Hi friends,
For sales order if costing contains any error then sale document should not
save.
Can we put check like this? If so how?
Regards
Rama rao
Hi,
Anyupdates on this please.
Ratna
Similar Messages
-
Error reading material cost estimate for sales order (KE292)
Dear All,
I have an issue with billing. we are posting july month transactions, the material cost is maintained through MR21. When releasing billing document for accounting we are getting error message like"Error reading the material cost estimate for sales order "11"
Message no. KE292
Diagnosis
In Profitability Analysis (CO-PA), the system tried to valuate item 000010 of sales order 11 by reading the corresponding product cost estimate.
However, no product cost estimate could be found for this sales order item.
The system accessed product costing for product AMLFP011011XX00P using costing key YB3 as defined in the
CO-PA Customizing settings.
System Response
The system cannot process the document any further.
Procedure
Check your Customizing settings."
We cross checked with other client as a current date and we ran cost estimate through CK40N with same material. and we posted entries. Here it is working fine. but in above process it is not working. Can you pls guide me where i missed.
Regards,
Nagaraju,Hi,
When the Costing Key is assigned to the material types in the COPA customizing, then system expects Cost estimation when billing is released to Accounts.
If you dont run cost estimation but update the material master through MR21, system will not accept as in the Costing key configuration you must have selected the Current Standard price field for the valuation.
Hence, try to run cost estimation and then do releasing.
Thanks & Regards
Ravi Kumar -
Plan cost of Valuated Sales order
Hello,
I am using Valuated Sales order and wanted to see the Plan cost is sales order report KKBC_KUN.
a) When i use a costing variant in the Requirement class with automatic marking, i am able to see the plan costs in the sales order report.
b) However if i dont use and costing variant in the requirement class and instead use the valuation with standard price of Make to stock inventory (with out val.strategy is checked), my sales order report does not show the plan cost.
I want to use option (b) and also see the plan cost in the sales order report. Is this acheivable.
Regards
RaghuHi Raghu
Valuation Indicator in Req Class and Costing fields in Req Class are independant things
You can specify valuation field as A (No Separate Valuation) and still use the Costing fields to calculate sales order cost estimate.. This will remain for info sake only
However, it does nt make sense to calculate SO Cost est if you dont use that in valuation
br, Ajay M -
Suppress Cost Feild in Sales Order
Hi everyone,
Client wish to Suppress cost field in Sales Order, as well as in Invoice document.
I searched the SDN, and checked SHD0 for BUS2032 --> BUS2032_4440 & BUS2032_4480; but unfortunately, I haven't got any clue.
May I request you to guide - how may i acheive the same?
Is there any Enhancement work required? If so, then please guide on the same, too.
Thanks in advance
- Sumi.Thank You Sidi and Typewriter for your responses.
Condition Type "VPRS" needs to be present and calculated. The requirement is that Condition must not be visible in Sales Order and Invoice Document or in Outputs. So, I am not sure - how much will it be applicable if I deactivate it in VOV7.
Also, the wiki shared, is not much helpful and in Technical Information, VRPS is stored in Structure, and I have not found any Table/ Field in any of the existing Screen Variants, as I have shared in my very first post.
Also, We are interested to use Standard Transactions only VA01/ 02/ 03.
I will really appreciate if one can guide, the procedure, in case, I am doing wrong.
Thanks,
- Sumi. -
they get the consumption of sales using customized transaction
actual cost is zero
user create the material master withot pricing
we ask to update the material master and they do the costing run
in material master standard costing estimate found
after they run the consumption report ,once again actual cost is zero
i chech\ked in costing status using CK11N ,std cost estimate found
is it possible to update the cost in sales order
(redetermine or recalculate the pricng in sale order)
so that my consumpotion report will update
thanks
Edited by: Suresh Kumar on Jul 26, 2011 4:59 PMHi Suresh,
I hope ur doing MTO Scenario.
for this u need not do standard cost estimate.
during sales order creation VA01 > extras tab > Costing. u can do costing for each customer aganist each sales order.
not for each product.
for do it u need to maintin some of the settings .Check Requirements Classes .
if u maintain Costing ID B Automatic costing and marking.
in requirement tab if u maintain these settings when ever u save sales order it calcutes sales order cost estimate and released automitically.
thanks
kareem -
Simulation of Standard cost for closed Sales order in CO-PA
Hi Experts,
We are using sales order costing and hence when sales are booked, standard cost is flowing into CO-PA. Is there any possibility that we can simulate standard cost for closed sales order on the basis of current standard cost in CO-PA ?
