status (FG) on top level of BOM .
    Its don't check component material.
    Function CO_ZF_CHECK_MATSTAT_POS  component item in BOM , the program will not check item plant status.
    When I use TX: CO40 to test. I found that CO40 with Program LCOSD1J - CHECK_MATSTAT_COMP have component material status check.
    I'm not sure is that genic CO41 don't have component material status check?
    ths alot
    Marco

  • Update the x plant material status and plant speific material status

    HI Experts,
    I am new to abap. In my requriment i want to update the status of x-plant material status (MSTAE) in MARA  and
    plant specific material status (MMSTA) in MARC. In master data the status of those fields is blank. Insted of balnk i have to upload '01' or '02'.
    using BAPI_MATERIAL_SAVEDATA  i am unable to upload. its not working.
    is there any another way to upload that two plants status.
    thanks in advance
    sravan

    Hi martin,
    i think insted of it_*** (internal table) we have to use work area. please make sure conform this one.
    i am giving my logic wat i have written and my requirement also...
    The process to update material master data status is described in 'xxxxx' Mark and Release Cost Estimates and BAPu201D.
    u2022     As a result of releasing a standard cost, certain master data elements need to be updated by the Cost accountant in order to enable further activities within SAP.
    u2022     All material codes for which Cost Accounting has released a new standard cost, need to have their Material Status indicators changed from 02 (reviewed) to 03 (released).  This removes the system blocks on certain activities within SAP like purchasing, production and Sales.  The status will be needed to change in two views of the Material Master. 
    u2022     The u201CX-plant matl statusu201D field on the Basic Data 1 view
    u2022     The u201CPlant-sp. matl statusu201C field on the Costing 1 view
    This update should be automated
    Select materials for which a price change document was posted based on selection parameters.
    Select price change documents for company code defined in selection screen since last run date
    u2022     Reference procedure = PRCHG (MLHD-AWTYP)
    u2022     Entered on MLHD-CPUDT u2013 verify against last run date to include in selection
    u2022     Entered at MLHD-CPUTM u2013 verify against last run date to include in selection
    u2022     Store last run date and time by company code, so that it can be picked up in the next run. (store in table TVARVC?)
    Select only the documents of plants which belong to the company code in table MLIT. The link between company code and plant can be found in table T001K.
    u2022     Valuation area = Plant MLIT-BWKEY
    u2022     Create a list of all materials MLIT-MATNR
    The next 2 updates should happen independently;
    u2022     Update the u201CPlant-sp. matl statusu201C field (MARC-MMSTA) on all plant views belonging to the company on the Costing 1 view to status 3 with as prerequisite;
    u2022     The current plant material status is 02
    u2022     This action must be done on all plants belonging to the company code
    u2022     Update the u201CX-plant matl statusu201D field (MARA-MSTAE) on the Basic Data 1 view to status 3 with as prerequisite;
    u2022     The current X-plant material status is 02.
    in pt_final1 i get the data corresponing to given tables.
    LOOP AT PT_FINAL1 INTO GS_FINAL1.
    *HEADER DATA
      GS_HEAD-MATERIAL = GS_FINAL1-MATNR.
      GS_HEAD-IND_SECTOR = GS_FINAL1-MBRSH.
      GS_HEAD-MATL_TYPE = GS_FINAL1-MTART.
      GS_HEAD-BASIC_VIEW = 'X'.
      GS_HEAD-COST_VIEW = 'X'.
    APPEND GS_FINAL1 TO IT_FINAL1.
    *CLIENTDATA
      GS_CLNT-PUR_STATUS = GS_FINAL1-MSTAE.
      GS_CLNTX-PUR_STATUS = 'X'.
    *PLANT DATA
      GS_PLNT-PLANT      = GS_FINAL1-WERKS.
      GS_PLNT-PUR_STATUS = GS_FINAL1-MMSTA.
      GS_PLNTX-PUR_STATUS = 'X'.
      CALL FUNCTION 'BAPI_MATERIAL_SAVEDATA'
        EXPORTING
          HEADDATA    = GS_HEAD
          CLIENTDATA  = GS_CLNT
          CLIENTDATAX = GS_CLNTX
          PLANTDATA   = GS_PLNT
          PLANTDATAX  = GS_PLNTX
        IMPORTING
          RETURN      = GS_RET.
        Commit to release the locks
       RETURN-TYPE is 'E' in case of error, else 'S'.
      IF GS_RET-TYPE = 'E'.
        LOOP AT IT_RET.
          WRITE: / RETURNMES-MESSAGE.
        ENDLOOP.
      ELSEIF GS_RET-TYPE = 'S'..
        WRITE: / 'PLANT MATERIAL STATUS '.
      ENDIF.
      CALL FUNCTION 'BAPI_TRANSACTION_COMMIT'.
    ENDLOOP.

