Component Assignment to Activity

Hi
I am facing one issue regarding material assignement to network activity, When I assigned the material to activity then option  'NEVER' is populated for Reservation/ Purchase Requisition. I want this should be with option 2 ( From Release).
I have checked network profile also & here I had consider the option 2 ( From Release).Is there any other place where we set this setting. Please share your valuable opinion.
Regards,
Ashok Sangal

There is not othere place it will pick from network profile only, just chech you are referreening correct netowrk profile only.
With Regards
Nitin P.

Similar Messages

  • CN01 assign Material Component to internal activity

    Hello gurus;
    In transaction CN01 / CN02 can I assign only one Material Component to internal activity without Bill of Material (BOM)?
    It is possible? How can i do?
    Best regards,
    Mariano

    Virendra;
    Thanks for your response.
    I saw the SAP Help portal in [http://help.sap.com/saphelp_46c/helpdata/es/4c/227a7746e611d189470000e829fbbd/frameset.htm]
    and I must use a Bill of Material to assign material component. There is no other choice
    This is the point where I disagree with SAP, cause the client says that they use Operational Networks, cause it's more simple to assign components to activities.
    Best regards.
    Mariano

  • Dealer Portal - Vehicle Management System - Personalization - Web Dynpro component assignment for business partner is missing

    Hi,
    In the Dealer Portal, Vehicle Sales Role --> Personalization.
    I am getting below Warning message.
    The Web Dynpro component assignment for business partner is missing.
    As per my investigation found below.
    Since address formats are different for each country, you can define in the Customizing activity Assign Web Dynpro Components to Country-Specific Address Formats under SPRO --> Logistics Execution --> Dealer Portal which Web Dynpro component you want the system to use for displaying end customer addresses.
    BUT do NOT understand the name of WebDynpro Component to provide.
    What are the entries or WebDynpro component names to fill in below?

    Hi Hussain,
    Could you share the step-by-step solution? Thanks.

  • Component for netwowrk activity

    Hi all,
    When we add a component to the activity in the TAB assignment we have fields assembly, BOM category, Main assembly, MAin assembly cat and fixed key date.
    can any one help out to understand where the above fields are being pulled from and what significance they have.
    reg. sam

    Hi Amit,
    I have checked out the BOM also but havent found any details regarding assembly and may be thats the reason i have no assembly data flowing in to the project. Correct me if i am wrong.
    Thus i want to know how do we get these details at the BOM level so that i can see those flowing into the project.
    reg.sam

  • Error: "Component is not active" but component is active

    Hi Experts,
    I transported a Web Dynpro application from source system to target system. When starting the application via browser I'm getting this error message:
    "Component XXX_BDB is not active"
    But the component is active in source and in target system. When I try to activate the component in target system there comes this error:
    Component XXX_BDB can't be generated because of errors: see long text.
    (Message no. SWDP_WB_TOOL100)
    According to the long text, there is a heavy error and I should check the component in order to eliminate the errors. Checking the syntax is OK and strangely, the component controller is also active. But when I want to start WebDynpro-Component, the error message "Component is not active" is displayed.
    I have checked this thread [Problems when activating ComponentController   |Problems when activating ComponentController; without any effect....
    Does someone have any ideas?
    Thanks in advance,
    Tan

    Hi Thomas,
    where can I check the generation load limit?
    I've done an extended syntax check (in source system, is that okay or should I do the check on both systems?), there are some errors regarding strings, field properties and structure extensions and some warnings regarding field properties.
    But this errors are on an other wd component as well, but this other component is running, so I'm not sure if these errors are crucial. However I'm going to fix the errors now.
    Baskaran, I will check the component controller and component usage as well but how can I identify the errors or should I just check it in general?
    And what about the fact that both applications are running on the source system?
    Additional info: the source system is ECC 6.0, the target system is Solution Manager 7.0
    Thanks
    Edited by: Tan Yildiz on May 4, 2011 9:26 AM

  • ABAP Runtime error when doing component assignment in routing creation.

    Hi All,
    I have a problem in component assignment while creating routing (CA01) by using Copy from function. We are creating a Sale order specific routing for a finished material by copying it from the same material. The Transaction runs very slow and when it goes to component assignment it is taking more than 2 hrs and going to dump.
    This finished material is having  very high no. of compoents in its BOM. (14000). Pls suggest why this is happening.
    Regds
    Mahesh

    Hi,
    You can analysis the Dump error using t-code ST22 with the help of your ABAP consultant. He will be able to explain you why the dump you are getting.
    Regards,
    V. Suresh

  • Problem while assigning service activity to WBS

    when i assign service activity to WBS element without filling any fields (like Purchase groupand Material group) it is going straight to Service Specifications.
    if we fill the service specifications and save the project we can save the project with out any errors
    i require entry of PurchaseGroup and Material Group is mandatory
    and then system should go to Service specifications
    Please advice

    Hi,
    Just check in Network profile, on Activity tab (TC: OPUU). You must have maintained required details like Material group, Purchasing group etc in Service activity section. Whenever you create a service activity these values get defaulted in activty. Let me know if it solves your problem.
    Reward points if helpful.
    Regards
    Message was edited by:
            Shrikant Rakate

  • Operation level Component Assignment

    In MTO scenario with VC and Engineering, the sales order specific engineering BOM is
    derived through VC and around 80% complete at the time of sales order creation.
    Engineering activities are carried out and sales order specific production BOM is derived
    very late in the process.
    So, operation level component assignment is not at all possible in advance.
    need to get different components assigned to different operations at at time of
    production order creation/change automatically.
    Is there any function module,exit or Bapi or some other method with help of which
    operation level component assignment can be done automatically in the production order.

