Dear All
I have the following scenerio.
Original Budget (2010)- 100
Released Budget(2010)-100
PO commitment(2010) - 20
Actual (2010)- 30
Assigned Budget(2010)-50
Available budget(2010)-50
I want to Carryforward budget in 2011. Please let me know the steps.
Note: In our scenerio, Investment management is not used.
Thanks in advance .
Regards.
Vishal

Hi ,
Thanks a lot for the answer.
I am able to carryforward budget now.
I found that  CJCO, takes forward,    Commitment + Rem. Ord Plan + Available budget
I have  few queires.
1.  What would happen if CJCF is not used & commitement  lying in the previous year as it is.
2.  What is the significance of using these two t codes
CJEN : Reconstruct ProjectINFO base
CJBN : Reconstruct availability control
Thanks in advance .
Regards,
Vishal

Similar Messages

  • KOCO -( Budget Carryforward)  & KOCF ( commitment carry forward ) report

    Hi
    Can some one explain me how to be sure that some one has  successfully run two t-codes KOCO -( Budget Carryforward)  & KOCF ( commitment carry forward ). I want to make sure that Budget and Commitment carry forward has taken place.Is there any report which I can run.This situation is due to a  person left the organization suddenly and I am not sure he has run it.In any case if I run it again what will  happen ?
    Thanks in advance
    Satya

    Hi Abhinay,
    Thanks for the answer.
    When you say they have to perform year end activities like checking PO and PR, what actually they are doing? Do they just need to check whether those PO or PR are required (if not, close them) or they need to do something more? . As far as I know, no steps like checking PO and PR are required here. So I am wondering whether we have missed anything or not. Can you give me some details about that step?
    Also, if we are using only Total value for the budget, not annual value, I don't need to do the budget carry forward closing step. In this case, do I need to do the commitment carryforward step?
    Thanks,
    Ting

  • Budget carryforward

    Hi all,
    I need to manage a Program structure with Internal Order, for actual and Budget values (Investment management).
    I have created my Program structure with Internal Order.
    Then I have distrbuted Budget over Internal Order (IM52 - Edit ) and done some activities over Internal Ordes (Purchase Orders,...).
    At the end of the year I have some remaining budget so I want to carryforward it to next year.
    Steps I do are:
    1- IM27 - Open New Approval Year
    2- IMCAOV - Budget Carryforward.
    After running this last, the system tells that everything is Ok, but if I query a report (ex.: S_ALR_87012824 - Budget Availability in Program ), I don't see the new values on the following year.
    Ex.:
    2009: 100 (Actual 50)
    2010: 100.
    After budget carryforward I would expect to have:
    2009: 0
    2010: 150.
    But nothing is changing in terms of values.
    Can anyone help me?
    Thank you
    Edited by: Caforio Claudio on Mar 17, 2009 3:37 PM

    Hi Caforio Claudio,
    Pls check if you have (If the Investment Measure is Internal Order)
    You performed the commitment carryforward for measures belonging to the investment program - KOCF
    You performed the budget carryforward for measures belonging to the investment program - KOCO
    which are pre-requisites for Budget Carryforward for Investment Programs...
    Pls check and revert back...
    Srikanth Munnaluri

  • Budget / Planning Process

    Hi,
    My company would like to use the budget process in SAP to keep track of actual vs budget / Panning.
    Can some one provide me the full configuration setup for the budget / planning process ?
    Like creating budget version or plan version, entering of planned values, any need to create additional accts or used of secondary accts ?
    Thanks.
    Angel.

    Dear,
    If you are using Funds Management then you can have the budgeting funcitonality at very deep level.
    If you are not using FM then use Internal Order functionality to meet your requirement. Do following to get this done...
    1. Create Order type with category 01. (Tcode - KOT2)
    2. Create Budget Profit and insert this into order type created in step1. (Tcode - OKOB)
    3. Define tolerance for an Internal Order type which is located in SPRO>CONTROLLING>INTERNAL ORDER
    4. Create internal order.
    5. Assgn budget to internal order.
    Regards,
    Chintan Joshi

  • Budget Release Process

    Hi
    Planing to use budget release process on monthly basis, done relevant configuration but release process is not working
    For release done following configuration:
    Define Release Scenario
    Define Budget Types for Release
    Assign Budget Types for Release to Processes
    Kindly advice where I am missing
    Regards
    Upendar

    Hi
    Thank you for reply
    Sorry for later reply
    I will explain requirement:
    1. we are planning to annual into 12 portions and for this each portion I am trying to use release process
    2. Can you please let me know if I want to use release process what is process to be followed, done the following configuration for release process
    Define Release Scenario
    Define Budget Types for Release
    Assign Budget Types for Release to Processes
    3. In FMMBC what is the selection we have to use while entering budget with release process
    Regards
    Upendar

  • Open Item & budget Carryforward.

