Cost Planning Error
Hi to All,
My name is Samad Farooq, currently using SAP Version 4.6C
When creating a cost plan using the transaction code KP06, error is encountered when we try to save the planned data. Error that is displayed is as follow Ledger 4A has fiscal year variant V6 instead of K4.
This specific case is happening only when using the controlling area JVCS and company code MAZ. Company code MAZ uses a calendar year.
Thanking You,
Samad Farooq
Samad.. chech out the process...
The fiscal year variant contains the number of posting periods in the fiscal year and the number of special periods.
You can define a maximum of 16 posting periods for each fiscal year in the Controlling component (CO). To define the fiscal year variant, go to Customizing for Financial Accounting (FI), Financial Accounting Global Settings--->® Fiscal Year -
Maintain Fiscal Year Variant.
Integration
You need to specify the fiscal year variant for each company code.
When you create a controlling area, you also need to specify the fiscal year variant. The fiscal year variants of the company code and controlling area may only differ in the number of special periods used. You need to ensure that the fiscal year variants match, in other words, they may not have a time conflict.
You can assign a company code using a fiscal year variant with 12 posting periods and four special periods to a controlling area that has a fiscal year variant with 12 posting periods and one special period. The time frame, for example, from April 1 to March 31 in the following year, must be identical in each fiscal year variant.
However, it cannot be assigned to a controlling area with 52 posting periods for example.
For more information on fiscal year variants, see the SAP Library under AC Financials -
FI Financial Accounting -
FI General Ledger Accounting(FI GL) -
FI - Closing and Reporting in Posting Periods and Fiscal Years.
Thank you
Similar Messages
-
Cost Planning in CRM Campaigns--Value Distribution Is Incorrect---Error
Hi,
Im working on CRM 2007 (6.0)
I used the standard ones
Planning profile Group--4MKT
Profile--4CRMMP03,
Plan Type--Cost planning
Planning Area--4CRM0001(Marketing Budgeting/Cost Planning)
This is assigned to the category CP in the define planning profile groups node in IMG.
Im able to view this in WEB UI 2007, however when i choose DISTRIBUTE, im not getting the BPS Layout appearing from BI Planning.It is appearing in Tcode-BPS0(BI) perfectly but not in CRM WEB UI.IM getting the error------Value Distribution Is Incorrect
Im basically looking at that layout to appear in the campaign where i can key in my planned costs, resources and then i would like these values to be sent to ECC and BI will extract them and provide reporting.
Is this a standard functionality or should i necessarily use a EEWB field, if so how?Hi Noah.
Please check the following things:
- Whether the Planning Profile 4CRMMP03 has been activated from Client-000 of BW system and transported to Client-800
- After activating the Planning Profile 4CRMMP03 in Client-000 and transporting to Client-800, go to transaction bps0 in BW system and select the planning profile tree. Right click on it and set the profile.
- Check whether Planning Profile 4CRMMP03 is associated to multi Planning Area, which will consist of basic planning areas.
- Check whether at Planning level, Characteristics and Key Figures are selected and filtered.
Wish this will be useful to you.
regards
Srikantan -
Dear All
When I try to create easy cost planning on WBS level by click button ECP system open screen "Edit Costing" instead of "Create cost estimate" When I try to enter version 0 & costing variant PS06 system give error message version 0 not for Easy Cost Planning. First I don't know why system open screen "Edit Costing" instead of "Create cost estimate" please anyone give inputs on same.
RegardsHi Pramila,
Check weather the version is allowed for planning.
In SPRO, Costs- >Create CO Versions , check weather the version 0 is defined and also check weather the Plan check box is checked.
Hope it helps
Warm Regards,
Punith. -
Hi Experts,
When i am going to do the cost planning in the CJ40 cost element wise it is giving an error message as
Layout 1-701FG contains errors.
Message no. K9156
Diagnosis
One of the elements of planning layout 1-701FG contains values of a characteristic which is not part of the current application. Thus, the planning layout is not compatible with this application.
The characteristic here is FKBER
I had created the planning profile & in that planning profile i had assigned the Cost element group & that cost element group i had mentioned the cost elements also..
The cost element group i created in KAH1 & assigned the cost elements to it..
Can u please suggest from your vaild inputs.