    Hi,
    Just a quick thought:
    If your order is having status CRTD or REL (but without any confirmations, goods issue, settlements) then you can use the Read PP Master Data (Order header - Functions - Read PP Master Data) & this will re-read your routing & BOM. But for this to work for you, the routing should be updated with the assignments.
    So what you could do is start processing your order as late as possible, thereby you can re-read the BOM & Routing as the modifications take place.
    But if this is not possible in your scenario, then i am not aware of a BAPI or a FM which adds components to different operations in production order, you might evaluate writing a BDC program for the same. Anyways will update you if i manage to find a BAPI or a FM for this.
    Hope the above helps.
    Regards,
    Vivek

  • "Component Assignment Incomplete" while Apply Model from ESR

    Hi all,
    I am trying to configure a scenario by using Model Configurator with Tools->Apply Model from ESR.
    My Process integration scenaro is : PAYE_EOY_GB which belongs to the swcv "E-FILING GB 1.0" whose content imported from ESR content available on sap marketplace.
    I am trying to configure the scenaro.
    The sender is a Business System "Sys_MyECC" which represents SAP ECC.
    The reciever is UK govt gateway.. for which i created a party with the name "GovernmentGateway" and a Communication Component "GG_submission" within the party.
    When i am in the model configurator, in the step 2 Assign Components, when i am selecting the sender Component as Sys_MyECC,  it is giving the popup message:
    Component Assignment Incomplete :
    Each business component must be assigned a business system component. Incomplete assignments exist; these can be removed automatically.
    What does this message is trying to convey.
    thanks in advance,
    Madhu_1980.

    Besides having a Business System, you need a Business system Service to have a B2B communication
    I did not get what exaclty the Business system Service means.
    for the sender, we have SAP ECC, the scenario will be triggered using sproxy communication.
    so, we created a Business System representing the ECC server.
    the "Bysiness system service" means.. does it also represent ECC server, in pi 7.1, if we create Business Component, how we can link the Business Component with the Business system.

  • Assignment of activity types to centers

    Hi
    where can i assign particular activity type to a cost center
    Thanks in advance

    See Guys
    Cost Center and Activity Types Relationship:
    Normally Activities are assigned to Work Center.  In this Work Center u have to maticoned Cost Cetner at Costing Tab in Work Cetner.  So Here is the link with the Cost Center and the Activity
    Previously mentioned In KP26 is the link, but it was on planning side only and it was not mandatory.
    Regards
    raj

  • Create Person & Assign to Activity - CATS

    Hi Experts,
    I need to create persons and assign it to the internal activities in person assignment tab and use for CATS.
    We are not implementing HR module. Please suggest and advise.
    Thanks & Regards,
    Kabir

    Hi Kabir,
    1. You can create person through Mini-HR. T.COde is PA30. you have maintain following ifotypes 0,1,2,6,7,105 & 315. No need of HR module
    2. Create activity type in CO & maintain rate in KP26
    3. Create workcenter and assign person & activity type in it.
    4. Attach this workcenter in Internal activity
    5. Do the workforce planning in CMP2
    6. Book the time in timesheet using CAT2
    7. Transfer the time to PS using T.code CAT5
    Hope, this will help you.
    Regards
    Prabu

  • Download component assignment

    Hi,
    Is there a table or other ways to download the relationship between materials and operations (results of component assignment) in routing?
    Thanks!

    Hi Harvey
        Table PLMZ stored the relationship between operation and  component ,but if you want get more detail ,you have to connect to table  STPO .
         The relationship as below:
          Table PLMZ ,key field :
            PLNTY  Task list type
            PLNNR  Group
            PLNFL   Sequence(it may have more than 1 sequence in a routing due to alternative or parallel sequence)
            PLNKN  TL Node -  Task list node (it stand for Operation , but not  simply equal to operation no,  Say in a routing ,there are 3 operations  0010 /0020/0030 ,in here ,for operation 0010 the TL node  is  1, but  if  you delete it and create an new operation 0010 ,it may become to 4. pls  link to table PLPO to get the operation no. )
            you can get below information :
            STLTY  BOM category
            STLNR BOM
            STLAL Alternative
            STLKN  Nodes
            WERK_STL Plant
           Connect to table STPO ,then you can get the material no and other things .
           Hope this can help you .
    Joe.Li

