Hi
What all settings ve to be done in order to capture excise for a asset material. The client is not maintaining material code for assets. Till now they are creating PO against account assignment category ' assets' by giving material description.
How can this process be configured?
Then how J1ID, FV11 etc can be maintained?
pls share your views. Its urgent.
regards
B Shar

Hi,
It is always recommnded to maintain a dummy code based on tax structure wise against which you can change the text in PO, maintain j1id for that code & maintain FV11 conditions.
Earlier my client was also asking as per your requirement, but now he is happy with having only atx structure wise dummy codes (not more than 4.)
Without Material code, it will be very diff. for you to maintain excise as well as other CST / Vat conditions.
Rgds,
Vikas

Similar Messages

  • Stock transfer between plants - Material used is Asset material

    Hi All,
    We are using TAXINJ.
    We are doing stock transfer of an asset material from Plant A to Plant B.
    Proceedure followed as below:
    Supplying Plant -
    STO PO - ME21N
    Outbound Delivery -  VL10B
    PGI - VL02N
    Billing - VF01
    Invoice DOc - J1IIN
    Receiving Plant-
    Goods reciept - MIGO
    Capture excise thru - J1IEX
    When capturing excise ETT is GRPO and the subtransaction type used is 01
    We are getting the below message:
    "No Cenvat amount to be posted"
    "No Cenvat Amount to be reversed"
    We are not getting any message when we are not using subtransaction type 01, and we are able to post part2 entries.
    Pls suggest.
    Thanks in advance
    Pavan.

    Hi Deivakaniraja,
    Thank you for your suggestion.
    Still have a querry....
    The subtransaction type that is defined is not conventional.
    We define various subtransaction type like 01, 02, 03, 04, but there is no standard that 01 to be used only for subcontracting.
    I understand that IP is defined only for Import postings.
    Can you pls brief me.
    Thank You in advance.
    Regards
    Pavan

  • Excise for assets

    Hi
    For asset purchase we were not capturing excise invoice. Now we are planning to capture excise for assets. Assets are not having any material code only material short text is maintained in PO. Pls tell me the settings to be maintained for capturing and posting of excise on asset materials . We have to do from scratch. Here raw materials are made excisable.The complete master settings and CIN settings and FI integration has to be done for assets .
    Rewards assured
    regards
    B Shar

    Hi,
    Go to J1ID and maintain details as blanks material i.e.
    1.Blank material name + chapter ID combination.
    2.In Tax rate maintainence maintain  Blank chapter ID + validity and rate
    3.In Exceptional material maintain blank material + Blank Vendor combination.
    Do this in quality system and Test it.
    Reward if helpful,
    Regards,
    Chetan,

  • Capture Excise Invoice for material document created against a PGR

    Hi SD Gurus,
    We have a scenario of reverse subcontracting where we have to receive raw material from vendor, process it and then dispatch the finished goods to the vendor or the vendor's customer.
    For receiving the raw materials, i have created a document type which is copied from standard RE type. Against this order, a returns delivery is created which is then PGR-ed. With reference to the previous document, a service order is created in SD, which is then billed.
    But i am facing a problem when i tried to capture the incoming excise invoice for the raw materials. When i tried to capture the excise against the material document generated for PGR, the system is throwing a error, that it cannot capture the excise for this materia document type.
    I would be greatly obliged if anyone can throw some light on this. Do i need to maintain any special configuration for this? Why is SAP not allowing it? How this can be done?
    With Regards,
    Arindam Datta.

    Dear Arun R,
    You Kindly go to the following path and maintain your movement type over their and do the MIGO.I am very sure at the time ot migo excise tab will come for part-1 updation and subsequently you capture part-2 on J1IEX.
    SPRO->LG->Tax on Goods Movemet->India->Business Transactions->Incoming Excise Invoice->Specify which movement type involve excise Invoices.
    Hope this will help you out.
    Regards
    AKS

  • QM for asset material.

