why is that when i batch determined my production order, the system doubled the required qty and two batches were allocated. originally, 250 was required. when i clicked batch determination, system doubled the qty and split two batches for it. this is weird behavior and must not happen!
>
Dhaval Choksi wrote:
> Hy Raf,
>
> Pls do below checks,
>
> - Is the qty of that component in Component screen of Production order is OK and only at the time of Batch determination this probelm exist?
> - Have you use any alternate unit of measure for that component in BOM ?Then confirm its conversion factor and also its use in Order.
> - Pls check required qty for Order qty by using transection code CS11/CS12/CS13.Is it OK there ?
>
>
> Regards,
> Dhaval
>
> Edited by: Dhaval Choksi on Aug 5, 2008 5:46 PM
1. It is correct on initial Production Order. When i batch determined, the original one line of 250, became 2, with qty 250 for each line
2.No alternate UOM is maintained
3.It is correct in CS11, it explodes correctly
Similar Messages
-
GR quantity check against Production Order in MB31
Hi Experts,
How to check GR quantity against Production Order (101) can not be greater than Confirmation quantity for the Production Order in MB31.
Regards,
Praful MankarHi Praful,
Use user exit MBCF0002, here put condation that check AFEU table (confirmation table) and allow
that quantity only to do GR
and it will triger at the time of MB31
Regards
Girish -
Error in cost calculation for production order
Dear All,
I got error of cost calculation while release of Production Order due to price of some material is not mantain .
What will happen if I release , save the Order with error & do Good Issue ???
IshwarDear Ishwar,
Check the log's created for costing and rectify the same.
I feel its better to rectify the cost related errors and then release the production order and proceed to Good's Issue.
Check whether there is a MAP for all the Raw-materials and an origin group in costing 1 view.
The Finished product must be having a standard cost estimate that's valid for the current period.
Revert back in case of any more help needed.
Regards
Mangalraj.S -
GR quantity more than production order quantity triggering cost difference
Hi Gurus,
We have observed a scenario where the cost(price) dfference account getting hit whenever the GR quantity is greater than the production order total quantity. The dollars posted to this acount are directly propotional to the difference between the GR quantity and the production order quantity.
The total quantity specified in production order is 1 M2U and GR quantity is 1,000 M2U.Material price is $195.65.
Accounting Document;
Inventory account - 195.65
Offset account - 200.00
Cost difference account - 4.35
If we do GR for less than or same quantity as in the production order, this account is not getting triggered.
Any idea what is causing this scenario? I really appreciate if you can share with any SAP note related to this.
Thanks,
Mano.Hello Gurus,
One more observation is,
The palnned costs and actual costs are always different when dealing huge quantities. But the cost difference account is only getting triggered if the actual quantity is more than the palnned quantity.
And,
when the difference between atual quantity and palnned quantity is huge then
Planned costs are booked to the inventory account
Actual costs are booked to the prodcution cost account.
Significant cost variance is booked to the cost variance account.
When the difference between actual quantity is less than/equal to planned quantity is not so huge then
Actual costs are booked to the inventory account
Actual costs are booked to the prodcution cost account.
Is this a standard behaviour?
Thanks,
Mano. -
Quantity mismatching in production order
Hi PP experts,
The delivered quantity for a production order in CO03 is 53 while Goods receipt has been done for 59 materials. You can refer the below screen shots.Hello
Please implement and run the report ZPCON_076D, from the following note, in order to correct such inconsistent orders:
1352231 - Correction: Goods receipt quantity and value in order
This repor sum the posted goods movement quantity and updates the delivered quantity on the order.
BR
Caetano -
Run time error while running BDC for production order creation and confirmation:
Dear Gurus,
We have a situation, where the users are trying to do the entries creation of order or confirmation (through manual and BDC). But, if there is any kind of a deficit quantities in consumption or GR quantity, then it is going to run time error and Dumps are coming in program SAPLCORB
and the transaction code is coming for CO11N.
How to avoid this error to run the production system in smoothing way...Any flash lights on this will be great full
Regards,
Madhu.GHi Madhu,
Expert Caetano has rightly point out. Refer Note 1840705 - RAISE_EXCEPTION short dump if running CO11N in background
Cause
The short dump is triggered because SAP transaction CO11N contains new GUI elements that cannot always be dealt with in a background process,
such as the confirmation texts.
