Finding actual costs of hours booked in CAT2

Hello experts,
I am trying to locate the actual costs per hour that will be posted when a person enters time on a timesheet in CATS with a known activity type and cost centre.
I believe the formula in the work centre calculates 'planned' costs - but I am looking to find the actual costs from a costing sheet.
I hope this is simple enough
Many thanks

Hi,
Activity hourly rates, you can see in COST table. As for CATS cost, you can see against relevant cost object. For example, if you charged your time against a newtork activity then you can see this actual cost in COSS table against the network activity object number.
Regards
Sreekanth

Similar Messages

  • Function Module to Find Actual costs and Total Cost Commitments

    Hi PS Experts ,
    Please let me know if there  is any function module to  find Acutal costs and Total cost commitments by passing WBS element as Input .
    Regards,
    Karan

    Hi Karan,
    I think for actual cost - there is definately one FM availbale. Try to find it out.
    Just ensure - if you are using Network Activity then you may have to pass NWA OBJNR into this FM to get actual cost. As some entry posting happens against NWA like Timesheet. Hope it will give you some idea to get rid on your issue.

  • Actual Cost Machine hours is zero (After confirmation)

    Dear Guru,
    We are implementing PP module and product costing. We enter the budget with activity type in KP06 & KP26. After confirmation, the actual cost in machine hours is zero but not in electricity or steam. Why the actual cost is zero in activity type machine (we enter the actual qty machine hours) ...
    May you assist me to solve this issue
    Thanks
    Maju S

    Dear Umapathi G & Shaubhik
    Thanks for your replay.I have checked the Control key is marked for costing and the cost center is assigned correctly and we have executed the KPSI before and I found the fixed price for Machine hours in tcode KSBT and cost center is not locked for posting secondary CE
    For additional information, we have 3 activity type, Machine hour, Electricity and steam. The actual cost for electricity and steam are not problem, only for actual cost activity machine is zero. The issue only for activity type for machine.
    May you have me to give the other solution to be checked
    Thanks for your replay and I am really appreciate it
    Maju S

  • Service Order Actual costs and revenue

    Hi,
    Can you please let me know how to find actual costs and revenue related to service orders?
    what tables to go to?
    We are planning on going back to a service order from the billing document and get the actual labor costs.
    Thanks,
    MS

    Hi Mahesh,
    Thank you very much for that quick response.
    EKKO is for purchasing documents. Can you please let me know how to use it for my service order?
    Thanks,
    Maulik Shah

  • Function Module to find Planned Costs and Actual Costs against WBS element

    Dear All,
    We have a requirement where we need to find out the Planned Costs and Actual Costs booked against a WBS element, in a year. The costs can be against all the plan versions or on individual plan version.
    Are there any function modules to retrieve this value?
    Thanks for the help.
    Warm Regards,
    Judith

    Hi,
    The easiest way would be to get the OBJNR for all WBS elements from PRPS and look up RPSCO and summarize for Value type (RPSCO-WRTTP) 1 for planned cost and 4 for Actual cost.
    Please let me know if this helps.
    jibat

  • CATS INTEGRATION WITH PP AND PM MODULE ( TO FIND ACTUAL MANPOWER COSTING THROUGH ACTIVITY TYPE)

    Hi Experts,
    We have a scenario like, Client wants to track the actual manpower costing through activity type ( Ex: How much hours an employee worked on a particular work center to produce an “X” product, So that his actual cost should be loaded on that product.
    We have employee ( 1. Staff 2. Worker 3. Contract labor employee and apprentice from third party roll and staff and worker we plan to go with negative time management and for contract labor and apprentice will go with through cats.
    Since we are not going to run the payroll for contract labor employee and apprentice, we just maintaining the employee data as a group ( Ex: Group A,B,C etc.. Each group consists 20 or 30 employees, According to system each group as one employee and according to us each group consists as 20 or 30 employee.
    The Activity type as well cost center will be created by Co module, the same will be assigned in info type 0315, but still i want more input from experts on the same, since i am new to cross application time sheet configuration, could any one help me out to find the actual manpower costing in a better way.
    Regards,
    Prem

    Hi Experts,
    Can any one please reply on the same.
    How to arrive the exact manpower costing through activity type ?..
    Regards,
    Prem

  • In which table we can find service entry sheet no to find the actual cost

    In which table we can find service entry sheet no to find the actual cost of External service
    Service code,     Service description      Quantity     UOM,     Vendor,     Cost

    Hi,
    Total Actual Material Cost - Sum up the total cost ENWRT against the AUFNR in the table RESB and display in the report
    Total Actual External Service Cost - Provide the field AUFNR in the table EKKN and get the Purchasing document field EBELN & apply this field data in table EKPO get field NETPR and display in the out put
    For link between operation & order - Selection criterion is the order number (Field AUFNR table AUFK). The content of field AUFPL has to be used afterwards as selection criterion in the table AFVC. The selection field in this table is again AUFPL and display the field LTXA1..
    Kuber

  • (project system) do book confirmation amount as a actual cost

    HI all
    it is possible in project system when i confirm my activity then it does not book actual cost to my network activity.
    because i need to show this confirm amount as  only for information purpose....my clint requirement.
    thanks

    with the material ledger, actual costs are not only used to value the stock at the period end. You also have the possibility to revalue the cost of goods sold with the actual costs of production for the period.
    The system takes initial stock, initial value, production of the period, actual costs of production of the period to calculate "cumulative stock of the period" and "cumulative value". The cumulative value per unit is then applied to all consumption of the period (goods sold) and the final stock.
    Your only alternative to the material ledger would be to value yout finished goods at V-price, not S-price. The problem with this is that you don't necessarily have all the information about actual costs at the moment your finished product enters stock. For example actual activity prices can only be reasonably calculated per period.
    Whether V-price is an option depends on the details of your scenario.
    To me material ledger is the right way to value stocks and COGS at actual cost.