    Dear expert,
    How to do QM for asset material?.Actually we have a z report and accepted quantity is zero after QM.Is there any customization for it?
    Regards
    Tanmoy_mm

    HI
    For MM reports
    You can create one material code Non Valuated  for asset ,
    and use it in Purchase order , along with asset master, as it is Non Valuated so no accounting Entries are there.
    Vipin

  • Service PO for Asset material

    Hi
    I want to send an Asset material for service through service PO to a vendor for certain sort of service, after finishing the process at vendor , the same material should go to other plant in the same company but not to the issued plant. How can I do this.What is the business process to follow.
    Regards
    venkat
    Edited by: garapati on Mar 12, 2008 10:53 AM

    Hi,
    One thing you can do is, change delivery address at item level in PO.
    Hope I'm getting you right.
    Regards,
    Piyush

  • Materia transfer Procedure for asset  material within the plant

    Hi
    We need to set the process in SAP for asset material transfer from onle location to another within the plant and also send back defective one back to vendor.
    Please suggest the procedure to do the same SAP.
    Regards
    venkat
    Edited by: garapati on Feb 29, 2008 6:35 AM

    hi,
    clarify that material code is used or not.
    if material code is used then use 301 mov type.
    regards
    points if solved/helpful
    Edited by: RAMESH ARORA on Feb 29, 2008 12:04 PM

  • How to add  Spare material to Existing Asset Material.

    Hello  Gurus,
    I have a Problem that I made a Asset code of  One material, Later On one spare of that 
    Asset material is Damage. i replace it with  new one,
    But what i do  with new one spare?
    Wheater i make new Asset code for it. and if yes then How i link  the cost of it to Existing Asset code.
    For Example,
    I made a Asset code of  Computer  as
    Main Number         subnumber
    100000                   11
    Now i replace  a Hard disk of Computer to New one. so what I do with New Hard disk,
    Wheater I Make new Asset code for it And if yes then How i link the cost of it  to Existing Compuet asset code.
    I am eagerly waiting your reply.
    Regard,
    Riten Patel

    Hi,
    MMAM is the Transaction.
    Regards,
    Satish

  • Asset material stock

    Dear Gurus,
    The user has done gr for asset material having material master.When the flow of transactions is checked in mb51, it is showing stock. But in mmbe it is not showing any stock. GRN is done w.r.t to PO having account assignment'A".
    Pls suggest...

    For procuring Assets, you will have to maintain Asset master & material master both in your system. You place a PO for the material (which you define as your asset & want to capitalize) & maintain AAC as A- Asset. Then at the item level, you assign the asset code to the masterial. After you post the GRN, the debit entries are posted to the asset.
    Check Asset Stock at
    S_ALR_87011979 - by cost center
    S_ALR_87011980 - by location
    S_ALR_87011981 - by asset class
    S_ALR_87011982 - by plant
    S_ALR_87010137 - bar codes

  • Asset Material

    Hi all,
    For asset material,during GR account assignment tab,if we choose percentage indicator as 1.5 and partial invoice as calculate proportionally means,it effects Invoice quantity?
    Thnks & Regards
    SAP Beginner

    hi
    this is nothing but Share of the total quantity that you want to assign to this account assignment item.
    it is for the distribution of the quantity of items in different acct assignment
    suppose u have 1 item with 10 no
    here u can specify 50 % for acct assignmet 1 and 50 % for acct assignment 2
    so system will automatically calculate depreciation for the acct assinment (asset no )
    hope it clears
    regards
    kunal

  • Freight on asset material

    Hello.
    I created a PO that was an asset and at the time of creation the freight charge was not know. The invoice came and the freight was included in the amount of the material.
    I keyed in the freight amount in unplanned delivery, What I would like to do is for the freight line in BSEG to reference the asset material so the freight amount can be added to the material to be capitalized.
    Has anyone come accross this and how was this resolved? I saw some notes in OSS to create a subsequent line for this and it didnt help resolve my problem. Any assistance will be appreciated.
    Thanks

    Hi,
    You can check the frieght if planned during Purchase order generation, in the item level of the purchase order, Detailed break up will be avalable  in the conditions tab.
    Regards,
    Tushar Patankar