Resolution
SAP recommends that the standard production order BAPIs, such as BAPI_PRODORDCONF_CREATE_TT, should be used to post a confirmation in background.
If this is not feasible, the following workaround may be uses:
Define a confirmation profile in transaction OPK0;
In the detail areas, remove the area "Confirmation text";
Set this profile as standard, so that it is chosen automatically by the system when a batch-job
is started;
Assign this confirmation profile to the batch user with transaction SU3 using parameter CORUPROF.
Also see Note 429432 - CO11N: Batch input in background dumps if long text is maintained
Refer to note 1154692 - Endless loop during confirmation in background if you doing Auto GR during confirmations
Thanks & Regards,
Ramagiri -
Error at the time of Production order cancellation.
Hi PP Gurus,
The transactions happened when Sales order costing was activated
1. Sales order created
2. Production order creation, release
3. Production order confirmation and QM lot created
4. QM lot cleared with Result recording and UD has taken
5. While doing PGI system started to ask about Sales order costing
Now as per CO requirements all the documents has to be reversed and Sales order has to be deleted. But when I'm trying to cancel production order confirmation, it's giving error that Stock of Sales order quantity is deficit in Quality stock (As it is already moved to unrestricted Sales stock). And when we reversed it through Movement type 322 its giving error like UD has already taken for partial lot....
We tried following options.
1. Another Sales order irrelevant to Sales order costing created and we tried to move stock from old sales order to new sales order through movement type 413E but got the same Sales order costing error.
2. We tried to move stock from old Sales order to unrestricted use, same error we got.
As per my knowledge UD can't be reversed in Standard system.... What could be done in that case... Please help if some one faced the same situation.
Thanks & Regards,
Abu ArbabDear,
If you want to change UD code, it is very simple from QA12. But if you want to reverse goods movements also, it is some thing big process. please check OSS notes 175842.
Please check SAP note note 33924 Reversing the UD and 175842-QM lot stock reversal.
Please refer my reply in this thread also,
UD cancellation or reverse after GR
Please go through the transaction CO09, you enter your plant,Material, MRP area (Plant) and Checking rule then execute, it will take you to next screen there you can able to see what are the conformed quantities for the Sales document wise(Reservations), and also you can see the current stock possition (Cummiletive ATP Quantity).
Regards,
R.Brahmankar -
Change input quantity of a production order in SAP - PP
Hello,
I am working in a custom code where one of the steps is to create production orders basically based on a product, workcentre and quantity for what I use 'COXT_BAPI_ORDER_CREATE' function module.
Now I have a new requirement which is to be able to change the input component quantity to a different value than the output (similar to what you can do in transaction CO01, and like what the on-line help claims you can do).
This new value should be on top of the ratio that is possible to specify in the BOM (i.e substract 5000 KG to what ever is in the input node after creation of the order).
The GUI allows for this so I assume there is a way to do it in custom code as well, but has not find the way to do it or function to call.
Can you advise on how to change the input quantity value without affecting other info of the order?
Thanks
Regards,
Update: found this other thread Change components and Routing of production order
Edited by: Mauricio Pego on May 3, 2011 6:00 PMHi,
The requirement can be met via BADi - MD_DISPLAY_ELEMENT (method - CHANGE_MDEZX_EXTRA).
Give the specification your technical person & the same can be done.
Regards,
Vivek -
Batch determination for a component material of a production order.
I created a new production order type in SAP and I created a new production order from the new order type. When Iu2019m doing batch determination for a component material Iu2019m getting the error u201CBatch determination for 000000000002003610 without selection datau201D. I have to click [Selection criteria] and manually assign the selection criteria for the batch class.
This is working properly for existing production orders and system automatically picking up the selection criteria.
Is there any place in configuration to assign new production order type to batch selection criteria or how can I overcome this.Hi,
Will you share steps you have completed so far for doing for Batch Determination?
It will help us to find the missing part..
- Check all the Batch Characteristic values are maintain in the Batches.If values are missing then also Determination will not take place.
- Check whether you have maintain Sort rule to Batch Determination strategy or not
Regards,
Dhaval -
Changr HU quantity generated via PRoduction order confirmation
Hi gurus,
I have created GRN of 112 quantity via production order confirmation.