Thanks & regards
Raman T SHI,
For this i raised the OSS message & i got the solution that if we had activated the Funds management, & want to use the standard Layout is the SAP, then only two opitions are there as per the SAP standard,
1) We should activate the Funds & the Functional area,
2) We should activate the Funds, Funcational area & Grants.
Reply in the OSS message
Funds activated can be seen in the table FMISPS in SE16.
In general the layout 1-701FG could only be used if as in combination
both components 'Fund' ! AND ! 'Functional area' are active.
No SAP-Standard-Layout exists for using ONLY 'Functional Area' or 'Fund'According note 489315 please create your own planning layout as
a copy from 1-701FG as you have checked before.
SAP does only support the following combination:
- fund and functional area activated
- fund, functional area, and grant activated
Therefore in order to use the Standard Layouts you must activate
BOTH Funds Management AND Functional Area.
If you would like to use only your own-defined layouts, then you have
to modify the standard coding as described in the attached note
47207 CJ40/KO12:User-def. plan. layouts for detailed planning
You can go through the some of the SAP notes 47207 & 489315.
Thanks & Regards
Raman T S -
Cost element error while processing GR of Subcontracting sch.agreement
Hello All,
While processing GR for a Subcontracting Sch. Agreement, the system gives the following error:
Cost element 50050002 is not assigned to a cost component in CostCompStruct M1
Message no. MLCCS010
Diagnosis
You have activated the actual cost component split.
No cost component has been assigned to cost element 50050002 origin group in cost component structure M1 for chart of accounts MMC. The system is unable to assign the value to a cost component.
System Response
You cannot carry out posting.
Procedure
Check whether for this operation the value to be posted is to be assigned to this cost element.
If the value has been assigned to the wrong cost element, you should change the account assignment for this operation.
If the value has been assigned to the right cost element, then maintain an assignment of the cost element and origin group in Customizing of Product Cost Planning.
The Sch.agr contains the parent material and the child part is maintained in the Component overview for that material in Maintaining the sch.line.
What should be looked into.
Please help.
Regards,
ManojHi,
Check on it;-
http://www.sapfans.com/forums/viewtopic.php?f=6&t=300552
Cost element not assignment to Cost component structure when activated M.L
pherasath -
Valuation with material cost estimate: error with product "117122"
Hi people,
We have the error:
=====================
Valuation with material cost estimate: error with product "117122"
Diagnosis
In Profitability Analysis (CO-PA), the system tried to valuate a line item using the current standard cost estimate.
In order to determine the current plan period, the system needs to read the valuation segment of the material master.
The system has found that the current plan period is not filled forproduct "117122" in plant "UBE1".
We have the follow configuration in trans.: KE40:
. Determine material cost estimate
. Transf. Standard Cost Estimate
. Costing Variant
. Control Data for Standard Cost Estimate
. Period Indicator = "Current Standard Cost Estimate acc. to entry in mat master
. Addiitonal data CO-PC
. Transfer cost estimate in controlling area currency "activated"
We think the reason about our error is because the field above is activated and some configuration more is necessary for this case. For examplo: Trans.: OKYW and this one was not configurated yet.
Do you know what happend?
If we need to configure some transation, or sonly process the cost estimate?
Thanks,
Rosana.Hello Guido
Thank you very much for your return.
It is happenning in a Client that some people are doing the configuration.
Before we didin't have in KE40, the fiel "Transfer cost estimate in controlling area currency" activated.
And now, the people activate that in this new Client and I don't know the impact about that.
I think we have to make the configuration in OKYW.
The other transation you told me, we don't have any information.
Could you tell me some other idea what happend?
Message error is just "Message no. KE350"
Abou claculate the cost:
It was calculated by trans.: CK11N for future planning and the real wasn't not possible to release because this material already have moviments.
Could you tell us is there is some thing more to do?
Thanks,
Rosana. -
Personnel Cost Planning - Detail Planning
I would like to ask you if some user in R3 system can handle the detail planning functionality of personnel cost planning component for all the plans-scenarios for all existing organizational units;
how is it possible and through wich connection between the user and this role.
(For example this user must be able to add or to increase cost items to the total sum of the company)
thanks a lotHello Andreas,
Please review the note 736170 and make sure that the suggested support package is implemented in your system.
And also please check if your cost plan has the 'Detail Planning Possible' date filled in, because it should be maintained.
If Badi HRHCP00_RESP_OBJECTS activated, then did you try to regenerate the Badi definition for checking the
resposible objects? (Se18)
Is any other Badi activ instead of this one?