  • How to find the Actual Cost & NR of a material

    Hi experts,
      Can anybody tell me the table from which I can come to know the actual cost of the material and also the actual NR.
    Thanks in advance.

    Hi Shakeel,
    Go to Se16n transaction
    and select EKBE table, there u  will find so many field ranges, restrict it as u like
    u can get it there
    regards,
    subbu

  • Tables & Table relationship to find ACTUAL & PLANNED COST for ACTIVITY ELEM

    Hi Guys,
    I have to create a report for Project, WBS, Network, Activity and Activity Element to show :
    Reporting period: March 1,2007 to March 25, 2007
    Planned cost   ( (from March 1, 2007 to March 26, 2007)
    Current reporting period   (from March 1, 2007 to March 26, 2007)
    YTD Actual Cost   (from Jan 1, 2007 to March 26, 2007)
    Kindly let me know the table to get the ACTUAL COSTS and PLANNED COST with relationships.

    Hi,
    Refer to the BLOG
    SAP Project System - A ready Reference ( Part 2 )
    Hope it will help full
    Regards,

  • When the labor cost of timesheet  go to the Actual Cost Line Items report ?

    Hi ,
    when the user book the time in timesheet on Network / Activity, when this record reflect the actual cost of project ?
    After Timesheet Approve via CATS_APPR_LITE
    Or after Confirmation
    Or after transfer via CATA
    Who can tell me the relationship among these three steps ?
    Thanks and Regards
    Shubin

    Hi,
    The flow is like this ( if u r using timesheets for confirmation):
    CAT2 : Timesheet: Enter Times : User enters the time.
    CATS_APPR_LITE  : Approval of timesheet
    CAT5  : Transfer to Projects.
    This will post cost to Projects.
    Another way of getting the Actual cost is Confirmation using CN25 or CN29.
    Regards,

  • Early confirmation of activity - Problem with actual cost updating

    Hi Guys...
    I have trying to find out solution with trail and error basis but.....
    The issue is :
    Network activity  - Planned duration 100hrs
    periodic confirmation taken place .... no problem... actual cost also updated accordinly,
    at one point of time, realised that activity is completed with 70hrs effort only.
    then I have updated 100% completion.
    what is the twist here is:
    though I have completed 100% of work with 70% of actual hours,  however, system display actual costs equals to 100hrs.
    I can not reduce planned hours equal to actual hours. at the same, I would like to see my activitiy completed with 70 hrs and actual cost equal to 70hrs of effort only.
    is there any enhancement there so that we can have both display planned 100 hrs and actual as 70 hrs.
    and costs also.
    Looking forward to hear from the gurus and thanks in advance
    Shal award points for appropriate answer.
    Regards,
    PSR

    Hi,
    One probable solution would be using User status which will block additional confirmations. At the point when you know that work is completed within planned hours, set this user status so that no more confirmation is possible, at th same time user will come to know that activity is completed.
    Hope this helps.
    Regards

  • Break Up of Actual Costs in a report for list of orders

    Hi All,
    SAP standard reports displays only the total planned & total actual costs.
    Is there any standard report available which can display break up of planned & actual costs along with total costs, for list of orders (e.g: time, material and external resources consumption).
    Thanks in advance
    JK

    hi
    you can find the material cost,external service etc in the standard cost report itself select the change layout and select the items you want to display ,you can get the result
    regards
    thyagarajan

  • PS - Report on Planned v/s actual cost of the project

    Hi,
    I have a client requirement on the above subject. In Report S_ALR_87013542, Under actual cost the system is taking both the Revenue and Actual cost booked on the project. Is there any other report wherein the system shows only the actual cost booked on the project so that planned V/s Actual can be compared.
    Rgds,
    Prasad

    Hi,
    You can also refer the report S_ALR_87013543 - Actual/Plan/Variance Absolute/Variance %. This will give the reports based on cost elements. Morever plan cost Vs actual cost can be obtained from Project Infosystem report (CN41/ CNS41).
    In fact the report S_ALR_87013533 is a hiecherachical report for plan & actual cost of project.
    If the system is calculating wrongly both revenue & actual cost under actual then you need to check Cost elements asignments & value category details.
    Hope this will help you.
    Regards,
    Rakesh Pradhan

  • Report to show hours booked against a project

    Hi all,
    Does anyone know if there is there a report that will show the number of hours booked for labour against a project and that also shows a breakdown of the labour costs?
    Many thanks.

    CJI3 - Line Item report can show you those values provided you include the fields Quantity, Personnel Number etc., in the layout.
    Regards
    Sreenivas

Maybe you are looking for