Compare the cost element of each internal order

Hello All,
How can we compare the cost element of each internal order?
let me know how can we maintain the budget for each cost element for each internal order.  so that along the year, we can compare budget and actual for controlling purpose.
Thanks
Naveen

Hi,
I guess you mean comparing plan value by cost element for different IOs.
If you want to compare those (same as actual), you could put internal orders, ranges or groups into the respecitve columns. I also did this once I think for car costs, where the manager wanted to see 10 cars next to each other and compare them (in this case it was actual figures, but same is possible with plan values).
You just need to unselect IO on general data selection and use this as characteristic in the columns then.
hope this helps?
regards
Bjoern

Similar Messages

  • Recover cost element associated with internal orders. Tx KPF6

    Hi,
    I need to recover only the cost element associated with the internal orders listed in tx. KPF6. Can anyone please tell me how can I do this?, do I need to copy the entire tx to a Ztx?? or can i do this through an User Exit???
    Thanks, Fiorella

    Hi Fiorella,
    Try using table AUFK.
    It gives you the Responsible cost center as  well as the Cost center for basic Settlement for a particular internal Order.
    In case you need any other information, feel free to revert.
    Thanks,
    Sonal
    P.S. Would it be helpful if i tell you how to get Internal Orders from an Internal order Group??

  • Is there a way to redetermine the cost center for an internal order on a PO

    When we create a PO for an asset we enter an internal order number and a cost center is determined from the internal order. Sometimes after the po is created the cost center on the IO changes. The po is not updated automatically on the PO and it results in the wrong cost center being posted to during the Goods Receipt and invoice receipt. Is there a program or batch job that we can run that will redetermine the accounting data on a PO?
    Thanks!
    Chris Lintner

    When we create a PO for an asset we enter an internal order number and a cost center is determined from the internal order. Sometimes after the po is created the cost center on the IO changes. The po is not updated automatically on the PO and it results in the wrong cost center being posted to during the Goods Receipt and invoice receipt. Is there a program or batch job that we can run that will redetermine the accounting data on a PO?
    Thanks!
    Chris Lintner

  • Change cost center in statistic internal order

    Hello all,
    I have got a problem with the master data of our internal orders. We´ve defined them as statistic objects, and the information of the cost center is an obligatory input within the master data of each internal order. After the first entry has been done the cost center can not be changed anymore. Now we have the necessity to change the cost center in all our internal orders once. Could you help me to find a solution how the cost center remains a changeable input in the master data of a statistic internal order? Or how I may change the cost center just once?
    Thanks for your help.
    Best regards,
    Bettina

    Dear Sir,
    The field is greyed off if the following is applicable:
    -> the order has planned or posted entries
    -> you have created a settlement rule on it.
    If you want to have the field to be changable, please apply the modification note 198036
    regards
    Waman

  • FM to find out the total cost/cost analysis of each production order

    hi Friends,
    Im on report development to list out Production Order Costing analysis. Where Iam using table of AFKO, AUFK and COSS, in that COSS table is for Cost Totals for Internal Postings which is taking too much time as performance issue to fetch the records as per my select condition (which is given below) for even my date period range is a day or two.
    select * from coss INTO TABLE IT_COSS FOR ALL ENTRIES IN IT_AUFK WHERE OBJNR EQ IT_AUFK-OBJNR AND VRGNG
    EQ 'RKL'.
    Is there any FM available where I can get my values through the object number of each production order? or is any other way to derive my requirement?
    Please advise.

    Hi Sankar,
    Try this.
    For production order nos. - AUFK or AFKO
    For production order status - JEST & to know the status eg REL etc, refer TJ02
    For costs - COSS & COEP (Pass order nos. to the field OBJNR as OR followed by 12 digit order number)
    Add this logic.
    {*IF NOT it_aufk[] IS INITIAL.
        SORT it_aufk BY aufnr.
        DELETE ADJACENT DUPLICATES FROM it_aufk COMPARING aufnr.
        SELECT * FROM coss INTO TABLE it_coss
                   FOR ALL ENTRIES IN it_aufk
                   WHERE objnr EQ it_aufk-objnr
                     AND vrgng EQ 'RKL'.
      ENDIF.*}
    Hope the above helps.
    Regards,
    Vijay
    Edited by: vijay chavan on Sep 21, 2009 2:49 PM

  • Sales order cost objective vs OKB9  Internal order cost object.