    Dear All!
    we are little bit confused regarding the closing procedure of  Funds Managment ( BCS).
    I'm writing the following scenerio that may I able to understant every one!
    I entered the Budget $100 and Released $ 40. When I execute the transaction FMRP_RW_BUDGET for budget overview, system display the following Information:
    Current Budget : 100 , original budget : 100 and by executing the FMRP_RW_BUDCON transaction. system display the following information
    Consulabale budget: 40 Consumed Budget: 0 Avilabale Budget : 40 and Current Budget: 100.
    Now I created the purchase order : 30, then system displaying the information by exeuting FMRP_RW_BUDCON  the cosumed budget 30  and available budget : 10
    and current budget : 100
    I carryforward the  open item (purchase order) to next year, system forward the open item & display the following information in next year by executing the above reports
    Transaction: FMRP_RW_BUDGET
    Current Budget : 30 Orginal : 0
    when I carryforward the residual budget, system carry forward the $ 70 to next year and the amount $100 is still available for release & consumabale, also the current budget become again 100 by forwarding the budget.
    please expalin what the system is doing is ut correct? why all the amount still available for consumable?
    please tell me following are the correct sequance of closing.
       1- Open Item
       2- budget ( with key figure YE_RESIDUAL)
    further, in what cases the transaction FMMC-close open item is being used?
    Thanks

    Hi MSiddique,
    We are a governmental entity. We use FMMC to close out prior year obligations (encumbrances - i.e. purchase orders, purchase requisitions) that will not get carried forward into the next fiscal year.
    For the encumbrances that remain open and will get carried forward to the next fiscal year, we use FMJ2.
    So for instance if we have 100 original and 100 current in starting out in FY06, and we have an existing purchase order for 20 and 35 was already expended (i.e. invoiced and paid), the consumed would be 55 and the available would be 45. At the beginning of FY07, only the existing encumbrances that we didn't close using FMMC will be carried forward along with the related budget of 20 using FMJ2. If 45 wasn't used it would not get carried forward (unless it involves a multi year capital project)
    The FY06 Budget would look like this
    Original 100
    Current 100
    Encumbered 20
    Expended 35
    Consumed 55
    Available 45
    After the carry forward to FY07 would look like this
    Original 130 (new approved budget for the new year-not related to FY06)
    Carryforward 20
    Current 150
    Encumbered 20
    Expended 0
    Consumed 20
    Available 130
    We had to create custom reports instead of using the standard reports.
    Our sequence of closing is as follows...
    All requisitions not converted to a P.O. gets closed - FMMC
    All P.O.s identified not to roll forward gets closed - FMMC
    All remaining P.O.s are carried forward FMJ2
    FMJ2 rolls forward the remaining P.O.s as well as creates a budget document for the new fiscal year (but we keep it seperate from the original by using a carryforward column. I hope this helps.

  • Workflow Planning Unit Ownership - Begin the budget review process

    As an Admin, is there a way to assign multiple planning units with an import option or something like that? Right now the only option I see is to go in one-by-one and start the fcst cycle and then assign the ownership to the person who is entering the budget information. I have 150 Entity members to assign for one forecast cycle and was wondering if there was a "smarter" way to do this.

    Hi!
    We are referring to the same example of wf for which you answered some time ago. But we need to extend the process to the whole entity dimension. Thus we have this situation.
    our entity dimension: --> http://postimage.org/image/d3utdauzn/
    Our wf process:
    free format wf. (since the entity hierarchy does not follow a linear path: bottom-up or top-down)
    1.ENTITY 1 inserts data and submits them to a reviewer.
    2.the reviewer approves or rejects data.
    3.then the process should be sent to ENTITY 2,3,4 (lower levels of ENTITY 1) to start to modify/adjust data that ENTITY 1 has imputed and distributed to their levels trough a rule.
    the problem is at the 3rd point. How could ENTITY 1 or the REVIEWER pass the process to ENTITY 2,3, and 4 at the same time? I see that I cannot make a group of users owner of one PU, and then limit their level trough the provisioning. The only solution that I have found for this is to send an e mail to ENTITY 2,3,4 and then let them start to input their data (the drawback in this case is that they can always modify data in cells for which they have the write provisioning , and not only when the reviewer has approved data.
    moreover in the case the reviewer approves data sent by ENTITY1 he becomes the new owner of the PU, that is the only way trough which ENTITY 1 cannot modified them after the approvation)).
    Thank you very much.
    Edited by: user648334 on Jun 6, 2012 2:51 AM

