ExciseInvoice(J1IIN)raising wrt second Bill No(SamesSalesOrder forBothBills

Dear All,
I need your suggestion in a scenario which is as follows:
This is Make-To-Order scenario. In the Sales Flow both PS and SD Modules take some part.
The FLOW is Sales Order in VA01; Delivery creation in CNS0(PS); after doing CNS0 picking, packing and Goods Issue will be done through VL02N.
Billing will be done in VF01(Accounts Posting is done from this; This Bill was created with reference to Sales Order, since Billing Plan is there in the Sales Order). Then by going to J1IIN, Excise Invoice is raised with refrence to the Bill No that was generated in VF01.
The situation here is as follows.
The material that the Client Delivers is huge(1000 Ton).
That is why the Client is doing Partial Dispatches.(Material being huge
Now whenever they do the Dispatch(partial) they will raise the Invoice for the corresponding part value and post the Details into FI.(Say for Part 1 they will raise the Invoice. Here the invoice will contain part1 value only)
Now the problem here is that I was not able to raise the Excise Invoice for the Invoices later than the starting Invoice.
{Say, while Dispatching Part1 Invoice 101 has been raised.
For part2, Invoice 102 has been raised.}
Now I have raised Excise Invoice(J1IIN) for Part1 by reffering to Invoice 101.
BUT WHILE RAISING THE EXCISE INVOICE FOR PART2 by REFFERING to Invoice 102, system is giving the following error:
" MODVAT UTILISATION has already been done for Invoice 102 and Delivery No. HM001"
Here Delivery No. reffers to Order No.(The point to note here is both the Invoices were raised by reffering to same Sales Order No.).
So I need to know whether I can raise the Excise Invoice again for the second Invoice. Here I should be able to raise the Invoice for the second time also since the part2 Excise Duty value is not yet posted into CENVAT A/Cs.
Please give suggestions so that I can  do this process in a better way to solve this problem.
Regards,
Raj Kumar Reddy Poli.

Similar Messages

  • How to Create Excise Invoice (J1IIN) with order related billing document

    Dear Experts,
    Is it possible  to Create Excise Invoice (J1IIN) with order related billing document? How? please guide
    Regards
    BK GAIKWAD

    Sir,
    We have make the supplementary Invoice (Debit Note) as per below process
    1) Create sales order_VA01
    2) Create billing document_VF01_with reference to sales order
    3) Create Excise Invoice With J1IS (Other Movement) It is manually job & due to heavy work load (create 200 invoice  per day) it is not possible to do manually.
    Hence we want to create excise Invoice with J1IIN instead of J1IS, any alternative solution for that?
    Regards
    BK GAIKWAD

  • How to raise an Intercompany Billing

    Dear All,
    Can anybody help me with the settings required for configuring the intercompany billing. I have extensively searched the Forum but could only able to get the process for the settings required for intercompany sales, which is working fine.
    All that, I want is to know how the intercompany billing is raised.
    a) Settings required for the Intercompany billing that needs to be raised
    b) What will be the Item category in case of the supplying plant raising an intercompany invoice to the selling sales organisation
    c) Is there any settings required for copy control ?
    d) Is the Intercompany billing is a delivering relevant billing or order related billing, if so, then would like to know the settings required in the copy control (incase of order related billing or delivery related billing)
    Currently, moment I'm trying to raise an intercompany billing, system is throwing an error message, "Sales Organisation is not defined"
    Can anybody help me ?
    Rgds,
    Indra

    Hi Indra,
    Check with this link ... it will help you
    http://www.sap-basis-abap.com/sd/configuring-intercompany-billing.htm
    Regards,
    Seegal

  • Zero BED value when posted J1IIN excise invoice from billing document

    Hi Guys,
    I created VA01, VL01N and VF01. Bed value is showing in VF03 but when I created J1IIN from billing document, BED value is zero. I checked several places like below
    a) Logistics-General > Tax on Goods Movements > India > Account Determination > Specify Excise Accounts per Excise Transaction. Here ensure that for DLFC, necessary Account names are maintained.
    b) Similarly, in the next tab, Specify G/L Accounts per Excise Transaction, ensure that for that Excise Group, relevant G/L Accounts are assigned
    c) Finally, in Business Transaction tab, select Outgoing Excise Invoices where you need to ensure that you have assigned billing type to delivery type and also the default Excise Groups and Series Groups are maintained.
    I couldn't figure it out where the problem is. Please help me where to check and what should be done for this?
    Thanks,
    Manohar.