    Hi All,
    we facing an  issue with sales order cost objective vs OKB9 cost object.
    For IC PO service material, we assigned account assignment category 4.Reasonis Service material was not showing on G\R account.
    The G\L account 7898788, we assigned to Service Item (material type DIEN)  , for G\Cost 7898788 cost element is assigned in OKB9. Combination business + order 3478787.
    Now conflict with sales order cost objective vs OKB9  internal order cost object.
    While posting intercompany IR posting system thronging below error messageu2026
    Enter only one true account assignment
    Message no. KI249
    Diagnosis
    You made assignments to several objects in CO (cost center, order, project etc.). 2 of these have been created as true objects.
    System Response
    You are allowed only one account assignment for each cost-relevant account
    How to resolve this issue.. Do I make any config changes in the system to overcome this issue?
    Or any sub account to assin in VKOA config for internal orderu2026
    Regards,
    Adi

    Hi Waman,
    Thanks for your inputs.
    Issue :  IR failed to post for wax  Sales Order -> ICPO  - Error:  Enter only one true account assignmentu2019.
    Background:
    Original setup  in  Test system   & Productionu2013 account determination for servive (DIEN) account assignment category u20184u2019 was linked to G/L Account  34444444, As part of project orange u2019, account determination was linked to account u201889710100u2019.
    Account u20188970100u2019   34444444 was replaced with 8970100 ,is not linked to any cost center & always post with reference to IC Sales Order as per config in OKB9 based on company code (US99) + cost element (89701100) + business area (9yyy). This caused a conflict while posting IR, system could not determine exact order for posting financial value.
    Conflict:  Actual Sales Order 34789343 is  linked to PO via account assignment category & IC dummy sales order (8014331) is determine via config setting. Two cost objects cannot be linked to one IR G/L account booking.
    Regards,
    Adi

  • Employee cost should hit to Internal order

    Dear Friends,
    We started new plant and  hired employers ,cost center profit center not ready yet( we created one Internal order as over head order ).
    Employee Cost through Payroll  so HR People has already created a new Organizational Unit and we have tagged it to an Internal Order.  We have hired some test employees and have run payroll for this newly hired employees.
    So the system is throwing the following errors.
    Error 1)*Account assignment objects are incorrect. No substitution is possible.*
    *Message no. 3G209*
    *Diagnosis*
    *The account assignment object check showed that, from the point of view of CO, the specified account assignment is not valid, and cannot be replaced by the employee's master cost center or a substitute cost center. This item cannot be posted.*
    Error 2)Internal error: No valid return value for segment found
    Message no. 3G330
    Diagnosis
    No valid value was returned as a result of the segment check. The Customizing settings for the general ledger, however, request a value for the account assignment of the segment.
    Error 3)No segment found
    Message no. FAGL_ORG_UNITS007
    Diagnosis
    No segment could be derived for the current line.
    However, in the Customizing settings for General Ledger Accounting, you have selected the segment as a mandatory balancing field. This means that a segment must be assigned in each line item.
    System Response
    The posting is rejected.
    Procedure
    Edit your segment derivation or make changes to the Customizing settings for document splitting.
    Kindly suggest me onthis its very urgent.
    Regards,
    Sudha.

    Dear Raviteja,
    Thanks for your Reply ,
    Allready i checked the link which you have provided but our case is different.
    Actually the Employee Cost should hit to Internal order not  to cost center.(that is our requirement)
    While creating internal order i didnt maintain  any profit center bcoz cost center and profit centers are not ready yet for time being we are planning to move Employee cost to internal order later we will settle to Cost centers once its ready.
    Thanks & regards,
    Swapna.
    Edited by: swapnasudha chowdary on Jan 24, 2012 11:59 AM

  • Cost center v/s Internal Order

    Hi
    What is the difference between a cost center & Internal Order
    Regards
    Samir

