Collective completion of quality notifications

Hi Gurus,
I'm on an archiving process, and I need to complete a big number of quality notifications, is there a mass change for this ?
Regards,
Mahmoud

Hi
There is only way QM10 by selecting Incomplete Notification and process one by one by slecting alll entries.
As there is no STD t code for processing the same.
If there are no madetory field entries left to put( like partner etc) then you may also use LSMW.
Regards
Sujit

Similar Messages

  • Complete quality notification

    Hi,
    following problem: If every task is completed, the system starts a workflow
    in order to complete the quality notification. Normally this task is delivered
    to the coordinator of the quality notification. In our case it's delievered to
    every single person, wo has the rights to do that according to PPOMA.
    Any idea about that?
    For proper input points will be awarded...
    Thanks,
    Barbara

    Hi !
    can you elaborate your query? What kind of task and what is the notification type? Do you want to add some follow-up actions?

  • Assign Execute and Review for Quality Notification

    Hello Experts,
    Can we configure the workflow WS24500047 or is their any change in configuration in SPRO so that we can make the following business scenario.
    1- Quality Administrator will create quality notification in QM01.
    2- Quality Administrator will assign the task to the responsible person for eg. User1 is responsible to complete the task to fix a bolt of a machine
    3- After fixing the issue. User1 will make the the task complete and request to close the task
    4- Other User say Reviewer will see the request from User1 and finds the the task is properly done and he will make a request to the approver to close the task
    5- The approver will approve the request and close the task.
    6- And if the all the task of the quality notification is complete then
    quality administrator will complete the quality notification and close the task.
    in other words.
    QA (will create the Quality notification and assign to user) --> User1 (Fix the issue and make a request to complete the outstanding task to the reviewer ) --> Reviewer (Inspect and make a request to the Approver to approve and close the outstanding task) --> QA (finally close the quality notification after completion of all Outstanding tasks)
    Thanks and Regards,
    Kuldeep Verma

    Hi Kuldeep,
                       You have to generate 3 SAP Login ID's like ...
    1. Q_01 : Who will have the rights of Creating & Changing the Notification. He will also have the right to complete the Notification as wel as revoke it.
    2. Q_02 : Who will have the rights to enter the details about the Task and its activities as you said fix a bolt on machine.
    3. Q_03 : Who will have the rights to review the whole process thru closing the Task.
    I feel that there is no need to have fourth one in picture as your all requirement can meet within these three.
    Please revert with comments.

  • Update System Status for Quality Notification

    I have a program that completes a Quality Notification.
    I would like to know if there is a bapi, badi or function module to change the system status before I complete the notification. When I click on the icon in the notification to complete it, a pop up box comes up to change the status to NOTI or NOTE. I would like to do the same in my program before I complete it.
    Any help would be appreciated.
    Marianne

    Hi,
    You need to get the OBJNR(object number) for the notifications and then use the FM: STATUS_READ.
    This FM will give you list of all the status or only active status( Set ONLY_ACTIVE = X in FM)..
    Hope this helps
    Regards
    Shiva

  • Workflow Send Mail when Quality Notification is Complete

    Hi All,
    I need help related to QN Workflow, which is copy of standard workflow WS24500047.
    In this case , when all tasks are marked completed and get stated TSCO in QM02, against individual tasks.
    But, on completion of tasks, no mails is being sent to the coordinator, presently.
    A mail should be sent to the coordinator, in case all tasks are released and marked as completed.
    Please suggest how do I implement the above functionality.
    Thanks in advance.

