Changing Purchase Reqs after release.

After releasing a Preq (Cost Centre), if we attempt to change it in ME52N everything on the line's display only. So I can't increase the qty for example and send for re-approval (trigger the release strategy). This is normal?
The Changeability indicator in OMGQ for the release indicator (F - released) was blank. I changed this to 4 but neither allow us to change the Preq after realease. Could you maybe advise please? Is it possible to change the req after release, seems odd I can't?

Hello,
  in customizing for release indicator, you must check also field "Field selection key" which is defined under "Material management --> Purchasing --> Purchase requisition --> Define screen layout at document level". You should check the "Field selection key" assigned to your release indicator: that key defines the mandatory, optional and view-only fields in Purchase documents, and can be linked to a release status.
Hope to be useful.
Best regards,
Andrea

Similar Messages

  • Change message status after release purchase order

    Hi,
    I'm a newbie in MM...
    When a purchase order is created, the message status is not processed (yellow light) until the purchase order is released. Then the message is printed and the status changes to green light.
    As far as I see, I can't find in the spro where is this customizing set or if there is a user-exit or badi for changing the message status depending on the release indicator.
    Thanks in advance!
    Jen

    Hi Jen,
    Complete the condition record, for example, like this:
    - Transaction: MN04
    - Output Type: NEU
    - Choose third option: Purchasing Output Determination Document Type
    - Document Type: NB
    - Function: VN (Vendor)
    - Medium: 1 (Print output)
    - Date/Time: 4 (Send immediately (when saving the application))
    Select the line and press button "Communication". Complete the output device and mark the option "Print immediately"
    So, when the PO is created the system generates the message with yellow status. Then, when the PO is released, the message status will be green
    Regards,
    Fernando

  • Automatic ORDCHG Change Purchase Order after Order response from Vednor

    Hi
    How to trigger Change Purchase Order action after receiving PO Confirmation - Order Response from Vendor.
    The scenario is that Order Confirmation vednors sends contains delivery date or delivery qunatity variance within defined tolerances. In such cases it is acceptable to allow automatic PO change.
    This is an EDI scenario. Idocs ORDRSP and ORDCHG in use.
    Thanks for hints.
    Mariusz

    - For automatic document adjustment, you must make the necessary settings in Customizing (SPRO ->Materials Management->Purchasing->Conditions->Automatic Document Adjustment). The system logs all the relevant purchasing documents and can therefore determine all the documents affected by a change to a condition.                                    
    - This is only possible for purchasing documents for which follow-on documents (goods receipt, invoice receipt) do not exist.           
    - Before you run this report, you must have run report RMEBEIN4 (creation of worklist for automatic document adjustment).

  • Changing a Budget after release in ECM - Urgent!

    After a budget has been created and released in ECM can you add new Budget Units?
    For example,  if a few days after we release the budget we need to move some people into a new Org Unit.  Right now we've noticed that if the Org Unit wasn't around when the budget was created, it is not recognized.  Is there any way to change this?
    Any ideas or suggestions would be greatly appreciated!  Thanks!

    Thank you for your reply. 
    This is true, but you can't reset it to planning if some of the budget has already been allocated (which is the case in our situation).
    Has anyone else had this issue? 
    If someone else has tried this and it is not possible that information would be helpful as well.
    Thank you!

  • Transaction me52n (Change Purchase Req.)

    Hallo Dear Experts,
    in the Standard Program of me52n there is no menue (button) to print Purchase Requisitions.  Is it possible to extend the Menue with printing functionality? Has any body an Example for that.
    Thank a lot and Regards
    Fisseha

    Output in sap is available for External Purchasing documents (eg: PO, Contract, RFQ etc.).
    PR is internal document and we can not output this. No standard transactions available for this. However print out can be obtained from the Item level

  • PR quantity change after Release

    Hi Friends,    
                                       I am unable to change PR Quantity after release of PR. Please suggest..
    Regards,

    hi,
    When you set up the release strategy there is an indicator for the changability, which states that whether you wanna make the further changes in the PR doc, once it is released...
    So, if you wanna allow the changability for the PR docs, then you can use the any of the indicator among 4, 5 , 6 as per your req....
    by this you shd be able to make changes...
    Regards
    Priyanka.P