    Hi Samir,
    Cost Center is an Organizational unit within a controlling area that represents a clearly delimited location where costs occur. You can make organizational divisions on the basis of functional, settlement-related, activity-related, spatial, and/or responsibility-related standpoints.
    Cost Center is a CO Object maintained on long-term basis to capture costs related to particular type of cost based on functionality, nature of cost etc.
    An internal order is used to monitor parts of the costs, and under certain circumstances, the revenues of the organization.
    Internal Order is a CO Object maintained to capture the costs of specific purpose (like campaigns, events etc) which is of short-term purpose.
    Let us understand the difference with the following example...
    If you have a Cost Center "HR Department", whenever some expenditure is incurred for HR Dept, that cost will be booked to HR Dept Cost Center.
    Let us assume that your company is about to take up a Recruitment Campaign (like campus placements) for about 3 months all over the country.
    So, you can create an Internal Order "Recruitment Campaign". The Internal Order can be "Real" and "Statistical".
    If you create the Internal Order as a "Real" object, then, at the time of booking the expenses relating to Recruitment Campaign, all costs will flow to the Internal Order and then, costs will be settled to your "HR Department" Cost Center at the period-end.
    If you create the Internal Order as a "Statiscal" object, then, at the time of booking the expenses, you can select your "HR Department" Cost Center as well as your "Recruitment Campaign" Internal Order as CO objects. In this case, real postings will happen to Cost Center and statistical postings will happen to Internal Order. There will not be any requirement to settle the Internal Order to Cost Center. Here, this statiscal internal order will be information purposes only...
    Hope this is clear, pls revert back for further explanation...
    Srikanth Munnaluri

  • Create a new standard layout for the cost report of a sales order

    Hi,
    I would like to create a new layout to view costs in a sales order.
    path: view sales order (VA03), mark sales order item, go to environment cost report. At the moment the SAP standard layout 1SAP01 is shown.
    first question: how can I assign this layout as default layout?
    second question: how do I create the new layout, via report painter? can you give me a path or transaction code?
    thanks.

    i found it myself. You define the groups in the cost component structure. this structure is assignen to the costing variant of each cost object.
    thanks

  • GR55 - report generates no data for some of the cost elements

    Hi
    When executing GR55 for Monthly cost center analysis (target currency), the report generated has values for all the cost elements in the report. However, few cost elements do not show amounts. The amount columns show a ××××.
    Please suggest on why the system is not displaying the values only for few cost elements when running GR55 for report group CCPA (Cost center Actual vs Plan).
    Thanks
    Neetar

    Dear Neeta,
    Every customized report generated in Report painter will have a base as Form, were you do your customizing to get the report.
    So might be in some places the value key figure would have not properly customized.
    Check the report in T.Code GRR3 and see the places where you get XXXX.
    Hope it clarifies your doubt.
    Thanks and regards
    Praveen.J

  • How to Add the Cost Element in Existing Zreport Painter

    hi friends
    i have issue with report painter
    one Cost Element is not picked in Z Report which was created in Report painter
    transaction data could be found in standard reports.
    please expain how to Add the missing Cost Element in Existing  ZReport
    Point will be awarded.
    Thanks

    Check your sets first, if the cost element is missing from there, then change the set using GS02
    Cheers
    Prakash

  • Finance and Controlling report in combination with Cost center, GL account, Internal Order

    Hi Members,
    Finance and Controlling report in combination with Cost center, GL account, Internal Order.
    Please provide any slandered report in all 3 dimension.
    Thanks
    Dileep Kumar

    Search this query in FI Controlling forum am sure you will get useful results there.
    This kind of reports related to Controlling are usually created using Report Writer tool.
    In fact majority of reports in Controlling component is created using Report Writer only.

  • What are the costs we collect in maintenance order  and work order

    what are the costs we collect in maintenance order  and work order
    is work order and maintenance order differeent or same

    Usually the main costs of maintenance are the spare parts and labour. And these are the costs we would like to track per maintenance job from a maintenance management perspective. There could also be cases where other costs such as travel to place where the equipment is might be required to be collected in the maintenance order.
    In SAP there is no term called work order. But loosely the term is sometimes used for maintenance or service order. Probably even production orders also.
    thanks
    Bala

  • Link between the Cost element - PA segment

    Hi,
    I have an issue with a document which cannot be transferred to Accounting because the combination "cost element 611532 and PA object" is not possible.
    I have checked the validation rule "combination cost element - PA segment" which refers to a customed table.
    In that table I can see the validity year, the cost element and the cost center node.
    What else do I need to check?
    Thank you for your feedback.
    Kind regards,
    Linda

    Hi Paul,
    The Profitability segment is an optional entry in the Field status of the cost element.
    It concerns an "Advertising Samples Resale Goods" account.
    Kind regards,
    Linda

  • Can we change the cost element after posted some expenditures.

    Hi friends,
    My client ran the depreciation upto jan 2009, afterthat we found the depreciation GL's are not set the cost element.
    so the Depreciation values were not posted cost center wise, now we want to change the GL's cost element , is it possible, if it is possible what is the steps.
    with regds
    muthuraj.g

    Yes,
    You can create cost element and interface depreciation posting to CO. For missed Depreciation, manual posting in CO can help to reconcile with FI.

Maybe you are looking for