BP604 (Budget Exceeded When posting GR) - Urgent

Dear SAP guru,
We got a problem with our system when we will post GR (BP604-Budget
Exceeded). The scenario is :
Project : NEW-DTCRW101
Our original budget is : RM 16000 (Ringgit Malaysia)
Commitment PO : RM 15564 (7000SGD with exchange rate 2.22340)
Assigned : RM 15564
Available Budget : RM 436.
When we will post GR next day or two days later , the error message BP604 appears. It seems that the system check the available budget and the exchange rate when we do the GR posting.
Many thanks in advance.
Best Regards,
Denis Evitanto

Hi Nies
This note is not for implementaion. It gives the formula used by the system for checking availability control for budget. Please check whether it says some thing about exchange rate for calculation budget availability. Also run CJBN and see whether you are able to post GRN. If its not working then raise an OSS call with SAP as they will be in a position to advise on the right note to implement
Asha

Similar Messages

  • Err:Ntwk actvty 9002367 0050 budget exceeded when calling standard GR BAPI

    Hi experts,
    Error:-604 Item 001 Ntwk actvty 9002367 0050 budget exceeded
    When we post Goods Receipt or Invoice using BAPI_GOODSMVT_CREATE/BAPI_INCOMINGINVOICE_CREATE we are getting the above error message.
    and when we create manually through MIGO we are not getting this error message.
    please any one explain me the solution.

    Can you pelase review following sap notes..
    1008235   No commitment carried forward for commitment value zero
    1030078   Budget overrun with MIRO posting
    734808    MIR4: Error message BP603 when simulating
    1034618  BP 604: Budget exceeded with parked invoices
    Hope above help you..
    Regards
    Siva

  • Ntwk actvty 9000006262 0050 budget exceeded when creating GRN

    Error:-604 Item 001 Ntwk actvty 9000006262 0050 budget exceeded
    When we post Goods Receipt or Invoice using BAPI_GOODSMVT_CREATE/BAPI_INCOMINGINVOICE_CREATE we are getting the above error message.This error message generating when i call the BAPI through  JCO.
    I have tested from front end SAP transcation MIGO and also entered data manually in BAPI
    through SE37, Goods receipt is created successfully, I feel background run created problem when BAPI called from JCO.
    Please any can suggest me the solution.

    Can you pelase review following sap notes..
    1008235   No commitment carried forward for commitment value zero
    1030078   Budget overrun with MIRO posting
    734808    MIR4: Error message BP603 when simulating
    1034618  BP 604: Budget exceeded with parked invoices
    Hope above help you..
    Regards
    Siva

  • 604 Item 001 Ntwk actvty 9000006262 0050 budget exceeded when creating GRN

    Error:-604 Item 001 Ntwk actvty 9000006262 0050 budget exceeded
    When we post Goods Receipt or Invoice using BAPI_GOODSMVT_CREATE/BAPI_INCOMINGINVOICE_CREATE we are getting the above error message.This error message generating when i call the BAPI through  JCO.
    I have tested from front end SAP transcation MIGO and also entered data manually in BAPI
    through SE37, Goods receipt is created successfully, I feel background run created problem when BAPI called from JCO.
    Please any can suggest me the solution.

    Can you pelase review following sap notes..
    1008235   No commitment carried forward for commitment value zero
    1030078   Budget overrun with MIRO posting
    734808    MIR4: Error message BP603 when simulating
    1034618  BP 604: Budget exceeded with parked invoices
    Hope above help you..
    Regards
    Siva

  • Err: Budget Exceeded(when int.order changed in asset) while creating invoic

    Hi All,
    Hope you are all doing wonderfull !
    We have created a statistical order type and wanted to assign them to assets as we don't wanna settle thoze expenses,but needed only for statistical purpose.
    It was okay, when we have changed them in asset master. However, we could not change them in already existing PO's, so when we are trying to create Invoices for the PO's having old internal order number, it is shooting us an error " item xxx order xxxxxx budget exceeded?
    Please let me know how to proceed further to clear this problem.
    Thanks
    Sri

    Hi Sri,
    Can you please elaborate a bit on your scenario. Have you assigned an internal order in asset master record.
    The internal order in asset master record has different purpose. It is used when you want to post depreciation of that asset to internal order.
    Regards
    Chetan.