  • Changing "material status" via "project transfer"

    HI,
    I known that I can change the "material status" by transferring an item to a specific stock Locator that I already defined.
    Is it possible to change the material status via project transfer?
    For example my item's status is "active" and it was assigned to a project named "ACTV_PROJECT" I transfer this Item
    to a random locator whose project is "HOLD_PROJECT". while I perform this transaction, item status will become "HOLD" (Hold is a status that I already defined)
    Thanks for your
    Help
    Ceyhun

    Hi
    I assume you refer to Item Status Control.
    You can update the item status code using the designated form Item Status. This will automaticlly update the values of the following attributes -
    BOM Allowed
    • Build in WIP
    • Customer Orders Enabled
    • Internal Orders Enabled
    • Invoice Enabled
    • Transactable
    • Purchasable
    • Stockable
    Project Transfer is a inventory transaction, that moves certain quantity of the item from one project locator to another project locator. Such transaction is not changing the item status.
    Dina

  • Giving BOM material as free good in Sales Order

    Hi,
    I have a business requirement.
    I want to give a free good in Sales Oreder which is a BOM material.This should be possible by manually changing Item category for the line item in the Sales Order just like how we can change TAN to TANN in normal circumsatnces when we add free good material for any NON BOM material.
    In standard functionality,the item category determined for this BOM material is TAQ but this item category field in Sales Order is non editable because of which I can not include the BOM material as free good in my sales order.
    I have already defined one z Item category for free goods for this BOM material & want to use it in Sales Order.
    Can you please suggest how this can be handled ?
    Or is there any other work around by which will allow me to include BOM material as free good in my Sales Order ?
    Thanks in advance
    Regards,
    BM

    Hi,
    Thanks everyone for the feedback.I agree with Samir Danish.It is a standard functionality of SAP which does not allow free goods for BOM material.
    However, can someone suggest work around to deal with this issue.I mean if any one has been doing any work around for this issue then please let me know.It s becoming critical for me.
    Regards,
    BM

  • Schedule Lines for Sales BoM Material

    Hi All,
    When i trying to maintain the multiples schedule lines for the Sales BoM Material(Both Header and Item), system is not allowing to maintain it.Please guide me how to achieve this?

    Hi,
    "Schedule Line allowed" is enabled at Item category. The Requirement is If we have multiple schedule lines for BoM Line Item, we are not able to maintain. Suppose the Order Quantity is 50 Units and we need schedule line of 10 Quantity each month. We are not able to maintain. System takes the complete 50 quantity and do the availability check and proposes the availablity Date. We are not able to maintain different schedules manually.

  • Unable to enter multiple Schedule lines for BOM material in Sales Order

    Hi All,
    We have a Sales Order where in which we cannot add additional schedule lines for BOM material.
    The schedule lines are greyed out, user was able to add schedule lines earlier.
    I have checked all assignments in VOV6, VOV7 and everything seems to be fine and no changes have been made to item category being used.
    Please provide a solution for this.
    PFB link in which similar situation posted in this community but the final resolution method is not discussed.
    http://scn.sap.com/message/13201504#13201504
    Regards,
    Samiksh

    Hi Samiksh,
    Pls check for that particular customer, only complete delivery allowed(c) is set in the CMR or CMIR. If so, you can't enter multiple schedule lines for that customer.. it would be grayed out in the sales order schedule lines except confirmed line.
    or check the problematic sales order at item level shipping tab if the par del/item is set to 'C'
    With regards
    S.Siva

  • Material statuses error message should go after entering Trackin No in PO

    Hi All,
    I have created one Material statuses with error message, I have created material with the use of that material statuses..
    Its working fine,At the creation of PR, PO I'm getting that Error message..
    My requirement is if I enter Requirement Tracking Number at item level of PR or PO means that Material statuses Error message should Go out and system has to allow to create PR or PO..
    Is it possible?? how to do it?? plz help me...
    Is it possible in standard SAp???
    thanks and regards
    rames reddy

    Hi,
    You can keep Requirement Tracking Number as Required Entry in field selection key (NBF or a copy of NBF as ZNBF) of PO document type in u201CReference data, itemu201D segment in following path:
    SPRO > Materials Management > Purchasing > Purchase Order > Define Screen Layout at Document Level
    And then assign field selection key to PO Document type and save.
    SPRO > Materials Management > Purchasing > Purchase Order > Define Document Types
    Now create PO with PO document type, system will ask you to enter Requirement Tracking Number in u201CItem Overviewu201D unless then you can save Purchase Order.
    The same you can do for PR document type by having a field selection key for PR document type.
    Regards,
    Biju K