    I maintained excise defaults for TAXINN, I am maintaining A/R BED % which is coming in billing document but not in J1IIN. When I click on simulate it is giving a popup box saying 'No defaults could be proposed for Excise utilization' and click on continue then it is giving another message saying 'Excise modvat accounts not defined for GRPO transaction and E2 excise group'. Please help me what is it?
    Thanks,
    Manohar.

  • Create Excise invoice(J1IIN) document while creating billing document using bapi BAPI_BILLINGDOC_CREATEMULTIPLE

    Dear Experts,
    My scenario is:
    We have batch split scenario, where the parent line item of billing document has 0 quantity and its subsequent item (item with batch number) holds actual quantity data.
    When we create billing document using VF01 against delivery document, system creates billing document along with excise invoice document (J1IIN Document). And in excise document contain same number of line items that of billing document. Please see the below attachment: 
    Biiling document screen shot:
    While creating billing document, the J1IIN Document created automatically. Below is the screen-shot for the same.
    Now the issue is:
    When we create billing document using BAPI: BAPI_BILLINGDOC_CREATEMULTIPLE system creating only billing document and not creating excise invoice document.
    When we create excise document manually using J1IIN the zero quantity line items are excluded in excise invoice document.
    Please see the below screen-shot for the same; The z quantity line items are missing.
    We want excise document to be created while creating billing document using BAPI BAPI_BILLINGDOC_CREATEMULTIPLE. Or is there any other BAPI for the same purpose.
    Customization is also maintained for creating excise invoice document automatically.
    Regards,
    Rajesh Sadula.

    HI
      Pricing will be carried basing on the pricing
    procedure.
    Case1: Prices will be carried out automatically if
    necessary condition records are maintained for the
    condition type.
      For this you can go to Sales Order-> Item Conditions
    In the screen you can click on command button Analysis,
    which gives you the list of condition types associated
    to the pricing procedure. By clicking on the condition
    type you can know the action that has taken place.
    Case2: Manually forcing prices for Items.
      To do this, you have to populate ORDER_CONDITIONS_IN &
    ORDER_CONDITIONS_INX. Also note to identify the item
    numbers, you manually pass the item number for each item
    in the sales order, use the same item number for
    populating conditions.
      Parameters required:
    ORDER_CONDITIONS_IN:
      ITM_NUMBER, COND_TYPE, COND_VALUE, CURRENCY
    ORDER_CONDITIONS_INX:
      ITM_NUMBER, COND_TYPE, UPDATEFLAG, COND_VALUE,CURRENCY.
       Hope the above info helps you. Do revert back if you
    need more info.
    Kind Regards
    Eswar

  • Per second billing

    Are we charged per second or per minute Eg if I talk for 10 seconds am i charged for the whole minute

    Skype is charging per minute. Every minute you start within a call you will be charged for.
    Follow the latest Skype Community News
    ↓ Did my reply answer your question? Accept it as a solution to help others, Thanks. ↓

  • Thru project raise Sales order for billing ?

    hi
    I am looking for any option available raising Sales order thru Project ie., CJ20N or CJ02.
    Currently we are creating customer project in Project System thru CJ01 with Project definitino along with WBS Elements. Create Network and assign WBS element, in network we have components & services procured.
    After project commissioned, we have to raise sales order/billing document for components & services, presently we raising thru VA01 and raise SO for materials & services, after SO, we raise billing documents and submit to customer.
    I have tried using DIP and it is not suiting for our requirement, now i am looking for option raise thru CJ02 project or thru CN22 thru Network.
    Pl help
    thanx in advance
    srihari

    Hi Srihari,
    You have to raise a Debit Memo Request (DMR, which is again a type of Sales order only). But for this also, you need the master Sales Order to be created separately.
    You create a Sales Order with the line item being the concept of the Project (for example, Power Plant Construction)
    Maintain the WBSE account assignment.
    Using RRB, you can generate a Debit Memo Request (this is a subsequent document to the Master Sales Order but also is a type of sales order)
    then in SD, with reference to this DMR, Billing Document will be created & simultaneous revenue updation on the Project can be done.
    regards

  • Return sales order wrt Billing doc.