  • Excise for assets during transfer from one plant to another plant

    Hi SAP gurus,
    Pls note i have an issue during tranfer of asset from one plant to another.When i tranfer asset from one plant to another , in my suppling plant i create an Excise invoice where EXCISE RECOVERY ACCOUNT (debit) is getting hit instead of CENVAT PAYABLE ACCOUNT ( debit).
    What may be the issue ?
    And in same ways during inward of the goods - MIGO at the receiving plant CENVAT CLEARING ACCOUNT (credit)  gets hit.
    Now both Excise recovery account & cenvat clearing account are not gettiing nullified.
    The Process is as given below.Should i change any step or do i have to configure something
    **Master Data**
    1.     Material code (UNBW) should be available in both plants with Sales views -MM01                    
    2.     Stock should be available otherwise upload the stock with 501 movements (UNBW). No impact on FI u2013 MB1C
    3.     Excise details maintained in both plants for the Material code as Asset u2013 J1ID
    Business Process:
    1.     Transfer the Credit of UNBW asset to the current financial year if not updated u2013 J2I8.
    2.     Create STO PO - for UNBW Material Code with Item category U and Document type ZSTO (Mention the Price which is the base for Tax calculation. This needs to be decided by UCAM. Normally it is the  first initial actual Price at which the asset was procured ) u2013 ME21N
    3.     Do outbound delivery -  VL10B
    4.     Do Vl02n PGI ( stock is reduced and NO FI Document, stock in transit in Receiving Plant)
    5.     Do VF01 with ZSTO billing type. Verify the Price and Tax details( NO FI Doc)
    6.     Do J1iin with reference to Billing doc, Excise values flows from Billing document and Excise  invoice is created. Now FI Document will be created
    FI documents have the below entries:
    BED account credited u2013
    E Cess account credited u2013
    S Hecess   account creditedu2013
    Excise duty recovered  debited +
    7.     Do MIGO in receiving plant with reference to PO/Delivery note and by referencing the Excise Invoice and Date, Post it. Stock will be updated in receiving plant. NO FI document. Excise Entries appear in receiving plant
    On hold Account + (50% of total duty)
    BED  + (50% of BED)
    Ecess + (50% of Ecess
    SHEcess + (50% of SHEcess)
    Cenvat Clearing  credited u2013
    8.     Transfer Credit in the next financial year  -J2I8 ( refer this separate business  process
    document)
    Pls guide
    Nandu

    Hello Nandu,
    Please check the G/Ls assigned against CAGI and CAGR in "Specify Excise Accounts per Excise Transactions"  and "Specify G/Ls Accounts per Excise Transactions" configuration for Tax on Goods Movement > India.
    The combination should help you arrive at the right G/L accounts.

  • Excise for Asset

    Hi,
    While creating the purchase order we give the asset master only .in this case how to calcule the excise value based on the given tax code?. is there any possibilities without maintaing the material as asset in j1id?
    Regards,
    Renuga.A

    Hi,
    Without material code it is verymuch possible.
    If ur in TAXINN then u can maintai the Combination with Mataerial Group in Fv11.
    If ur in TAXINJ then in J1id in exception put the Vendor code & Leave the Material code blank .
    Biswajit

  • How to generate Excise invoice-rejected material

    Hi,
    We have taken Cenvat Credit on receipt of material. But after QC rejection, we reversed the Cenvat credit through J1IH. Now I want to create excise invoice for this rejection transaction. Please guide.
    Thanks in advance

    Reversing CENVAT throgh JV i.e. J1IH should be last option.
    Better way is
    1. MIGO- Return delivery-122
    2.J1IS- Excise invoice wrt 122 document
    3. J1IV- Print excise invoice.
    Regards,
    Piyush

  • How to create excise invoice without material document

    Hi,
    I want to create excise invoice for a subsequent credit note. I am agreed to give additional amount to my supplier for which i have not paid to him, now when i issue a subsequent credit note, how to create a excise invoice and do the excise entries without a material document.
    Please suggest a solution
    Regards,
    Ashish

    Go to T Code J1IH.
    Select Additional Excise. Replace the document number by the vendors excise invoice. Enter the excise duties in lower box and click on Determine GL accounts button to simulate and then post.