My plant andstorage location is Handeling unit managed so with GRN handeling unit gets generated.
but packing had done for 1 quantity only.
now how to change this quantity? I tried HUCANC t code and gave the HU number but system is giving error that HU can not be cancelled. first cancelled material document
but GRN has made 112 quantity which is correct then how HU got packed with 1 only?
I stuck up pls helpwhen I am trying to change Hu in humo i am getting following error
Storage type 111 does not allow repacking - HUs cannot be changed
also getting following error if I am changing the quantity or emptying the Hu
Handling unit 10016000800120555 has status "cannot be changed" - Process cancelled
Edited by: vrunda on Jul 9, 2010 10:57 AM
If I tried to delete
Handling unit 10016000800120555 contains items that cannot be deleted
Edited by: vrunda on Jul 9, 2010 10:58 AM -
Error -10 while closing a Production Order with DI API
Hi,
I've been trying to close some production orders using this code:
Dim oProdOrder As SAPbobsCOM.ProductionOrders
Try
oProdOrder = Me.Company.GetBusinessObject(SAPbobsCOM.BoObjectTypes.oProductionOrders)
If oProdOrder.GetByKey(intDocEntry) Then
oProdOrder.ProductionOrderStatus = SAPbobsCOM.BoProductionOrderStatusEnum.boposClosed
If oProdOrder.Update <> 0 Then
Me.Company.GetLastError(intError, sErrMsg)
If (0 <> intError) Then
sErrorMsg = sErrorMsg & "Production Order Close Error: " & CStr(intError) & "," & sErrMsg & _
". DocEntry: " & oProdOrder.ProductionOrderOriginEntry & vbCrLf
End If
End If
End If
...But I keep getting the same error every time I try: -10,Date out of reference date range, '_SYS00000005340'
The error doesn't show when I close the Order with BO's Form. And I've checked the exchange rate for the posting and due date of the document (and also for my current date) and there seems to be no problem with it.
I'm currently working with SAP BO 2004A PL 45.
Anybody has a suggestion? a workaround?
I'll appreciate any help you can give me.
Thanks in advance...
AlfredoAlfredo,
just in case,
what is the previous state of the production order (planned, released,...)?
before you try to close the order, update the status to released:
If oProdOrder.GetByKey(newID) Then
'Cambio di stato dell'ordine da 'Planned' a 'Released'
oProdOrder.ProductionOrderStatus = boposReleased
oProdOrder.Update
I found this code in a DI API application written for 2004A. It was commented out so I suspect it didn't work.
'Chiusura dell 'ordine
'SelProductionOrder.ProductionOrderStatus = boposClosed
'ret = SelProductionOrder.Update
'If ret <> 0 Then
' sboCompany.GetLastError nErr, errMsg
' MsgBox "Errore " & nErr & " - " & errMsg
'End If
Hope this helps -
Error in scheduling parameters for production orders
Hi Guys,
Greeting for the day u2026u2026u2026.
I am trying to create production orders creation for own order type ex MM01, but I am getting error message as u201C scheduling parameters are not defined for the order type u201C even though I have maintained following parameters as below,
Production scheduler -
xxxxx,
Detailed scheduling -
check box of scheduling ticked,
Rough cut scheduling --- scheduling id u201301, scheduling and generate capa requi,, boxes ticked,
Adjust scheduling -- requi to operation date,
Scheduling control for detailed scheduling ---backwards and check box of auto scheduling ticked
Operation segment ---setup,
All operation in order will be reduce
Do not reduce,
Could any one light on this issue,
Thanks in advance,
MohanHi,
This error will come if you have not maintained Define scheduling parameters for production orders.
Check this order type whether linked with respective plant in OPU3.*And give production scheduler * mark ie, all.*
And in Define production scheduling profile - OPKP, link your order type in the page below.
In material master work scheduling view, input production sch profile or prod scheduler.
Regards,
Dharma -
Error during Goods Receipt for Production Order
Hi All,
When using MIGO to post Goods Receipt for a Production Order, I got a customize message saying that the posting is only available between 2010.08.25 to 2010.08.27. I have checked in Business Add-in using SE19 but there are no implementation present. I know that in Logistic Verification MIRO there is a transaction OMRM to set messages. I would like to ask is there anything similar for MIGO.
Or is there any other place in Configuration which allows me to add these Customize message.
Thanks.