  • Userexit for release procedure in purchase req

    hello!
    I am looking for userexit to influence the way the system reacts if a purchasing document is changed after the start of a release procedure.
    regards
    yifat

    Hi
    Changes to PO after release procedure started resets the realease . I am not sure what exactly is your requirement. Can you give more details ..
    Cheers

  • Purchase req type after MRP Run

    Ca we control the type of Purchase req after MRP Run.
    Now for every material it is creating "NB" type purchase req.
    Can we control it material type or by mat number.
    We have 2-3 purchase req types in system for Material.
    Amit Shah

    Dear ,
    Goto -OPPR-Enter Plant Code and Maintain MRP Group -0000( as SAP Standrad for External Procurement ) -Select Scheduling /Doc Type tab -Here you can assing the PR type as per your requirement so the while MRP run , it will selct the PR documents types based on OPPR .At the same time , assing this MRP group in MRP1 view of the material .
    Try and come back
    Regards
    JH

  • Not allowing users to change qty in PM order after release

    Hi
    I am using the user exit  IW010009(customer check for save event - ZXWOCU07 to control the permit functionality against the plan cost in the PM order, which is functioning well. But I have a requirement to check , the below scenario.
    In IW31, the user creates the order with component “A” and qty 10 having value more than the permit value (say Rs.5000/,) and if he tries to release the order, the system does not allow the user to release the order. The user goes and changes the qty of the component “A” to 3 and the value is less than Rs 5000. The user successfully releases the order, but doesn’t save. He then goes to the component tab and changes the qty to 10 and save the order.
    I need some help to control the user action, of changing the qty, after release. Is there any table/function where I can find the order no and the qty entered after release of the PM order and  before saving.
    I have done some coding for WBS entry (customization) and the permit in the user exit IW010009.
    Regards
    Vidhyadharan

    Hi Jogeswara Rao
    I have pasted below the requirement from my original thread
    "I need some help to control the user action, of changing the qty, after release. Is there any table/function where I can find the order no and the qty entered after release of the PM order and  before saving."
    Regards
    Vidhyadharan

  • What happen if I change a role after I released the transport?

    Here is my Scenerio:
    1) Assuming I've created a role : ROLE1 in DEV
    2) I create a transport TR1 with that ROLE1, NOT yet released.
    3) Then I added ME21 txn to ROLE1.
    4) Then I released the transport TR1
    5) Then I remove ME21 txn from ROLE1.
    6) Then I transport role from DEV to QA.
    Q1) I would expect In QA, ROLE1 will still has ME21. - True?
    Q2) TR1 will be the snapshot of the ROLE1 when I release the transport TR1 - True?
    Now, I want to delete the ROLE1,
    A) I would need to create another Transport TR2 first with ROLE1 in DEV
    B) Then delete ROLE1 in DEV
    C) Then release Transport TR2
    D) Then I decided that I still need ROLE1. (oops)
    Q3 I should not transport TR2 so that it won't delete it in QA. - True?

    Hi Dominick,
    >
    > 1) Assuming I've created a role : ROLE1 in DEV
    >
    > 2) I create a transport TR1 with that ROLE1, NOT yet released.
    >
    > 3) Then I added ME21 txn to ROLE1.
    You should add the role again to the Transport to avoid inconsistency
    > 4) Then I released the transport TR1
    >
    > 5) Then I remove ME21 txn from ROLE1.
    >
    > 6) Then I transport role from DEV to QA.
    > -
    >
    > Q1) I would expect In QA, ROLE1 will still has ME21. - True?
    Answer: If you reassign the role to the TR then you will get.
    > Q2) TR1 will be the snapshot of the ROLE1 when I release the transport TR1 - True?
    Answer:  TRUE (but without ME21 if you don't add the change to the CR - see below for detail discussion)
    > -
    >
    >
    > Now, I want to delete the ROLE1,