    Hi all,
    Thanks for all your answers
    We have resolved the issue.
    Problem was with the configuration settings
    We had to do config settings in 3 places:
    1) SPRO/ Quality Management / Quality Notifications / Notification Processing / Activate Workflow template / Click on Activate event linking/  Place cursor on task group / click Object button / select tab workflow template and add the custom workflow / Go back and then open the workflow from the list and activate the events
    2) Add the events in transaction SWE2 for the custom business object.
    3) Add the events in the transaction BSVW for the custom busines object.
    Thanks and Regards,
    Mozila

  • IQS9 Completes Quality Notifications without digital signature

    Hi all,
    When we complete quality notifications, the system requires the user to enter digital signature (username and password) in qm02. However when you select a list of notifications in IQS9, and then click on Edit from there, it brings the notificaion up in transaction IQS22 and you can complete a nitification there without digital signature which is bad.
    We can't take everyone away from using IQS22 because it provides a much better selection and drill down capabilities for all types of notifications (service and quality). Is there a way to have IQS22 require a digital signature for quality notifications just like qm02 does?
    Thank you very much,
    Sergiy

    E-signatures in Quality Notifications WAS (!!) not a part of the standard features in SAP. But as of ECC 6 (extension pack 4 - I think) e.signature in notifications are avalable in tasks and actions. I have never test this function. But:
    If this not solves your problem you can implement SAP e-signature Tool with alow you to add digital signatures "everywhere" in the system. This is a pre defined "ABAP-tool" to cal up at any system action by a exit/mod.
    http://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/e0fbaa71-cd8d-2910-5982-e30626035400
    I hope this will awnser you question and that anyone that has test te e-signatures in notifications can add info.

  • Completing quality notifications in bulk

    Hi Guys
    I need to change the system status of quality notifications (+/-500 000 records) to:
    NOCO and
    DLFL
    We’re using SAP ECC6 EHP6. Please guide me to a standard SAP tcode/program that can be used for bulk/mass system status changes (QM10 will require manual actions and is therefore not suitable).
    Notification origin = Q3
    Notification category = 02
    Best regards
    W

    Hello,
    Yes same i was told you that in PM/CS such facility is available bcoz notification is linked with costing object like order and those needs to closed before month end for settlement. But in QM there is no such criticality and that's why SAP not provides mass closure.
    Yes u cane use LSMW, eCatt and BDC like functionality for this in QM.
    Regards

  • Quality notification - more reference objects

    Hello,
    business need is to have quality notification with possibility to refer either production order or purchase order under one notification type.
    By standard this seems not possible as:
    Complaint Against Vendor references to Purchase order
    Internal Problem Report references to Production order.
    But in section "User-specific notification" is mentioned
    A user-specific notification type has the same basic structure as the standard, predefined notification types. The screen layouts, reference objects, and tab indexes, however, may differ from those in the predefined notification types, depending on how you customize the user-specific notification type.
    But I have not found a way in customizing to enable this.
    Advice appreciated.
    Br, Jan

    Thanks for the asnwer, but I think this does not solve my problem.
    In the configuaration for "Notification Header and Screen Areas" I do have
    - notification header screen H500
    - customized screen O550 (BADI)
    and both are needed.
    The BADI is used to customize refernce object screen, not reference documents screen. But my idea was to change reference document screen area in a way, that both purhcasing and production reference documents are visible in there.
    I only managed to get the vendor screen by adding screen area 037 to "Extended View: Tabstrips and Screen Areas" But adding purhcase document as reference to Reference documents remains my problem.
    I am kind of able to make the vendor screen visible by e.g. adding screen area 037 Partner overview screen (table control).But creating a new pop-up window for notification reference, where both options (pur ord, prod ord) would be available with copying functionality - in my opinion this requiers completely custom coding.

  • Quality Notifications tasks authorization

    Hello Experts,
    Need your advice on Quality Notification authorization access.
    In Quality Notifications once a coordinator enters the tasks we want to control who can have access to delete a task or change the user responsible for tasks. In other words we want users to execute the tasks and mark them complete but we do not want users to be able to change the user responsible for the task or delete the task from quality notification other than co-ordinator himself. So is there a way to control this using authorizations or by using BADI and writing a code for the authorization check? Please advice. It will be very helpful.
    Thanks.
    Regards,
    Sreepati Hari

    While assigning role to the user. I have to give authorization for qm02. Under qm02 I give access to QN* as suggested by you for user to complete or release task only.
    But the issue is when he is processing a task he can change the user responsible for the task as it is a open field. Is there a way that I can make that field display to most of the users other than coordinator?
    Thats where I am running into issue with.
    Thanks
    Regards
    Sreepati

  • Set a User Status for Quality Notifications only if they are "Activated".