Edited by: jamison2004 jordan2004 on Jul 9, 2010 9:09 AMHello Jiaul,
Sorry I may have mislead you. The actual error message is "Goods Receipt for Production Order XXXX can only be made on 2010.08.25 to 2010.08.27". These two dates are the Start Date and FInish Date for the Production Order in CO03,
The Basic Start Date for the current Production Order is 2010.08.25
The Basic Finish Date for the current Production Order is 2010.08.27
I think what it means is that you can only Post Goods Receipt for the Production Order only after the Basic Start Date of the Production Order. Do you know where I can find the configuration for this message?
Thanks -
Error during variance calculation for production order "NO cost estimate "
hi all,
I'm gettin this error message while trying to calculate the variance for a production order. error is "No cost estimate for material xxxx for 01.10.2008.
when i look at material xxx in MM02, under cost estimate for current period there is a value but nothing for previous period. So i'm guessing the the Cost estimate was not run of this material? am i correct here?
Now if i try to run cost estimate for material for the missing periods using CK11N, i get an error "cannot save for past period"
Could some one tell me how can i get a prior year estimate into the material master?
I tried CK40N and CKN1 but just cant get it to work...
Thanks heapsHi Tom
unfortunately there is no easy way to get a product cost estimate for a past date. One of the reasons for this would be inconsistant product valuation.
You could in theory create a cost estimate in a current date and use an ABAP or manually adjust the valid from and to dates directly in the tables (e.g. KEKO). To do this in a production environment would be restrictive off course.
The standard cost estimate is the basis for the target costs so as an alternative you could look to change the configuration of the target cost version in OKV6 to either of the following:
- Plan Cost/Preliminary Costing (that is the plan calc done on your production order)
- Alternative Material Cost Estimate (one that is not necessarily a product costing that is set for marking and release).
I hope this is of some help.
Elaine -
Error in Cogi after cancelling production order- Urgent
Hi Experts,
Its me again.
I would liek to seek your help regarding this problem I have.
Below is the process done:
1) Create production order
2).CO11N : producing qty in quality inspection status (Stocks received in QI status)
3) QA32 : accepting inspection lot ( thus the stock will be moved to "unrestricted")
Due to some errors discovered, prod order needs to be cancelled
4) CO13 : Cancel production => mvt 102 will fall into the cogi with error message "Deficit of BA Stck in qual.insp ... etc"
Could you please help me what to do to solve this error. pleaseHi ,
If QM is active , you cannot use 322 movement directly.
For this you need to activate 08 insp type in MM insp set up.
After that , you can bring the matl back into Quality using 322 movement.
Dont forget to deactivate the 08 insp type , once your work is over.
Hope this will helps you.
Regards
K.M.Arun
Maybe you are looking for
-
I have a 2g iPod Touch. I verified that I coudl connect via wifi from home and from a public wifi location before leaving on a trip to UK. However once I left I could never get net access on nay public or pasword wifi spot. I could get connected acco
-
i ran the diagnostic test and got this result.please help me out friends Microsoft Windows 7 Ultimate Edition (Build 7600) TOSHIBA ÿÿÿÿÿÿÿÿÿÿÿÿÿÿÿÿÿÿÿÿÿÿÿÿÿÿÿÿÿÿÿÿ iTunes 10.6.1.7 QuickTime 7.7.1 FairPlay 1.14.37 Apple Application Support 2.1.7 iPod
-
Windows update recognises msi n9600gt as nvidia 9600 gt
Hi all, I had my MSI N9600GT-T2D512-OC graphics card for many years. But recently on shifting to windows 7 64 bit computer, the windows shows my card in the device manager as nvidia 9600gt. Is it normal? And the MSI website has its drivers latest by
-
SUS-MM and ECC 6.0 quotations
Hello there, I'm using ECC 6.0 with SUS-MM (SRM 5.0 with SRM server 5.5). Did anyone implement the transfer of quotations from ECC 6.0 to SUS-MM. If yes, where would I find any config guide/implementation hints? Cheers, Franz
-
Additional Tab in Billing Transaction
Hi, I have a requirement of adding an additional tab in the billing transaction VF01 / 02 / 03. Please can you help me suggesting any BADI or EXIT avaialable. I found BADI_SD_TAB_CUST_H and it is for internal use only. Thanks in advance.