    > A) I would need to create another Transport TR2 first with ROLE1 in DEV
    >
    > B) Then delete ROLE1 in DEV
    >
    > C) Then release Transport TR2
    >
    > D) Then I decided that I still need ROLE1. (oops)
    > -
    > Q3 I should not transport TR2 so that it won't delete it in QA. - True?
    Answer:  TRUE. And if you want the role again back to DEV without recreating it, please download the role from QAS or PROD and then Upload it to DEV. After that you need to generate the Profile of the role.
    > -
    FYI:   When a Change is Included into a request to send in other systems, then this request is called "Change Request" (CR). After Releasing, the CR called as "Transport request".
    CRs are basically (in layman language) the Pointers to the DB changes performed. These are included into a CR as "Task". A CR can contain multiple Tasks created by different users.
    Please note if this is a Workbench CR then it is ONLY editable by that particular user(owner of the Task). Also the Object captured in a Task of a WCR possesses a Lock till it gets released and thus can't be added to any other Task of a different CR. The Objects are unlocked when the Tasks and the CR is released respectively.
    There are no Object Lock for Customizing CRs ... like your TR1 which contains Creation / Deletion of roles.
    After the release of each Task, all Objects contained into every Task are transferred to the Change Request. After release of all Tasks, the CR owner can release the CR and thus the Transport Request has been initiated. Technically, at this time, a copy of Data from the Database of DEV captured under the headers of each Tasks are written to Data Files in Central Transport Directory.
    Now coming to your queries..... there are no such synchronization happens for a Task if the Objects are edited in different time frames before Release.  So, when you added ME21, again you need to assign this change to the same CR. (_Answer to your Q1_)
    Please let me know if you have any confusion / query.
    Regards,
    Dipanjan

  • Release Stratergy User in Purchase Req.

    Hi Friends,
    We are using user exit to determine the Purchase Req. Approvers. In ME52N/ME53N under the Release Strategy Tab there is a table which shows the Approver name and description against each Release code. In our case we have multiple approvers against each release code, but the system show only one against release code, Is there any way to show all the approvers there(i.e.multiple rows against each release code).
    To be precise  all I want is that  my Purchase Req. Release Strategy tab should show all the approvers along with release codes .Please advise.
    Regards
    Sapient

    Hi ,
    I think what you are looking for has little to do with the worlflow. All you want is that your Purchase Req. Release tab should show all the approvers along with release codes .
    The idea is good but is not possible using user exit or workflow . You can go in for implicit enhancement for displaying all the possible approvers in the ME54N transcation.
    How workflow can help here is by passing the relevant Work item to all the approvers.
    Regards
    Gautam
    Edited by: gautam maini on Mar 21, 2011 10:26 AM

  • How to prevent PO changes in ME22N after Order acknowledgement?

    Hi everyone,
            Can anyone tell me how to prevent PO changes (ANY) in ME22N after Order acknowledgement?
            I would like to make it possible without release strategy process or authorizations.
            Do you know some User Exit or Customazing way?
    Regards.
    Jaime S.

    Dear Jaime S,
    You can do this by restricting in authorization SHDO and also by marking "changes not possible after release" in Release strategy procedure.
    And also you can navigate the menu to, SPRO------>IMG------>Material Management--->Purchasing(OLME)------->Purchase Order---->Define screen Layouts at Document Level---->And go to ME22n And Select the right parameter and in this you can make it display, optional or required entry for the fields.
    Regards,
    Manjunath B L

  • User exit/BADI to for Purchase requisition through release of Process order

    Hi ,
    i need to add some text to the Pur Req. The Pur Req will be created through the release of PROCESS order. Please let me know any exits are available for the same.
    regards