  • Internal Order Budget Exceeded when creating a PO

    Dear all,
    When we create a PO against an Internal Order, the system displays the message "Item 001 - order X budget exceeded". But checking that order we can see budget available.
    Do you guys have idea the reason of it?
    Many thanks,
    Amanda

    Hi Sreenivas,
    As we are planning to send budget exceed message to responsible person in the internal order, however, from the configuration, it is find that the warning message of budget exceed will send to the budget manager only, and the definition of budget manager is by internal order type and not by individual internal order.
    Please advise how can I send the warning message to the person responsible for the internal order instead of send to the budget manager for the internal order type.
    Thanks,
    Nina

  • Order budget exceeded when creating a PO

    Dear all,
    When we create a PO against an Internal Order, the system displays the message "Item 001 - order X budget exceeded". But checking that order we can see budget available.
    Do you guys have idea the reason of it?
    Many thanks,
    Amanda

    hI,
    You have to check tolerance limit for Order buget.
    Go to SPRO - Controlling - Internal Order -Budgeting & avalibily contrl & ammend the Tolerance limit.
    I hope it will work
    Regards,
    Manish
    Don’t forget to give point if useful ans.

  • Budget Exceeding

    Guys,
    I need help with this scenario. Here is the scenario. When i create a purchase requisition which has an internal order assigned in it, it was counting as a commitment, we didnt want this to appear as a commitment. We applied notes 955106,1227760 and1307755 to fix the issue.
    My problem is fixed for new purchase requisitions but for existing ones the commitment is being double counted and i get an error internal order budget exceeded when i am trying to create a PO
    eg i had a commitment of $ 100 before i applied the notes. My available budget was $90( after the purchase req posted). When i create a PO,  it should just move the $100 commitment from purchase requisition to Purchase order but system is taking commitment of $100 ( purchase requisition + $100 purchase order). Giving me the error message budget exceeded by $110 which is incorrect.
    Note 1227760 talks about this exact issue which is already applied in our system but that doesnt help
    Please advice how i can fix this, business is unable to create purchase orders

    Hi Azam,
    I think in the customization settings for tolerence limit, you have maintained it for TrGr ++ as well as TrGr 01for PO.
    The system will take the priority of 01; so please change the setting to ++ only with warning, error etc.
    After changing the setting advisible to run CJEN and then CJBN if needed.
    Hope this will solve your problem.
    Regards,
    Ganesh

  • Ntwk actvty 9000006262 0050 budget exceeded

    Error:-604 Item 001 Ntwk actvty 9000006262 0050 budget exceeded
    When we post Goods Receipt or Invoice using BAPI_GOODSMVT_CREATE/BAPI_INCOMINGINVOICE_CREATE we are getting the above error message.This error message generating when i call the BAPI through  JCO.
    I have tested from front end SAP transcation MIGO and also entered data manually in BAPI
    through SE37, Goods receipt is created successfully, I feel background run created problem when BAPI called from JCO.
    Please any can suggest me the solution.

    Try to dump the contents of all the parameters of the BAPI call into a temp table when using JCO and if you are still in development box testing this. May be your quantities are getting converted into some big amount due to decimal point placement or comma etc. Check all the conversion exits. MIGO and BAPI execution from SE37 will take care of all your conversions, but if you call it from a program or from an external system, you will have to take care of them including dates.

  • Payment Budget Exceeded Message Number BP 628 & 629

    Hi all,
    We encountered "payment budget for year 2008 exceeded" problem when releasing the Service Entry Sheet in ML81. The message number is BP 629.
    The standard SAP FM report shows that there are sufficient available budget for that funds centre and commitment item. We have also checked and verified that the necessary funds centre, commitment item have been duly created and assigned to the corresponding cost centre and G/L account.
    Would greatly appreciate if you experts can help us with the solution. Many thanks.
    Regards,
    Nathan Janardhana

    Hi,
    Pls check the below SAP notes:
    Note 879348 - Payment budget exceeded when creating a new line item.
    Thanks
    Aravind
    Assign points if helpful

  • Budget exceeded BP604 (when create Invoice)

    Hi All,
    User got an error message budget exceeded BP604 when create invoice. How can i know what the configuration to check why system check budget( Investment management). I tried to check the configuration in SPRO (Define tolerance limit for availability control) shows that budget profile use ++ which are : (no invoice checking) but in actual it checks budget.
    ++     All activity groups           
    00     Purchase requisition          
    01     Purchase order                
    02     Orders for project            
    03     Goods issue                   
    04     Financial accounting document 
    05     CO document                   
    06     Budgeting                     
    07     Funds reservation             
    08     Fixed prices in project       
    09     Payroll                       
    Many thanks in advance.
    Nies

    Business transaction group 04 (Financial accounting document) contains below transactions:
    G/L account posting
    FI invoice parking
    Invoice verification
    Goods receipt for the order
    Cash budget management
    Payment transfer
    Down payment posting
    Inventory difference
    Regards
    Sreenivas

  • Error Message : Budget exceeded for WBS(BP604)