  • User budget in process controlled workflow

    Hi,
    Is it possible to use the 'user budget' option with the new process controlled WF ? If it is possible what are the necessary customization that need to be maintained ?
    Thanks

    Hi Sarvanan,
    The requirement is to have approval process based on the user budget .
    For ex if a user has been assigned a budget of $5000 per month, then for shopping up to a cumulated value of $5000 no approval is required($5000 spread across multiple purchasing docs ; not restricted to a single document) . However when the cumulated value of purchasing documents in a single month by this user exceeds $5000, then the documents is routed for necessary approval.

  • Create GM Budgeting Release Process - GM_BDGT_RELEASE

    Hi,
    Our client wants to load Budget data which includes both FM and GM data. and we are using 4.7ver.  For FM we are using FMBB transaction and for GM we are using GM_BDGT_RELEASE transaction.Grants master record is already created using GMGRANT transaction. We tried to do a BDC for GM_BDGT_RELEASE transaction, but in shdb it is not showing the table control details.
    Then we searched SDN and found some notes to use BAPI_0036_CREATE function module. when we are trying to use this function module, but we are getting some BAPI errors.
    Below are the errors:
    1.Released budget for unreleased/released scenario is not supported by BAPI
    2. No instance of object type BudgetEntryDocGM has been created. External reference:
    Have any of you tried to create document using GM_BDGT_RELEASE transaction. If so please tell us the process to do.
    Thanks.

    Hi Rob,
    Thanks for the email.
    Now it is fixed. I'm able to create Budget for GM in 'unreleased' status. but this BAPI is not posting the budget to FM.
    Do you know how we can post grants budget to FM.
    Thanks.

  • IO Budget Carryforward

    Hi,
    Can someone pls help me understand this....
    In KO23;
    Initial budget was EUR 415,000.00 on FY2007.
    Actual cost on CIP was EUR 308,213.25 on FY2008.
    Negative amount was posted EUR -308,213.25 on FY2009 (from Disposal FA-Proceeds).
    When budget was carried forward to FY 2010, EUR 106,786.75 was carry forwarded.
    Is this correct?
    I think the negative amount should have been added as well and carry forwarded total EUR 415,000.00 to FY10. 
    Thank you,
    NH

    Can someone PLEASE answer this?
    Regds,
    NH

  • How to do Commitment item carryforward (Fund Management) ?

    Dear experts,
    Please guide me how to do commitment item carryforward.
    I've read thought SAP help, it said I need to do commitment item carryforward.
    But I have no idea, what's the transaction code, what parameter to fill in..
    Kindly guide me or send me related document...please....
    [FM Newbie]

    T code : CJCF - Carry Forward Commitment
    Parameters: - Carrying Forward Commitments
    To carry forward a commitment to the first period of the following fiscal year, proceed as follows:
    Choose Accounting ® Controlling ® Cost Center Accounting ® Year-end closing ® Commitment carried forward.
    Enter the relevant cost center(s).
    Select or deselect the following indicators:
    Test run
    If you select Test run, the system carried forward the commitment, but does not update the results.
    Detail lists
    If you activate Detail list, the system displays the results of the commitment carried forward. The results list shows which values were carried forward.
    You should activate the Detail list together with the Test run. This ensures that you can check the results of the test run.
    Reversal
    The Reversal indicator controls whether data that has already been carried forward should be reversed again or not.
    If you have large amounts of data to process, it is advisable to execute the commitment carry-forward using background processing. This means you can process data at times of minimal system usage.
    Choose Program Execute in background.
    SAP help : - Year-End Closing Reports  
    The reports on year-end closing give you an overview of the closing operations (commitment carryforward and budget carryforward) with fiscal year change.
    The reports display totals records. A comparison of the line items transferred to the new fiscal year with the totals is possible using the program (RFFMCFRC) Year-End Closing Data: Totals Records on Line Items
    Features
    ·        Commitments and budget carried forward (RFFMEP1GX)
    This report displays commitment, budget for commitment and budget for a fiscal year that were carried forward to the following year.
    ·        Commitment carried forward in a test run (RFFMEP2GX)
    This report displays commitment belonging to a fiscal year that was carried forward to the following year in a a test run using the Commitment Carryforward
    ·        Preselected budget (RFFMEP3GX)
    This report displays budget for a fiscal year that was determined for the carryforward into the following year with the program RFFMCF25.