    Hi,
    check the below enhancements in transaction SMOD.
    CCOWB001            Customer exit for modifying menu entries                    
    COIB0001            Customer Exit for As-Built Assignment Tool                  
    COZF0001            Change purchase req. for externally processed operation     
    COZF0002            Change purchase req. for externally procured component      
    PPCO0001            Application development: PP orders                          
    PPCO0002            Check exit for setting delete mark / deletion indicator     
    PPCO0003            Check exit for order changes from sales order               
    PPCO0004            Sort and processing exit: Mass processing orders            
    PPCO0005            Storage location/backflushing when order is created         
    PPCO0006            Enhancement to specify defaults for fields in order header  
    PPCO0007            Exit when saving production order                           
    PPCO0008            Enhancement in the adding and changing of components        
    PPCO0009            Enhancement in goods movements for prod. process order      
    PPCO0010            Enhancement in make-to-order production - Unit of measure   
    PPCO0012            Production Order: Display/Change Order Header Data          
    PPCO0013            Change priorities of selection crit. for batch determination
    PPCO0015            Additional check for document links from BOMs               
    PPCO0016            Additional check for document links from master data        
    PPCO0017            Additional check for online processing of document links    
    PPCO0018            Check for changes to production order header                
    PPCO0019            Checks for changes to order operations  
    Thanks
    Sandeep
    Reward if helpful

  • Purchase order changes after release

    Hi,
    How can I block a purchase order to any changes after release it and then, in case of need, mark for deletion the purchase order itens?
    Regards,
    Maria

    Hi,
    To block any changes in the purchase order to after release, set Changeability  indicator as 1 for  Release ID "R" in following path & save.:
    SPRO ->MM - Purchasing -> PO -> Rlease Procedure for PO -> Define Release for PO -> Release Indicator
    NOTE:If you set  Changeability  indicator as 3, PO can be changed after release and trigger a  new release strategy based on value changes.
    Regards,
    Biju K

  • How to block changes in purchase order after purchase release

    Dear all
    Can u please tell us how to block any changes in purchase order after purchase order is released...
    (We don't want any line items addition or quantity addition or any changes once purchase order is released..)We wanted this for a particular purchase order type only
    Regards
    Sudha

    Dear Sudha
    Yes it is possible to confiquire your system insuch a way where once if the PO  gets final relase then it cannot be changed.Only possiblity that will be available for the user to make chanegs in PO is possible when the final release is to be reset and then make the changes.
    Release Indicator: specicfies whether the PO documents is blocked or can be processed for the follow functions.
    You can define the release indicators you need for your release procedure:
    •The Released indicator is used to specify whether messages (PO documents in output format) may be transmitted for a purchase order with this indicator.
    •The Changeability indicator shows the effect of changes to the PO (a change to a PO may require a new release strategy to be determined, for instance).
    •By means of the Value change indicator, you can specify that the release strategy is to be re-started if a PO is changed and the value of a PO item thereby increases by a certain percentage (e.g. 10%). Set the Changeability indicator to "4 - Changeable, new release in case of new strategy or value change" or "6 - Changeable, new release in case of new strategy or value change/outputted" and enter a percentage in the Value change field.
    And after that you can specify release statuese where you can specify which release indicator/status a PO is to have after having been released via a certain release code.
    and after release simulation .
    Test for the PO change after final release System will not allow you tomake changes by giving the message that the release  indicator doesnot allow you make the changes in PO.
    Regards
    Sunny

Maybe you are looking for

  • Right problem with apache and tomcat

    Bonjour; I use a user login "apache" to stop/start Apache and tomcat. Because never launching apache et tomcat as root. But I have the following problem with apache (file error.log) : [Tue May  6 17:26:22 2003] [error] Connection "warpConnection" can

  • Xslt: mapping different elements onto instances of an unbounded element

    How can you map different elements onto sequential elements of an unbounded type? For example: <record> <tag1>abc</tag1> <tag2>def</tag2> <tag3>ghi</tag3> </record> onto <properties> <property name="tag1" seq="1">abc</property> <property name="tag2"

  • MSS approve working time error?

    Hello Friends, Iam planning to approve working time through UWL using "Approve Working Time " web application. When i click on the workitem to call the web application i get the following error Exception condition "PROFILE_NOT_FOUND" raised., error k

  • Adding footage fails with larger documents

    Hi, I'd be thankful for any advice: I tried to add footage to a document (2.300 kb) for several times, but it doesn't work. With smaller documents it's no problem. It's a pdf of a magazine we publish for open access. Has anyone an idea that would hel

  • Storing a mutable ArrayList in cache

    Hi - I have an object as follows Entity { key k; collection<Person> personList; Each time, i get a new person, I want to add the person to the list. But when I try this, I get unsupported operation and found that the arraylist that I stored became im