Change of GL code in Maintenance Order

Dear All,
We have got a requirement that when stores is issuing maintenance material against reservation created through a maintenance order the default GL consumption Ac debited is " Consumption of Stores and Spares Indigenous " , instead of this GL code " Repairs & maintenance " GL code should be hit .
How do we configure the same in system. Useful answers will be rewarded with points.
Regards
Milind Nair

Hi,
Thanks for the reply but if I do the changes it will be at company code level , I want the accounting effect to occur only in case of material consumed against maintenance order that too for some specified plants only.
In case stores are consumed against production order then it should not hit repairs & maintenance but it should hit stores and spares consumed . Hope I am clear pls get back if you need any further clarifications.
Regards
Milind Nair

Similar Messages

  • Can we change company code in maintenance order

    Hi All,
    We have changed the maintenance plant of Equipment from 1100 plant to 1200 plant.
    Planner group is by default appears in work order once the technical object is selected in order creation.
    Can we change the planning plant and company code in maintenance work order?
    Thanks in advance
    Surya

    Dear Friend,
    you moved equipment from one plant to other plant, but company code is same know.
    Actually its not possible to change the company code in maintenance order.
    once you shift any technical object from one location to other location, do change the technical object materdata also.
    for your question you change the equipment masterdata so that u new planner group will triggeer in main.order.
    Regards,
    pardhu

  • Change the Tax Code-  In Sales Order i have  Tax code for VAT

    In Sales Order i have  Tax code for VAT ( Condition type JIVP) it is reflecting "P4" instead of "A4".
    Where the "P4" Tax code is picking in Sales Order.
    How to change the Tax Code.
    Urgent

    Hi CHAKRI,
                     Check if the condition record is maintained with the appropriate taxclasssification.If yes, Go to sales order in change mode,then goto-header-billing-alternate taxcalssification and modify tax classification.It will pick up right tax code.
    Regards
    Ram Pedarla

  • Prevent changes in Component of a maintenance orders

    Hi Experts,
    I have two questions:
    1. Is it possible to restrain and changes to Component line items (Materials) in maintenance order once it's released except for allowing deletion of the material?
    2. Is it possible to make the filed "Item Category" as Display right when entering the materials in a maintenance order to prevent users from the changing the IC which is defaulted from Material Master?
    Once I set it as Display it only takes an effect once we enter a material number and press enter but if a user changes the IC before that the system allows it.
    Please help

    Hi,
    For question 1:- Use User exit PPCO0023 : Check Changes to Order Components
    For question 2 :-  In our project we have used use exit CNEX0013 Order: Cust. enhancement: Default item category comp. assgmt to populate item category once material no is entered & grey out the field ..
    pls check the above user exits ..
    regrds
    pushpa

  • Restrict changing the tax code in purchase order after goods receipt.

    Hi,
    Po is created with tax code x1.
    Gr is done for partial quantity.
    IR is still pending.
    User has changed the tax code to x2.
    This case we want to restrict the tax code change in PO after goods receipt.
    Please advice.
    Regards
    Ravi Kumar

    Hi Sumit,
    Po created with wrong tax code x1.
    Stores person has done the receipt and consumed the stock.
    Now user has suddenly realised that tax code is wrong and changed the tax code in PO.
    In IR we will use correct tax code and post the accounting entry.
    Stock values will be adjusted properly. to stock ac if stock is there and to price diff ac if stock is consumed.
    Point is user's are asking that how system is allowing to change the tax code after receipt.
    Point to be attended is restrict the change of tax code by any means after Gr has happened.
    what are the possibilities to restrict the change of tax code.
    Regards
    Ravi Kumar

  • How to restrict changes of material quantity in Maintenance Order

    Hi Expert,
    How can i restrict the user to change the material and quantity in the Order's components tab.(IW32) Eg, not allow changes after RELEASE.
    Can the system keep track on all the changes for material number and quantity in the Orders?
    Please Advise
    Thank You
    Best Regards

    Hi,
        Better way is grey that tab after releasing the MO .. try BADI ;-IWO1_SCREEN_MODIFY Field Content and Display Modification
    You can also explore User exit ;-PPCO0023 : Check Changes to Order Components
    FM ;- STATUS_READ
    regards
    pushpa

  • Change material code in process order or delete process order

    Hi experts,
    While creating a process order in COR1 transaction code, wrong material code was entered.
    Can we change the material code in process order.  If not, what is the complete procedure to cancel or delete the process order.
    Request you to revert.
    Thanks in Advance.
    Regards,
    Farha.