    Dear Friends,
    I have maintained copy control for VTFA.
    I have Billing doc for 100 Qty.
    When i create sales order wrt this billing document, i cauld restrict Order qty to max 100 qty with help of V4 : 229 message to E (setting  in SPRO: define variable message).
    But next time system still allows the Return sales order wrt same billing document for Qty. max 100 as in above case. Thus i could create as many return SO wrt Billing document.
    I want system to store the cumulative return SO qty vis a vis Billing document Qty.
    Eg. Billing qty 100.
    Return SO 1 for 50 Qty.
    Return SO 2 for 30 Qty.
    Return SO 3 for 20 Qty.
    Return SO 4 Not allowed.
    Kindly advise.
    Regards,
    Rajesh

    Hi,
    This is normal SAP behavior which will allow you to enter more quantity than that in the original outgoing invoice. This will not be controlled thru any config.
    For this you need to write a exit with the help of your ABAPer.
    Goto  SE38, enter MV45AFZZ
    when you see the code you will find user exit  "USEREXIT_SAVE_DOCUMENT".
    In this exit you need to write a code which compares the order entered quantity with the quantity from the invoice.
    When you try to save such document, system will not allow giving an error. This will surely work.
    Hope this helps you.
    Regards,
    Dhananjay

  • Excise Invoice created twice for same billing document.

    Hi All
    Excise Invoice ( J1IIN ) has been created twice for same billing document in 1 or 2 cases.
    How is this possible,if possible what is the config  to restrict the same.
    Thanks in advance
    Samson

    I dont think its possible to EI twice wrt: single billing document.
    EI created wrt: Invoice which is created wrt: Delivery document. Then there will be only one material document with movement type 601. Through which qty will get updated in Rg1 register.
    This document once utilized, cant used again.
    re-check billing document, which billing document you are using & their settings in IMG.
    Regards,
    Reazuddin MD

  • Several Return orders with Ref. to one MTO Billing Document.

    Hi,
    I am doing RE with ref. to MTO Billing Document but i am able to issue "N" number of credit memo's with ref. to same MTO.
    Please tell me the Controll, that stops raising the second RE order with ref. to same MTO.
    I checked copy controls completion rule in Item catagory but still the problem not solved.
    Waiting for reply
    Veera.

    Dear Veera,
        The issue is related to the copy control settings only , so you go to VTAF transaction then go in to the item details of your return order type and MTO Billing document type.
    Here you can find the field positive/negative quantity you maintain that as '-' negative.
    Now you try
    I hope it will help you
    Regards,
    Murali.

  • Supplementary billing for Depot. (India business)

    Hi All,
    We have the below scenario to raise a Supplementary billing for India Business for Manufacturing plant. For this process we need to raise a Supplementary billing (Credit/Debit memo) for the price revision.
    Our Current process for suppl. from the manufactuing plant(manula process to rasie Cr/Dr note):
    1. Sales order with for a particular matl, qty. The price diff. ( between original price and revised one) rate is entered manully in the SO. We eneter the basic Excise duty, HE Cess and SHE cess also.
    2. No delivery here (since no goods movement). Then commercial billing and with reference to this Excise Invoice (J1IIN) will be generated and will be sent to the customer.
    In this way, we are looking for Depot. process also. But the thing is we can able to raise an Excise inv. from Depot. (J1IJ) only based on Delivery and Matl document number. So here we are failing do to the same.
    Can anybody please suggest on this issue to resolve then will be highly appreciated.
    Thanks.
    Vijay

    Hi,
    Our Current process for suppl. from the manufactuing plant(manula process to rasie Cr/Dr note):
    1. Sales order with for a particular matl, qty. The price diff. ( between original price and revised one) rate is entered manully in the SO. We eneter the basic Excise duty, HE Cess and SHE cess also.
    2. No delivery here (since no goods movement). Then commercial billing and with reference to this Excise Invoice (J1IIN) will be generated and will be sent to the customer.
    Can we create an Excise Invoice using J1IIN, when there is no delivery document, as you have mentioned? If yes, kindly let me know the process.
    Thanks and regards,
    Amitesh Anand

  • Issue of Excise Duties in Foreign Currency in J1IIN

    Dear All,
    As one of my user has created Export Excise Invoice on 31st of May.  Unfortunately Exchange Rate was not maintained by him for currency Euro in OB08 and While creating the Excise Invoice all the duties came in EURO but the document currency is INR. Please find below screen shot.
    Now my query is, Is it possible to update/convert these Excise Duty Values in INR without cancelling this document. Because while creating ARE1 all the data are coming in EUR only.
    Regards:
    Abhishek

    Hi,
        Could you please replicate the scenario in Dev / QAS and check whether the excise duties are calculated correctly in J1IIN when the the billing currency is EUR, and OB08 is correctly maintained.
        Repeat the same scenario without maintaining the currency conversion factor in OB08 and compare the excise invoices. Revert back with the results.
        I guess that the issue is not because OB08 was not maintained. Found a similar issue mentioned in the notes:  957377 - Excise base appears in foreign currency in J1IIN for TAXINN  and  936007 - Excise base not converted to INR in J1IIN/J1II for exports You may check the notes if its applicable for your SAP release.
    Regards,
    AKPT