    Hello experts:
    I need to be able to set a User Status for Quality Notifications only if they are "Activated".
    When defects are recorded for an inspection lot, a "Defect Notification" is created which can be activated to become a "Quality Notification".  Initially, the only difference between the inactive "Defect Notification" and the active  "Quality Notification" is that  the system status DEFR is active for the "Defect Notification", but is cleared when the notification is activated.
    So, I'm looking for the business process associated with the Activation to use as a trigger for my own user status.
    I checked the business rules for status DEFR and found that the following processes clear this status
      PMM1 -  Postpone Notification
      PMM2 -  Put Notification In Process
      PMM3 -  Assign Order
      PMM6 -  Put Notification In Process Again
    Any Ideas ?

    Perhaps some additional information would help you understand what I need to do.
    For notification type F3, we are recording all defects found in production.
    Most of these are expected defects that result in a minor reduction in yield.
    For this type of defect, we do not activate the notification, and the inspection lot is closed automatically at the end of production.
    However, sometimes defects are observed of an unexpected type or a higher than expected quantity.
    When this happens we manually activate the notification and assign tasks to find and correct the cause.
    It is only for these activated notifications that I want to automatically set a user status, which among other things, will prevent the notification from being closed until some other actions are complete and a different user status is selected.
    The function of the user status currently works exactly as I want, but if it is set as the initial status for all F3 notifications, it is also preventing the un-activated defect notifications from automatically closing.  I therefore want to use the Activation event as the trigger to set my user status.

  • Status profile for Quality notification

    I want to restrict users untill notification is approved, they can not do it complete
    Dear All,
    I want to restrict users untill notification is approved, they can not do it complete.
    I have created status profile through BS02 as ZQM02 where 3 status no I have given:
    10-INIT>Init status checked>lower limit-10 higherlimit-20>Position 1>priority>1
    20-APPR>Init status not checked>lower limit-10 higherlimit-20>Position 1>priority>1
    30-COMP>Init status not checked>lower limit-10 higherlimit-30>Position 1>priority>1
    Allowed Object types>Quality Notification checked
    In transaction control Complete notification marked as forbidd.
    But it is not working, I can still mark as complete without marking it approved.
    status screen also not changing even after completion of notification, it still showing
    under status no 10 >INIT
    Plz advice what I am missing and how I can do this.
    regards,
    sp shukla

    OK. I think you are confused 2 things.
    First.. you have to create 2 kinds of status profile. One is for notification and another is for task.
    Second.. 'next action' means not next transaction. It means automatic set when the transaction is excuted.
    Try below.
    1) status profile 'A' for notification (select 'quality notification' only for object type)
    10-INIT-initial-forbid 'complete notification'-nothing other transaction
    20-APPR-allow 'complete notification'-set 'put in process(released)' (this means a notification will be set 'APPR' automaticaaly when you release a notification and user can complete it.)
    30-COMP-set 'complete notification' (this means a notification will be set 'COMP' automatically when you complete it.)
    2) status profile 'B' for task (select 'task' only for object type)
    10-INIT-initial-nothing other transaction
    20-REL-forbid 'delete task'-set 'release task' (this means a task will be set 'REL' automatically when you release a task and user cannot delete it anymore.)
    3) assign both in configuration
    'A' for notification
    'B' for task
    Regards
    Luke

  • Quality Notification checkered flag configuration

    I am looking for the configuration for the checkered flag (completion flag) for completing the a quality notification.   We are looking to gray out this flag to not allow completion while in QM01 transaction. 
    Thanks!