Regards,
Pawan KumarHi,
Check if tcode KE4TS helps
regards
Waman -
Credit check at sales order level?
Dear experts
I want to set credit check at sale order level with following conditions
consider open deliveries for credit exposure
consider billing documents for creadit exposure
do not consider any open orders
Also if oldest items are open for more than 7days then block the sale order creation
e.g suppose customer is having credit limit Rs.100000/- and open deliveries against this customer is having the value Rs.50000/- i.e. credit exposure is Rs.50000/-. In this case system should block the new sale order created of value more than Rs.50000/-
plz suggest the configuration steps
regards
kailashdear friend
For i am already having the same setting but still my scenario is not working. i will explain my scenario again
suppose customer is having credit limit Rs.100000/- and open deliveries against this customer is having the value Rs.50000/- i.e. credit exposure is Rs.50000/-.
In this case system should block the new sale order created of value more than Rs.50000/-
But with the said settings purpose is not getting solved.
my settings are;
In OVA8 ;
Update: 000015
Static check: TICK
Status: TICK
open deliveries: TICK
Plz suggest
kailash -
Hello,
I'm seeking to enable in BI a Cost Analysis Scenario with repect to the <b>Sales Orders</b>. That is, something similar to the analysis you can easily perform in the R/3 area <i>Accounting -> Controlling -> Product Cost Controlling -> <b>Product Cost by Sales Order</b></i>.
For instance in standard report KKBC_KUN, you can choose a sales order number and get all the <b>cost elements</b> related to that sales order, with the corresponding costs.
I have examined the following objects provided by the BW's Business Content:
- <u>InfoCube 0PC_C01</u>: it contains only the costs related to <b>production orders</b>, and not the costs associated with sales orders.
- <u>InfoSource 0CO_OM_CCA_9</u>: it seems interesting, in fact it delivers some header and line item data of the <u>Controlling Object Document</u>. Unfortunately it doesn't deliver the crucial characteristics <i><u>Controlling Object</u></i> and <i><u>Controlling Object Type</u></i>, which I definitly need for enabling my analysis scenario!!
(By the way, are these 2 characteristics delivered by the BC? There exists a 0COSTOBJ characteristic, but it's not used by any object in the flow afterwards. Moreover, I can't find a standard DataSource in R/3 which I can use to load either its attributes or its texts, and see what data enter it..)
Business Content for Product Cost by Sales Order), but none could help me.
It seems really weird that it's not possible to carry out a <b>Cost Analysis by Sales Order</b> in BW, so if anyone has some suggestion it'll be very appreciated indeed.
Thanks & Regards, DavideI eventually found the following SAP Note. No BCT for this analysis scenario....
<b>Note 584791 - BW-BCT-CO: Costs not extracted on sales orders</b>
<b>Symptom</b>
In R/3, costs are posted directly to sales orders. The costs have to be analyzed in the BW system. In the standard system, however, this data is not extracted into the BW system.
<b>Other terms</b>
0CO_OM_OPA_1; 0CO_OM_OPA_6
<b>Solution</b>
1. There are currently no DataSources for costs on sales orders in the standard BW Business Content. Unfortunately, there are currently no resources scheduled for a new development in this area either.
2. Therefore, the DataSources and the Business Content must be created in the customer project within the framework of consulting as a customer solution concerning the generic extraction options of the BW Service APIs or function modules you have programmed yourself for extracting data.
3. Technical background information about costs on sales orders:
The transaction data is available in the following R/3 tables
COSS and COSP - Totals records or COEP - Line items.
This concerns records for the VB* object numbers.
The master data of the sales orders is contained in the VBAK and VBAP tables.
The 0CO_OM_OPA_1 and 0CO_OM_OPA_6 DataSources only extract costs for orders with master data in the AUFK table. These types of requests always have OR* object numbers. Therefore, these DataSources cannot be used for sales orders.
However, you may be able to assign requests from the AUFK table (for example, maintenance orders or production orders) to a sales order through the AUFK-KDAUF table field. -
Sales Order Report Showing Cost on the Sales Order & total invoice dollars
I am looking for a report in SAP that shows you the Sales Order number, the cost on the sales order (NOT the average cost) the actual cost on the sales order detail line and then the total invoice dollars in month to date and year to date?
Thanks,
LindaYou can use <b>T.code: COOIS </b> if Product Costing has been configured for MTO scenario whcih gives the costing details.
You can also use To.code: <b>KE30</b> if CO-PA implemented.
but if you want to link with billing, Please search for any reports in Sales information system.