    Hi
    Im getting a message when im trying to post a commitment to a WBS through PO.
    Originally for the WBS element USD-110107117  I pushed down $15K   and yesterday I was told to push down another $40k. Bringing the total to $55K.
    Today I'm trying to cut a PO (73910) for an amount over $15k and it says that the budget exceeds. But if I cut it below or equal to $15k it works.
    But if you check the Budget it's right there are $55k.
    Can you please help me why still im getting this message.
    Your advice is appreciated.
    Thanks and Regards
    Megha

    Hi
    Thanks for this.
    Another question is that this 55000$ is allocated at level 2 WBS USD-110107117. In this assigned amount is 15000$.
    Project is USD-110100000
    The WBS element which im assigning in the PO is at level 4 USD-110107117-B-5656-03 which of now has 0 value.
    So how do i bring down this value of 55K to this level USD-110107117-B-5656-03 .
    Also if i give any amount less that 15000$ it is taking.
    This sounds strange.
    Any help would be highly appreciated.
    Thannks and Regards
    Megha

  • Item 001 WBS budget exceeded error while posting cat7

    Dear Experts
    We have implemented the following modules
    PS , CO , HR
    The project system has number of projects ,
    the time booking is done using cats , the actual labour cost is entered in the cats sheet it self in the price column.
    for cost posting after the data is posted to HR system , we are using cat7 to post the data to controlling and PS module.
    Mostly all the data is transported , but for some WBS i am getting the following error
    Item 001 WBS element <wbs element name> budget exceeded  and the system is not allowing to post data to controlling for this wbs .
    What is the relavance of this error in context of HR ?
    This error is related to which module , PS , HR or CO?
    How do i reslove this issue.
    Regards
    sameer

    Hi,
    Check the budget Limit and allocation of WBS elemet.
    Tcode - CJ30 ,CJ31.
    Check the budget avaialability control as well.I think the message is coming from availability control.
    check transactoin CN41,CJBN.
    check this link
    http://www.sap-img.com/ps001.htm
    Manoj.

  • Budget exceeded error when reversing down payment request via FB08

    Hi Experts,
          I am trying to reverse a down payment request via FB08 but unfortunately its throwing a budget exceeded error, is this normal behaviour?
    Regards,
    Lewis

    Hi,
    Please find the below link it will help full for you,........
    Order Value will be exceeded Msg No. F5373
    Naresh

  • Budget exceeded

    Hi:
       I  am  posting  in FI with wbs,the system gives me the following  error  message:
    Item 001 WBS element ******** budget exceeded
    Message no. BP604
    Diagnosis
    In document item 001 WBS element ***, budget for WBS element *******for fiscal year 2008 was exceeded by 320.00 CNY.
    but  there is stilll enought available budget in wbs(48,200.00 CNY), i confirm in report S_ALR_87013558   the budget is 48200 cny,the actual cost and commitment is zero ; the system should not issue error message, I am so  confused!
    Regards in advance.
    thanks.
    Edited by: junzhi wang on Aug 26, 2008 8:11 AM

    Availability control against overall value
    Indicator which controls whether availability checks are conducted against the overall value or against annual ones.
    Use
    In the project budget profile, the "Overall" indicator, used in conjunction with the "Releases" indicator, has the following effect:
    Ind. 'Overall' Ind. 'Releases' Avail. control against ...
    X - Overall budget
    - - Annual budget
    X X Overall budget released
    - X Annual budget released
    X = Indicator is set, in other words, checkbox was checked.
    if  Ind. 'Overall' Ind. 'Releases'  are both not ticked,it's  Annual budget ;we have done the Annual budget and  Overall budget  already.and some WBS with the same budget profile  have no problem when posting.

Maybe you are looking for

  • Can't find 3d option in photoshop cc

    I Can't find 3d option in photoshop cc

  • SWF tests good, but doesn't work standalone

    Simple flash movie will test fine from within Flash8, but when I double click the swf or access the swf from another site, it won't work correctly. Specifically, I want it to not scale and stay centered in the screen if user decides to open it up. I

  • Which one do you choose? JellyBean or trade-in credit or nothing?

    I read news from Verge : "Motorola also said that it would offer a $100 trade-in credit to those who bought a Motorola phone in 2011 (or later) that isn't eligible for the update to Jelly Bean." Resource :   http://www.theverge.com/2012/9/6/3298835/m

  • DAC Workflow run error code: [36331]

    Dear all , I want to Integrate OBIEE with Oracle R12.1.1 Initially I have defined new container & Phyiscal Data Sources in DAC Datawarehouse Test Connection Successful ORA_R1211 Test Connection Successful FlatFile Connection ? After that I created ne

  • Inter-Company Eliminations in Hyperion Planning

    Hi, I need to implement Inter-Company eliminations concept in Hyperion Planning. I know HFM has a functionality to implement inter-company eliminations.Please let me know that how this concept can be implemented in Hyperion Planning and what steps I