    Are you able to complete notification @ QM01? If you go with standard configuration then it will not allow you. Have you changed it? then re-do your config change.
    If you go with standard notification config and if you clikc on "put in process button - green flag" or "complete button - black flag" then system will throgh you error saying "save notification first so that a notification number can be assigned".
    Without assigning notification number, which notification number system will put in complete status?
    I hope this helps to understand system behaviour & expectation.

  • Q1-Quality notification

    Hi
    how to create/configure user status in quality notification(Q1)
    like testing,testing completed
    I will appreciate if any one thow some lights
    thanks

    Hi,
    U can define the user status in the following manner :
    First define ur user status profile in transaction using QIBS and assign to the object type u want ,by selecting ur status profile go into the details define the text and the box for initial status.click on object type to assign the same.
    Assign the User defined profile to the notification type.
    following is for ur information :
    You can define your own status profiles. You must assign at least one object to each status profile. Each status profile contains one or more allowed statuses. Within the scope of the business transactions predefined by SAP, you can specify how the system will behave for each of these statuses. In the status profile, you define:
    Your own statuses (user statuses) and document their functions in a corresponding long text
    The user status allows you to refine the sequence of system statuses predefined by SAP to your own requirements. However, this is only possible within the fixed profile defined by SAP; you cannot override the system status with the user status.
    The status order numbers for user statuses which determine the possible sequence of user statuses
    An initial status that is automatically activated when you create the object
    Which user status is automatically activated when you execute a business transaction
    Which transactions are allowed or not allowed when a certain status is active
    thanks,
    Prakash

  • If Quality notification as follow up action fails

    Dear all
    I have a situation where Quality notification is configured as a Follow up action once the UD is made.
    So I am getting Create notification screen once UD is filled and SAVE button is clicked.
    In Case some wrong data is entered in the Create notification screen and I am coming out of Notification without saving the notification.
    The status of the inspection lot is getting flipped to UDed as expected.
    But is there any setting where i can define if the Followup action is not successful( Notification not created), then wont make the UD of Inspection lot also. (OR some user status will get updated saying Notif not created etc..)

    Hi Navdeep,
    Thanks to Anand for his correct feedback.
    Please note that as per standard SAP, unless and otherwise there is a defect created, there can't be a 1:1 link with inspection lot with the notification, though in the notification header table there is a placeholder available (QMEL-PRUEFLOS) to capture this inspection lot field. You are trying to use a follow-up action wherein, after UD you are always creating a notification based on business case. I believe, the FM you are using in follow-up action, is not presently populating QMEL-PRUEFLOS. So there can't be a link to find out when there is failures in notification creation, but UD happening successfully.
    You can try out the below approach -
    Approach - 1
    During the UD save process, there should be additional checks happening. Ask the follow-up FM to update QMEL-PRUEFLOS or TEXT field with inspection lot for all successful notification creation and UD update, and send a confirmation email to approver or task processing partners, or the UD processing user ID (This email part can be skipped in case if this is not required). In case of any failures in notification creation at save, it should truncate the UD save process too and send a message to UD processing user for this failure.
    Approach - 2
    You can create a batch job running at the background to validate for which inspection lot there is no notification created, even though UD is done. Send a mail to the UD processing user to create a notification, as that is not created. User can then create it manually it by updating TEXT field in notification in foreground.
    Thanks,
    Arijit

  • Existing Quality Notification takes long time to open for certain vendors

    Hello Gurus,
    I have users complaining about the wait time( 2 t0 5 mintues) when opening of an Quality notification in QM03 for certain vendors. For soem vendors its fast and they always fast but for some it takes really long time and it always long.
    I tried the sql trace but nothin out of ordinary compare to the ones both kind slow and fast.
    Any help or idea would be really appreciated1
    Regards,
    Khan

    Dear Khan
    I think you need refer this to SAP itself. This is more of some program error than your execution. Please check this note if it can help you
    Note 1324998 - IQS9: Performance for general selection
    Regards
    Gajesh

Maybe you are looking for