In IMG - Cost Plan Runs - Badi Specify Authorizations & Objects in Area of Responsibility if badi is activated, see if you get this error if you deactivate it.
Please check further the configuration for the BSP application. Is transaction PHCPDETLC called properly?
See also the note 592085.
Best Regards,
Shree -
Easy Cost Planning version 0 cannot be used in DP81
Dear SAP Expert,
Please advice.
We have requirement to do sales pricing in DP81 with project and inquiry.
Some steps that we are doing :
1. Create Inquiry : VA11
2. Create Project : CJ20n
3. Create cost planning with network activity in CJ20n and use Planning cost version 1. ( We are trying to use more than 1 version, not only version 0)
4. Run DP81. It shows error message no expenditure.
In the config ODP1 ( DIP Profile) , version has been activated.
Is there any solution to use ECP with version more than version 0?
Appreciate for the advice.
Thank you.
NiesHi Sanjeev,
Sales Pricing (DP81) can read ECP with standard version 0. The issue is that DP81 cannot read version other then 0.
I need to do planning cost using version other than version 0 ( Actual/Planning version)
Thank you for your advice. -
Easy Cost Planning & Project Stock
Dear Experts,
I am using Easy cost planning for WBS cost planning and Project definition control data tab page has Valuated Project stock selected.My costing model had an external procurement material for which I generated PR & PO thru Execution services.But the account assignment in my PR & PO was P with the corresponding WBS as account assignment and not Q.
I have two question regarding this,
1) Does it mean that while using ECP, Project stock concept will not work?
2)How can we get the pop up of procurement type options(like Res + PR for WBS element) while generating PR through execution services?Hi,
I am replying again because in my last answer there was some typing mistake.
Hi,
I tried your scenario is my system.
whenever i am changing P to Q in Config in SPRO,It is giving an error that "The selected account assignment category is not supported" that means it is not meant for Q but i double click for object type PR WBS Element and changed Acct Assgmt Cat to Q then system allowed me to save.
The i create a PR and WBSE is coming in the Account Assignement ,then i converted PR to PO and then i recived goods as project stock.when i issued the material in ECP it is not issuing from Project stock because 221 Q is not present in Config for SPRO so it is issuing from Normal stock so special stock from ECP is not supported.
But you can manually issue the material to the WBSE in MIGO/MB1A by 221 Q.
Hope it is clear.
Muzamil -
Easy Cost Planning-prob Costing model
Hello ,
I am creating costing model
i want at time of Easy cost planning court fee(Characteristics) to be selected from drop down list
i have made characteristic court fee ,in currency format
(CKCM) while defining derivation rule(template), if i am mentioning quantity as court fee
Facing error that Syntax error in quantity
Pls help
ThanksAfter Double click on Qty , you have to define the formula there,
correct your Formula which may be wrong leading to Syntax Error.
Regards,
Nitin -
KP06 - No transactions for cost planning are defined in the Nos range table
Dear CO Experts,
I m trying to post Cost Planning using T-Code KP06.
please help, the Error which pops is :
*No transactions for cost planning are defined in the number range table*
*Message no. K8007*
*Diagnosis*
*You want plan primary or secondary costs/revenues in controlling area 9000. This is not possible because no entries exist in the number range table for the cost planning transactions you want to perform.*
*This is an internal system error.*
*System Response*
*Processing is terminated.*
*Procedure*
*Start program RKTKA04C.*
*Execute*
*After the program has run successfully, start planning again.*HI,
the planning subobjetcs to be assigned in KANK to a CO-number range are (maybe you do not need all of them):
KAZP
KOAP
KPPB
KPPZ
KSP0
KSPB
KZPP
KZRP
PAPL
RKP1
RKP2
RKP3
RKP4
RKP5
RKP6
RKP7
RKP8
RKP9
RKPB
RKPL
RKPQ
RKPS
RKPU
RKPV
RKPW
RKPX
RKPZ
best regrads, Christian -
Hi All
i have created an investment project structure and attached 2 levels of WBS Elements.
When i'm executing the " Easy Cost planning" the system is showing the following message.
" No WBS elements have been created for the Project yet"
and the details of the error is
Diagnosis
You have not yet maintained any WBS elements for the project. You can onjly maintain costings for WBS elements.
System Response
The system cannot create a costing.