    Dear ,
    One the Process Order has been created with any material either it is wrong code or correct code , it can not be deleted .If it wrong code , then do not  perfom goods Issue -MIGO-261 or through Backflash  and also operation confirmation etc .
    If Goods Issue , Confirmation happend then you need to reverse those txn once again .
    In that case the best oiption will be goto COR2-Enter the Process Order -Select Process Order from Header -Restrict Processing -Choose Technically Complete .
    Now , once you did TECO , then there will not be any farther txanationl posting like Goods Issue , confirmation will not be possible .Likewise , you can also Lock or make set CLOSE  from COR2 in case there is no WIP , Variance .
    Hope this is clear
    Regards
    JH

  • Download Maintenance Orders instead of Production Order in SAP IM-3.2

    Hi All,
    I am trying to fetch Maintenance orders instead of production order in syclo agentry IM-3.2
    In the receipts screen their is a button GetProdOrder which fetches the Production order,instead of fetching the Production Order i want to change it to fetch the Maintenance Orders.
    please suggest me steps for the above change.
    Thanks ,
    Deepak.M
    Tags edited by: Michael Appleby

    Deepak,
    I don't think this will be easily accomplished.  The BAPI is written specifically for production orders.  I believe it would require changes to the BAPI itself, or changing the java to point to a different BAPI.
    Jason Latko - Senior Product Developer at SAP

  • In ALE/IDOC Change Pointer using Maintenance order for message Type

    Hi All Expert,
    I am using Maintenace order to send via ALE/IDOC(Change ponters), i need standard message Name for Maintenance Order,

    Hello,
    I'm not sure you're taking the best approch.
    Usually when you need to migrate ISU contracts into an ISU-CRM integrated system, you first migrate everything you need in ISU through the VERY powerful migration workbench available (transaction code EMIGALL), and then you replicate your data to CRM via INITIAL download.
    That's definitely the strategy that will give you the best performance, and less work.
    Kind regards,
    Nicolas Busson.

  • While creating Maintenance order using t-code iw31 mainwork center not pick

    Hi,
    while creating Maintenance order using t-code iw31 Maintenance work center not picking from drop down (already have in drop down)but giving manually accepting.
    --Ganesh

    Hi,
    My understanding is that the selected work center is not copied into the input field. This can be corrected with note [1451299|https://service.sap.com/sap/support/notes/1451299]. Check if the note is relevant for your system.
    -Paul

  • How to change Unit for Breakdown Duration in Maintenance order.

    Hello,
    In cuni, somebody created Unit "TST" by mistake, system can not convert it to "second" for calculation automaticlly.
    "TST" make no sence. So if maintain "TST" as Unit for Breakdown Duration in a maintenance order, dump will happen. However there is a maintenance order maintained Unit for Breakdown Duration as "TST" saved by mistake, Dump will happen when I try to access to this order by IW32 to change the Unit for Breakdown Duration. Is there any way to change the Unit for Breakdown Duration"TST" to "H" so that I can access to this order by IW32.
    Thank you.

    Hi,
    You could temporarly adjust the CUNI definition for TST so that it can be converted to seconds. Adjust the notifications to set a valid unit of measure.
    The alternative would be to update the field MAUEH in table QMIH with a valid breakdown unit of measure.
    -Paul

  • Changing Tax Code in Sales Order

    Hi All,
    I've a requirement to change the tax code of MWST CT from normal value XX to a new tax code in sales order for few excpetion cases.
    For normal cases the tax code will always be XX for MWST CT in the sales order. However for very specific business need the tax code for the existing sales order needs to be changed to a new value. The need for changing the tax code always arise after creating the sales order.
    Kindly suggest the possible ways to meet this requirement.
    Regards,
    Ashish

    Changing the tax code in the sales order is not std sp procedure and I don;t think sp allow tampering with it either.
    The taxes are based on the combination for customer and material and I suggest that you maintain all tax codes at the material and customer level for all combinations possible and each customer is alloted one unique one.
    What are the possible reason why tax changes. It can only be the delivery address is changed. If the material iself changes then you may have to modify the sales order itself but if there is a change in the ship to party then....
    Now if the shipto party changes then you can always redetermine taxes in billing where the actual taxes will be redetermined based on the new conditions.
    If you see the tax line item in the sales order you will see that it is greyed out.
    You can change the excise duty but not taxes.
    This is the default where the condition type is prohibited from changing manually. But if you change the setting to Free or manual then you can change the value of tax bu the tax code will be as determined by the combination of material and shipto.
    regds
    Jude
    Edited by: jude xavier on Sep 7, 2008 8:23 PM
    Edited by: jude xavier on Sep 7, 2008 8:24 PM