  • Delivery in Make to Order situation for BOM Material

    Hi,
    I have the BOM material which is exploreing in the sales order 11005 as
    follows -
    LineItem Railing 10 (Top Material)
    01 A01 10
    02 A02 10 (Sub items)
    03 A03 10
    04 A04 10
    05 A05 10
    At the time of sales order level, we are sending the requirements to
    PPC for the top material Railing, at the time produciton stage PP run
    the MRP and do the production for Sub items A01 to A05. When doing the
    production confirmation for A01 to A05 materials, system is confirming
    the stock against the sales order number 11005 with item no 01.
    In our business purpose we are maintaining the stock for top material
    and also sub itmes because of Excise purpose. For Top material we are
    uploading stock manually with MB1C with Special Stock E and in PPC
    doing the produciton of sub items.
    At the time of crating the delivery system is not checking stock of sub
    items and its showing the stock as 0 because the proudction is
    confirmed at line item 10 for sub items a01 to a05.
    Reply ASAP
    Regards
    Goutham
    +919891936656

    Hi Friends,
    Can you please provide the solution for my problem and its slight urgent.
    Regards
    Goutham

  • Goods Receipt of BOM material- cost centre required for components

    I have created a subcontracting PO with a BOM material.
    When trying to post a Goods Receipt the components of the BOM material are required to have a cost centre assigned to them.
    The profit centre for the BOM material and components are the same. The BOM material does not require a cost centre to be entered in the Goods Receipt as the Profit Centre is allocated to account assignment tab.
    Why does the profit centre assigned to the components not default in the account assignment, why is the system asking for a cost centre?

    I receive this error when trying to post the material document:Field Cost Ctr is a required field for G/L account 1000 7023000200
    Message no. F5808
    Diagnosis
    The value for field "Cost Ctr" in the interface to Financial Accounting is an initial value but you are required to make an entry in the field selection for G/L account "7023000200" in company code "1000" linked to the field selection for posting key "81".
    System Response
    Error
    Procedure
    It might be an error in the configuration of the G/L account field selection. The initial application, used to call up the interface must otherwise define a value for field "Cost Ctr". If this is the case, contact the consultant responsible for the application used to call up the interface or get in contact with SAP directly.

  • Material status blocks creation of reservation in SRM

    Dear All,
    We observe the following behavior in our SRM (5.0) System:
    If we create a caddy for a product that has the Cross-Plant Material Status : 04 (Material master, view Basic Data 1) in the Backend-System, the reservation can not be created. There is a message indicating, that it is not possible to purchase the product.
    If we create the reservation for the same product direct in the Backen-System, there is no problem.
    This is OK, if we do external procurement, but internal procurement should not be blocked in SRM.
    Do you know where we have to customize this message?
    Thank you.
    Best regards,
    Thomas

    Hi Thomas
    understood.
    not possible to purchase the product --
    is it having a purchasing view in ECC .
    If you did not pull this materials in to SRM , how can you procure from SRM web portal.
    first you need to select this material via internal goods and services in the srm web portal . then only you can order a material from SRM.
    if you pulled a material from ECC to SRM and it must be in COMMPR01.
    mUTHU

  • How to validate material status in physical Inv Doc creation using MI01

    Hi Experts,
    I would like to know how to validate material status while creating physical inventory document using MI01 transaction.
    I tried to figure out a suitable BADI and customer exits ,but it didnt work out well.
    Kindly share your thoughts on how this can be achieved.
    Regards,
    Mohammed Aslam Rasheed

    Do you really create your inventory documents with this MI01 transaction manually by entering material for material?
    The real transaction for physical inventory is MI31. How do you want SAP to react if hundreds of materials are selected and inventory documents are created in a batch process?
    SAP takes care about the material status in MI04 and MI07 transactions.
    I am not aware of any exit for MI01 maintenance, you may consider Explicit and Implicit Enhancement Options

  • Free good for bom material

    hai i am new to sap , can any one tell me how to post free good for bom material !!

    Hi,
    Being a new member, one quick advice would be to search SDN and related forums before posting a new question, since this issue has been discussed many times.
    To answer your question, Free Goods does not support BOM.
    Please check [here|http://help.sap.com/saphelp_46c/helpdata/en/dd/55fa34545a11d1a7020000e829fd11/frameset.htm] for detailed explanation.
    Regards,
    Amit

Maybe you are looking for

  • How can i use my tv as the 2nd monitor

    hi, how can i use my tv as the 2nd monitor, for example pull a video from desktop to tv for windows7, the computer is hp omni 120 all in one. because i have a cable for it that connects to the tv but i dont know how to connect the pc to the tv. i tri

  • How to get file name and set it as static text in a dialog

    Hi, I m new to InDesign Programming. I have a menu that creates a dialog with different controls in it. The dialog will appear only if there is an open file. I need to display the name of the open file as a static text in the dialog. I know to get th

  • Status-12 IDOC

    Hi all, Is there any way to check to which receiver port the IDOC has been sent from R/3??? In WE02 , I am getting status as 12-Dispatch ok ..Is there any provision to see to which receiver port this dispatch is done..Because the IDOC has been passed

  • Configuration of condition types

    Hi all, pls explain the configuration steps for condition types, thanks in advance

  • Is there a Front Row update in Tiger?

    Is there a way to upgrade Front Row (my version is 1.3.1) without going to Leopard / 10.5 ?