  • Cost center assignment to Activity Type

    Hi,
    How to assign Cost Center to Activity type ?
    Thanks
    Prakash.B

    Prakash,
    You may create an activity type by using the transaction KL01.
    This defines the activity. Now you have to have a rate (per hour) defined for this activity. Additionally you have to maintain the cost center which will bear the expenses of this activity.
    So ,
    (1)Use KL01 to create an activity type
    (2)Determine with your CO team which cost center(G/L Account) should be allocated ?
    (3)Determine with your CO team what the rate/hr should be for this activity type?
    (4)Use KP26 to assign the activity type to cost center and also assign the rate.
    Thanks,
    KF

  • BAPI_NETWORK_COMP_ADD     Component assignment not intended for sales order

    Dear,
    I have problem when I use the function:
      CALL FUNCTION 'BAPI_NETWORK_COMP_ADD'
        EXPORTING
          number           = number
        IMPORTING
          return           = return
        TABLES
          i_components_add = i_components_add
          e_message_table  = e_message_table.
    I have inserted only these values  in the structure i_components_add:
    ACTIVITY_TYPE_PUR_RESV__ITEM_NR____MATERIAL_________PLANT___ENTRY_QTY___ITEM_CAT
    108--8101TAH052000110025.460--
    L
    108--8204RAVBLA098SL0111002.000--
    L
    108--83034R000000011004.160--
    L
    but the result is wrong
    e_message_table:
    METHOD--C--
    32                                                                               
    OBJECT_TYPE--C--
    32                                                                               
    INTERNAL_OBJECT_ID---C--
    90                                                                               
    EXTERNAL_OBJECT_ID--C90-----0108 0010 1TAH052000 1100
    MESSAGE_ID--C20-----CNIF_MAT
    MESSAGE_NUMBER--C3--
    1
    MESSAGE_TYPE--C1--
    E
    MESSAGE_TEXT--C72--
    Component assignment not intended for sales order or project stock
    Very kind for one answer of yours to this problem...
    Thanks & Regards,
    Marco Echino.
    Edited by: Marco Echino on Sep 8, 2011 12:16 PM

    Hi Marco,
    I believe this is a Functional Issue rather than a Technical one. If you could speak to the Functional Concultant or pass this data via manual transaction, you will get the error details.
    It's just that the data passed to the BAPI is either incorrect or incomplete. You can also refer the Function Module Documentation for tips.
    Regards,
    Pranav.

  • UCCX - Assigning the active CTI Port to a variable

    Hello,
    I've been rigorously searching the forums here and have been unable to find a way to assign the active CTI port to a variable.
    I'm wanting to assign the active CTI port during a supervised transfer to a variable that we will then be using for an exterior reporting application to narrow down call records.
    I've found the information I'm looking for in the db_Cra under destinationDN in the  ContactCallDetail Table, but cannot find anywhere in the CCX editor that I can assign it to a variable.
    Any information someone can provide on the issue would be very appreciated.  
    Halo Levi 
    UCCX Version 8.5
    UCM Version 8.6           

    Levi,
    A simpler way would be to use a Get Trigger Info step to grab the active Contact object.  Then execute a "toString()" call and extract the current CTI-Port from it.  In the string is a plethora of comma delimted information about the call so all you have to do is look for the CTI-Port number.  It is prefixed by 'TP=" and is usually at the end of the string.
    Below is an example of what to look for.  I've already captured the Contact object into cntTriggeringContact.  I just call cntTriggeringContact.toString() and the output below is what you get.  Those who've used UCCX for awhile will notice that the content is strikingly similar to a MIVR log entry.   Anyway, the TP=03009996230 was the CTI-Port directory number for this particular system.
    Hope this helps.
    -Steven

Maybe you are looking for

  • Canon IR Copiers printing from iPad

    So I deployed the iPrint Appliance 1.0.1.69 to solve our "Can't print from iPad" problem and now am getting stuck at the printer/copier. We're getting a PDL IMG DATA INVALID error on our Canon IR 4075. Anyone else have this problem and conquered it?

  • Premier Pro Shuts Down when trying to EXPORT

    I am a new editor, only at it for a couple month now. The problem I have is when I attempt to export, Adobe closes without warning. I have exported in the past, what I do is, set a work area or just highlight a clip, go to FILE: EXPORT: ADOBE MEDIA E

  • Sony BRAVIA network streaming

    Hello people, I am fairly new to the apple community and i am facing a problem. its been a whole week since i am trying to figure out how to stream video on my new bravia over the network. I ve even replaced my router last night. Equipment: Mac Pro -

  • HT1766 Hi I have a reservation tomorrow and I need to backup my phone but it doesn't backup what shall I do

    Mu phone is not backing up

  • DVD +Copyright/copy protection

    I am a sports videographer. I use Adobe Premiere Elements 2.0 to edit and burn game dvds for my customers. My customers are telling me that they are unable to take clips off my dvds to create highlight dvds or video files to send to college coaches o