One more you can create a ABAP Query Report using T.code: <b>SQVI</b>
Regards,
Anbu -
How to transfer cost from old sales order (cancelled) to new sales order
Hi Gurus
I want to know, how to move cost from one sales order to another sales order.
SD created sales order before 1 month and there was production order behind this. Production was completed and all the cost was moved to sales order and also SD has raised invoice on customer. This transaction was completed.
The above order was rejected by customer due to some changes in the order. SD raised another sales order and production order was created to to additional work. Production transfered above stock (produce before on old production order) to new production order.
My problem is stock is now transfered to new production order but cost is still sitting on old sales order. How do I transfer cost from old sales order to new sales order. SD cancelled old invoice and raised new one with full value (old + new work) on new sales order. Now cost is on old sales order and revenue is on new sales order.
Please help.
ThanksHi
I have reverse the sales order settlement, PP order settlement to sales order and I have also done KB11N for transfering the cost to the new production order.
The only problem is I was unable to transfer labour hour confirmation as cost element used for this are not for transfering cost. If I will reverse the confirmation in PP order system will reverse material movement also which I don't want any more. Can you please tell me how to I reverse the Labour hours with out affecting goods movement?
Many thanks -
Partial Delivery when the complete delivery flag is checked in Sales Order
We do the ATP check in APO when we create a sales order in R/3. We have "complete delivery" flag checked in Sales Order. But when we create batch orders say may be of 20, one of 20 is confirming with partial delivery.
We thought the issue is with ATP locking and we increased the re-attempts, but invain. We still have this partial confirming problem.
Appreciate your co-operation.
Thanks,
Sarath.Have you maintained the following setings in R3:
Material Blocks in R3:
MenuPath: SAP Customizing Implementation Guide ® Sales and Distribution ® Basic Functions ® Availability Check and Transfer of Requirements ® Availability Check ® Availability Check with ATP Logic or Against Planning ® Define Material Block For Other Users
Global Settings in APO for Availability Check:
MenuPath: SPRO>APO>GATP>General Settings>Maintain Global Settings for Product Availabilty
Questions for you:
(1)R3--Does the Availability CHecking Group you are using for your material and the initiator-A has the block checked.
(2)APO-- Has the TQA box checked in the global settings for Availability in APO
(3)Also what happens when AVAILABILITY CHECK is done manually for one of the partial confirmed order with Complete Delivery indicator set.
Regards
Kumar Ayyagari
null -
Cost center in Sales Order/Credit memo request
Hi SAP Gurus,
There is a requirement from our client. They are processing Credit Memo from SD VF01 via Credit memo request. The want to assign Cost center in the line items which is greyed out at the time of processing in VF01.
I also verified in the Credit memo request in VA02 even there is no field available for to maintain Cost center in line item so that at the time of billing it can derive.
Please advice whether can we assign the Cost centers in Sales order/Credit memo request line items?.
Regards
NTHHi NTH,
In the standard system, the field cost center is only ready for input
if the sales document category is VBAK-VBTYP= I (that is, order without
charge). For all other order types, you can make it visible by entering
an order reason provided that the combination of the sales area and the
order reason has a cost center assigned in OVF3. To change this standard
behaviour, USEREXIT_COBL_SEND_HEADER can be used. There you can find a
short example on how to make a field visible and modificable in the
account assignment screen.
Moreover, please take into account that the account assignment to a cost
center is possible only at header level. So it is not possible to
insert the cost center at item level, you can only insert it at header
level.
The cost center determination takes place in
FV45KF0V_VBAK-KOSTL_ERMITTELN and is reading from table TVAUK.
This table can be maintained in transaction OVF3.
If you wants to be able to enter the cost center manually in the
account assignment screen (header level), you can use the user exit
FV45PF0C_COBL_SEND_PBO_VBAK (SAPMV45A) - there you can find a short ex
ample on how to make a field visible and modifiable in the account
assignment
I hope that this information is of assistance to you. Thanks!
Regards,
Alex -
Availability check at Sales Order Create
Dear Experts,
I want to do availability check at sales order creation stage (VA01). My requirement is, the system should check the sales order line qty against the unrestricted stock. And if sufficient stocks not available it should prompt an error message.
In more detail; unrestricted stock of material X is 100 PCs. I put a sales order for the same material for 101 PCs. Then systems should block me from saving the order.