  • How to change planning plant in Maintenance order

    Hi experts ...
    In maintenance order , depending on equipment , the planning plant gets defaulted . If Equipment is installed in another FL whose planning plant is different , the order's planning plant doesn't change (Greyed) . Is there anyway to change planning plant in orders
    NPB

    We have maitenance and planning plant same .Equipment was in maintenance plant XYZ and planning plant XYZ earlier . Now the same equipment is in maintainance plant ABC and planning plant ABC . In order , I am able to change maintenance plant  to ABC , but unable to change the planning plant to ABC .
    If I do not change planning plant and change only maintenence plant , what are the effects in cost reporting ? Since ultimately cost is settled to equipment cost center (which is now changed to ABC cost center) , I feel there will not be any effect . Old planning plant may only affect search right ? ....Please advise ...
    NPB

  • Vendor code in Purchase order changed after invoice,net price showing zero.

    Dear Experts ,
    In one purchase order , user had done GR & invoice for a line item ( service ),item category "D" , and
    thereafter somehow the system allowed user to change the vendor code. The PO line is now having amounts in
    the sub-service line items , but net price for the line item is showing as zero. Since the PO was made
    directly without any contract/RFQ/PR , there is no reference document or info record shown against the line
    item.
    In the conditions tab of Item details,the condition for basic price is not seen & since there are no amounts
    applicable for the other conditions such as insurance , octroi etc., the NET price shown for the item is
    Zero, which is also getting printed in the PO as zero , which is not acceptable , as we can not send to the
    vendor PO copy having prices for individual services printed correctly but the total gross price showing
    zero.
    Pl advise what can be done so that Net Price is shown correctly & not zero.

    I think the new vendor is having a different pricing schema than the old vendor. Check the pricing schema for the old vendor (in purchasing view in field 'Schema Group. vendor) and compare it to the new vendor. I think they're different.
    If it is then what i think happening is the user already input the price for the condition type in pricing schema A, then the vendor is changed and the new pricing schema is kiciking in thus making the old condition type missing.
    Try to either:
    A. Change to the old vendor back,
    B. Change the pricing schema of the new vendor to be the same with old vendor

  • Changing basic finish date in Preventive maintenance orders

    Hi Experts,
    My requirement is to block PP work centre when maintenance schedule the equipment for preventive maintenance. I am making system condition as zero in generated preventive maintenance order but basic finish date is not changing in the order automatically. Can anybody please explain how to bring this? Finally my requirement is system should change basic finish date and time as time given in operation of task list.
    Thanks in advance.
    best regards,
    Srinivas M

    Hi Praveen,
    I have done all setting and tested but there is no change.
    My client requirement is like this - whenever maintenance plans are scheduled, for the scheduled dates, production capacity should not be considered by production. We could do this for breakdown orders but not happening for PM orders unless we change the finish date.
    The issue is to get the finish date automatically when scheduling maint.plans with respect to values given in operations. Please suggest how to get the  basic finish dates automatically.
    best regards,
    -Srinivas

Maybe you are looking for

  • How to find out who has deleted my query

    Dear SDNs, My query has been deleted in Prd system, so I want to know who did it. I try to get the log from SLG1 and SM21, but I can't get any information about the query deletion. I have also tried to read record from table RSRREPDIR, and this table

  • I have a new iPod touch. I've synced it through Itunes. None of my iTunes purchases show on my iPod now. Help....

    I've been trying to download some games to my son's iPod touch. I have several now in my iTunes library and have synced the iPod many times. They still do not show up on the iPod.Also, when I click on the purple iTunes app on the iPod it says that it

  • All Lumia 928 folders are 'read-only'

    So all of a sudden, all the folders on my Lumia 928 are marked as read-only regardless of the PC it is plugged into, and I can no longer drag and drop files between the phone and PC because of it - it tells me I don't have permission or something lik

  • How to use a decode function

    I want to use the following with decode, recently started on BODS. Can you please provide the steps to use decode function in source tabke fieldname is ordid and in target fieldname is Orderid decode(Order_ID = 1709,lpad(Order_ID,7,'700'),Order_ID) t

  • Workflow - RFC Status  -- User is locked

    Hi , experts I prepared a  workflow and  tested it with   PFTC_DIS transaction.           there was no problem .But when i trigered this workflow event in my program , workflow not worked. I used SWEL and SWELS programs to traced it. The list is belo