Procedure
Create WBS elements for the project.
Pl give me the solution
Thanks & regards
pavanHi Pavan,
I am also working on Investment Project scenario. Do you have any docs related to this scenario, like, FSBP or BBPs? If yes, please send them to me. See user profile for further details.
thanks
Pratap.V -
Personnel Cost Planning and Simulation - Detail Planning
Hi,
I am trying to access the PCP Detail Planning (t-code PHCPDETL) and for any of the Plan I choose it gives me the following error:
No Object exist in your area of responsibility
No data exists for the objects you are responsible for
We are on SAP ECC 6.0 EHP 4.
Many Thanks
Asim KhanHi Asim,
First of all check note 736170 and see if you have sugeested SP implemented in your system.
Also check if your cost plan has the 'Detail Planning Possible' date filled in.
Then check if Badi HRHCP00_RESP_OBJECTS is activated in your system. If it is, then make
sure you regenerate the Badi definition for checking the resposible objects in SE18. The problem
might be another Badi active here instead of the one I mentioned.
Also check IMG - Cost Plan Runs - Badi Specify Authorizations & Objects in Area
of Responsibility if badi is activated. Do a test - see if you get this error if you deactivate it.
Make sure configuration for the BSP application is OK and if PHCPDETLC is called properly?
Note 592085 can be also handy.
Kind regards,
Andrzej -
Actual cost splitting error (Equivalence numbers)
Hi
I am facing an error during actual cost splitting (KSS2) . The situation is working fine in the case of Plan cost splitting (KSS4)
I want to split costs in a cost centre based on equivalence numbers. But, i dont see any option of maintaining equivalence numbers for actual cost splititng. The option is available ONLY in KP26..
Hence, I have maintained equi no.s only in KP26. This gives me error in KSS2 Quoting some divergence error. The message reads that activity price calculation did not converge
It shows me a picture on screen which displays a loop between activity types. I am unable to understand it
Can any one guide me on this??
Any help wud be promptly rewarded
Regards
AjayHi Mahe,
Here Kss4 Before cost centers are assigned Splliting Structure to cost center r not Plz check.Then Only it Work.Actuval cost Splliting is Working Based On the Production Order Conformation and U r Fi entry Poistings Related to cost Planning.
Best Regards
Nagaraju Sami -
Throug Easy cost planning process in proj systems ,i want to do sales cycle
throug Easy cost planning process in proj systems ,i want to do sales cycle
i am new to proj systems module
i am trying to create 1 PS :quotation --> PS: Order > PS Billing Request>F2 Billing through Easy cost plannng methodology.
i also created till 1 PS :quotation --> PS: Order --> PS Billing Request without Material
while entering a WBS in quotation --> PS: Order --> PS Billing Request ** randomly from F4 options then system is picking but after saving , the selected WBS is not displaying.
at the creation of F2 invoicing , system is throwing an error as "Document 70000074 does not contain any items with open quantities"
Pls guide me in a better way even i dont know the full funda of Easy cost planning .
regdsSunitha
go through the following links:
http://help.sap.com/saphelp_46c/helpdata/en/b4/cb2d28e4ded31184080004aca6e0d1/frameset.htm
http://help.sap.com/saphelp_46c/helpdata/en/51/5828e4a44c11d189bf0000e829fbbd/frameset.htm
I hope these links will help you.
Maybe you are looking for
-
Vista - Can't connect to iTunes store
Hi Since upgrading to Vista I can no longer connect to the iTunes store, log into my account or update artwork. I get an error message asking me to check my settings and occasionally an "error-3150". I have no problems connecting to the internet with
-
I cannot install iTunes OR quicktime
I have taken quicktime off of my computer and tried reinstalling it; It didn't let me re-install it. Even from the iTunes website. I have also taken off iTunes and have tried reinstalling iTunes 8. It will not let me. Also. I believe I have Vista 32.
-
When I try to install iTunes 10 it cuts in about 3/4 of the way saying that "Cannot remove and earlier version of Bonjour"....PLEASE HELP!!!!!
-
i am new to java and facing problems in importing package which are self made. secondly does JDK 1.1.3 can support swing
-
"Role not defined for individual users" on user import
Hello, I am trying to import a certain user from one portal to another and I get this warning message: "Role <pcd_role_path> not defined for individual users." This role is assigned to this user at the 1st portal and exists at the 2nd portal at the s