Can some please provide me detailed step-by-step action for configuration of above scenario. Thanks in advance for your support
Regards,
RaminduHI,
User exits in program FV45VFZZ
USEREXIT_ADD_FIELD_TO_HEADER
USEREXIT_ADD_FIELD_TO_LINE
User exits in program FV45VFZY
USEREXIT_DELIVERY_GROUPS
USEREXIT_MVERF_INIT
USEREXIT_QUOTA_KEY_VALUE
User exits in program RV03VFZZ
USEREXIT_AVAILABILITY_IN
USEREXIT_AVAILABILITY_OUT
USEREXIT_DARA_REFRESH
USEREXIT_PLANT_SELECTION
Check these user exits also very helpful to you.
Regards,
kishore. -
Hello Experts,
I have few questions regarding the credit check in FI-AR credit mgmt and SD.
Currently we have a credit check in AR credit mgmt during the delivery order creation. But the management has decided to crap this and to put a credit check at sales order level.
Can someone tell me if there is any business process change in doing this?
Whats the concept of Horizon in dynamic check?
Can someone clarify the concept of Business Partner in SAP FSCM credit mgmt?
Any help in this regard is highly appreciated and duly rewarded.
Regards,
Sriramhi,
pl check this :
[Credit management|http://www.sap-img.com/sap-sd/credit-management.htm]
Dynamic Credit Limit Check with Credit Horizon
The customer's credit exposure is split into a static part; open items, open billing, and delivery values (see above), and a dynamic part, the open order value. The open order value includes all undelivered or only partially delivered orders. The value is calculated on the shipping date and stored in an information structure according to a time period that you specify (days, weeks, or months). When you define the credit check, you can then specify a particular horizon date in the future (for example: 10 days or 2 months, depending on the periods you specify). For the purposes of evaluating credit, you want the system to ignore all open orders that are due for delivery after the horizon date. The sum of the static and dynamic parts of the check may not exceed the credit limit.
regards
sadhu kishore -
Bottom/base price check in Sales order processing
Hi
In my company we are using process Sales Order > DO > Billing. Same pricing procedure for sales document types and billing types. No pricing procedure for DO. Our management wants to implement bottom price check in sales order processing e.g there must be one sale price on which sale invoice will be booked and there must also be one static price maintained and system will check after all taxes and discounts calculation that net value should not be less then bottom price.
Currently we are using user exit in enhancement MV45AFZZ. Our ABAPER has written logic in this of following scenario. We have maintained commercial price in ZCOM condition type and bottom price in ZBAS condition type. Lets take and example
ZCOM = Sale price= 500
ZDIS = Discount = 100
Net value/Amount for credit check 500-100 = 400
ZBAS Bottom price = 450
In above scenario system should not allow to save sale order/billing document and give error "Sale price is below bottom price" Then user will change the discount from 100 to 50 and Net value will be then 450 and system will allow to save sale order/billing document.
I want to to do this in Pricing procedure pricing routines. Please tell me is it possible with calculation types? Im wondering if we can do this in enhancement then we must write the same logic in VOFM pricing routine and we can control this from there too. In our current ABAP check everything is working fine but I just want to minimize the use of ABAP checks and enhancements and control the things from functional side not from ABAP.
Please let me know if someone need more clarification or someone have any productive suggestions in this regard. If there is any other solution it will be highly appreciated.
Thanks in advance.Similar functionality is already there, where if the net price of an item differs from "Customer expected price" (conditions EDI1/EDI2) then SAP automatically pushes the order into incompletion. You can ask the developer to see how EDI1 is used in the pricing logic.
However, the condition EDI1 is used to check if the item value is different to Customer expected price in case of EDI orders and is not standard for your requirement. But you get my drift, that you can have your own condition in the pricing procedure that will fetch the base price value and can be used in the logic to show an error message (to stop order processing) or push into incompletion log similar to condition EDI1
Maybe you are looking for
-
Is there a way to find all changes made to a range of vendors? Our auditors are wanting to validate that our vendor changes are being correctly documented so they've requested a report showing all vendor changes in a certain time period. I don't re
-
InDesign CS3 pstopdffilter Printing Error on Intel Mac
I'm having a problem printing in InDesign, now that I've upgraded to CS3. I've uninstalled all Adobe products and reinstalled, and I was able to print, but had a printer error on another printer, and now I am having the same "pstopdffilter" error as
-
How can I find out what my password on the computer is? I had to change it due to my teenagers helping themselves, and now every time there is a system update, I have to have the password, which I cannot remember or find. It then wants it every tim
-
Disadvantages in prepared statement
hi i could not tell the answer for the following question in my interview can u pleae tell me the answer for this question one of the disadvantages with prepared statement in jdbc?
-
What is the latest version of Photoshop? Photoshop CC or Photoshop CC (2014)?
I ask because I have both installed and would only like to keep the latest version. Thanks