  • Excise Invoice- Based on Billing Plan

    Dear All,
    Here in my client's place, we have a requirement like,
    For a project-XYZ we create one sales order with materials A,B & C.
    For this sales order we maintain billing plan 50% = X1 Rupees ,
                                                                    25% = X2 Rupees ,
                                                              and 25% = X3 Rupees.
    When project is finished 50% we create billing with X1 amount with reference of sales order and then we create excise invoice based on this billing document (NO delivery) and send it with material.
    And for second billing for X2 amount SAP is not allowing to create excise invoice and throws message like modvat utilization has been done already.
    Kindly suggest how to proceed and how to create excise invoice for remaining two amounts.
    Thanks & Regards

    Hi ,
    Thanks for your responce...
    Is there any transaction code for removing the billing block automatically in the sales order and how can i indentify the date category as per billing plan..
    Thank you very much..
    Thanks in advance.
    Regards,
    KV

  • Contract and billing question.

    I'm leaving to Basic Combat Training in mid September and I'm getting a phone beforehand so I can keep contact with people when they start allowing phone time, and so I can keep contact through Advanced Individual Training. I don't have a job so I've been saving money for awhile now.
    I'm getting an iPhone 5, so up front payment to start a contract is $199.99. The bill will be $110 monthly with the plan I've chosen. Now, I have enough money for the up front payment and the first bill, so I'm wondering, if I start my contract at the start of September 2013, when will my first and second bill be due?
    I'll start getting paychecks around the end of September/start of October and since I have enough money for the upfront payment, and the first bill, would the first bill be due at the end of September, and the next at the end of October? If this was the case, I'd be fine because my bank account would have my BCT pay already going into it so by the time the 2nd bill arrived I would already have more than enough money in my account from training to pay for it thereon out. However if the billing cycle is different (or if I have to pay the upfront cost + the first bill at the same time upon opening the account) then I'd need to put the billing on someone elses card then pay them back after my training. 
    Thanks, answers will help a ton.

    Hi voidn0ise,
    These forums are dedicated to Residential products and services offered by Verizon.
    For help on Verizon Wireless issues, please post your topic on the Verizon Wireless community.
    Thank you.

  • Two Separate Billing Documents created in the collec Billing through VF04

    Dear  Forum Friends,
    I am doing the collective Billing through VF04 for two deliveries (80015032 and 80015034) of the same day.
    When I am finding in VF05 it has been observed that Two Billing documents instead of one billing document have been created against the two deliveries.
    Could anybody guide where the problem is? I guess the problem is in Copy control but exactly what field is to be changed please guide me. I tried with the Data routine “003” and “007” but nothing happened.
    Regards,
    Jans

    Dear Jans
    If data from the related reference documents differs in the header fields of the billing document, the system will automatically split the invoice.  For example,  header datas like Payment Terms, Payer, Shipping Conditions etc differs, there will be invoice split.
    To find out the reason for split analysis, proceed as follows:
    Enter the number of the first billing document that you wish to compare.
    Choose Environment --> Split analysis.
    Enter the number of the second billing document which you wish to compare to the first in the dialog box.
    Enter the billing document number and choose Continue.
    The system displays the Billing document split analysis log. It is made up of three parts. The first shows the header partners and header fields which are different in the two documents while the second and third columns show the respective values for these fields.
    This provides you with a clear overview of which fields have differing contents, the information available, and why there was an invoice split.
    Thanks
    G. Lakshmipathi

Maybe you are looking for

  • Export notes in pdf

    How do I export the notes (yellow notes sidebar ) with the document while exporting to PDF? Is it even possible?

  • Reciept for production

    Hi All When we Release the Production Order from the Planned Stage . 1) Can we able to make Receipt for Production Order without Issue for Production with the issue Method Kept as Manual. If yes then what is the concept behind it, to do Receipt befor

  • What is going on?-iPod sync  error

    I keep getting this error: http://img487.imageshack.us/my.php?image=picture3sb2.png I've restored the ipod several times... This last time, I just updated my iPod by playlists only and went through all my playlists one by one...After that, I tried do

  • Removing JAVA add in

    Does anyone know the steps to do this. I know from a high level the pieces that are integrated such as Start profile for ABAP, DB schema , and os directories. But  a clear procedure is what i am looking for. One other question. How can you just disab

  • Test and Demo Systems (DPA)