  • Procedure to carry forward Un-utilized commitment budget

    Hi all,
    what is the T.code & process to carry forward the "Un-utilized commitment budget" from one fiscal year to other fiscal year. ( since FR34 is in 4.6) please let me know new T.code & process in ECC6.0
    Rgds,
    Swathi.
    Edited by: swathi fico on Dec 15, 2008 7:59 AM
    Edited by: swathi fico on Dec 15, 2008 9:08 AM
    Edited by: swathi fico on Dec 15, 2008 2:40 PM
    Edited by: swathi fico on Dec 15, 2008 4:54 PM

    Hi,
    As per your request you want to know the transaction to carryforward COMMITMENT BUDGET.
    Carryforward process with Former Budget
    ================================
    If you are using Former Budget and you want to carryforward commitment budget, you should ONLY run the following steps:
    Prepare Budget Carryforward (BPINDX05)
    Carrying Forward Budget to the New Year (RFFMCF30).
    Note that you can only carry forward commitment if the definitions made in the default settings for the year-end operations of Customizing for Funds Management Government allow this. For more information, see the IMG of Funds Management Government, section Enter Default Settings. Using program RFFMCFM1 Monitor Closing Operations, you can get an overview of the current Customizing settings.
    The Commitment Carryforward must be executed before the budget carryover because the budget tied to the commitment is included in the calculation of the residual budget.
    If you are using the function Revenues Increasing the Budget (distribution procedure), you must use the corresponding program to execute the budget increase. For more information, see Increasing the Budget in help.com.
    Carryforward process with BCS
    ================================
    You must define the parameters used for the commitment carryforward. Budget changes in the previous year and/or the following year depend on whether you use the statistics indicator for the commitment carryforward.
    You should use transaction FMMPCOVR to run the carryforward process. Please check the documentation of this program (RFFMMP_COVR) via SE38. You will find not only information text but links in order to check all the needed customizing settings in order to run the carryforward process.
    =================
    You can find more information in help.sap.com in the menu:
    Public Sector Management -> Funds Management -> Closing Operations -> Budget. There you have
    2 submenus:
    Budget Control System (BCS) and
    Former Budgeting
    I hope it helps you
    Best Regards,
    Vanessa.

  • In internal order budget can we maintain for calander year

    Hi,
    my client presently  doing their planning and budgeting  in internal order for financial year but
    they need the planning and Budgeting figures as per calendar year in the SAP  can any body sujest me.
    Thanks & Regards
    Ram

    Hi Den,
    You can do the budget carryforward of internal orders to the next year in the year end closing by TC KOCO.
    Further information is available at
    http://help.sap.com/saphelp_47x200/helpdata/en/96/248f38661fca77e10000009b38f842/frameset.htm
    I hope this helps..
    Regards,
    Suraj

  • Budget C/F

    Hello,
    This is regarding New F.Y 2010.
    I have opend new F.Y 2010 -11 and C/F all G/L and customer and vendor balances.
    Also opened F.Y 2010 - 11 for Asset. Every thig is OK.
    Now i have some budget balance for F.Y 2009 - 10.
    Shall i C/F Balance for 2010 -11
    Shall i execute KOCO (Budget Carryforward) or Only KOCF (Commitment Carryforward).
    Now for new purchase Order entry is not allowed using same Internal order of F.Y 2009 - 10.
    As i understand , If i want to use balance amount of same Order for new F.Y 2010 -11 i have to execute KOCO.
    But inthat case now if i enter MIGO in March,2010 thne balance showing -ve for F.Y 2009 - 2010.
    Pl suggest me correct way , how to goahed .
    Regards
    Swati Shah

    .

  • Internal order - budget leftover in previous year

    Hi all,
    We have an internal order from 2005 that had a pr/po deleted, freeing up some budget to be used now in 2006.  Since 2005 has been closed out, how do we use this 2005 budget in a PO for 2006?
    Thanks in advance,
    Den

    Hi Den,
    You can do the budget carryforward of internal orders to the next year in the year end closing by TC KOCO.
    Further information is available at
    http://help.sap.com/saphelp_47x200/helpdata/en/96/248f38661fca77e10000009b38f842/frameset.htm
    I hope this helps..
    Regards,
    Suraj