Hi all,
I need a FM to change the task list status.
Tcode IA06.. I have got fm to get the status of task list...CP_EX_PLAN_READ..but not able to fine one to change/.
(Given: Group, Group counter and profile..after this scrrn another screen comes...click the header atb to set the task list status)
can anyone help me?
Regards,
Check this FM - CP_EX_PLAN_READ.
This gives u all the details .
CALL FUNCTION 'CP_EX_PLAN_READ'
EXPORTING
plnty_imp = t_mapl-plnty
plnnr_imp = t_mapl-plnnr
plnal_imp = t_mapl-plnal
sttag_imp = t_mapl-aedat
TABLES
plko_exp = t_plko1
plpo_exp = t_plpo1
plmz_exp = t_plmz1
EXCEPTIONS
not_found = 1
plnal_initial = 2
OTHERS = 3.
Edited by: Raj on May 27, 2008 10:28 PM
Similar Messages
-
Hi freinds,
How to change task list in inspection lot manually??
I have maintained manual assignment of task list in material master.
Regards,
Amit Shirsath.Hi Amit,
There are two ways to incorporate your requirement: -
1. With having singable tasklist( With singable Tasklist counter)
Assume you have a Material "M"
Customer: - C1 And C2
Tasklist Group:- ABC
Counter: - 01
Go to QP02. Select the The Tasklist group counter line item, click on "Material Assignment" And assign the Material and both the customer C1 and C2 here to the material.
(Material will be assigned two times)
Now go to characteristics overview screen. Select the MIC and click on "Dependant Characteristic". Where if you have different limits (5 to 10 for C1 and 5 to 15 for C2), you can assign it the relevant line item representing the customer.
2. Two different group counters:-
Assume you have a Material "M"
Customer: - C1 And C2
Tasklist Group:- ABC
Counter: - 01 for C1
Counter: - 02 for C2
Then it is very simple boss! Go to material assignment and assign the materials along with the Customers over there.
update us to help you more, reward points to help you better!
Regards,
Shyamal -
Compensation Workbench (CWB) Access Changes (Task List)
I have a requirement to change the access levels for managers during the enrollment period for CWB plans.
For Example : The Letters task should be hidden at the start of the period and made available somewhere towards the end of it.
I am able to see that the task access can be changed from Plan Administration screens but they are not getting reflected in the Manager tasklists. I have even tried running the CWB Refresh process (Though I couldn't see how it would update the access levels) without much luck.
Any pointers will be appreciated.After some digging found the following.
If a task is set to read-only or hidden at the time of participation process, its status cannot be changed after participation. So, the way to control this from plan administration form is to set all tasks to full access, run participation and then update the tasks to reflect the required access levels. -
Change Request Management "There is no task list for this project"
Hello!
I would like to use the functionality of CharM in SOLMAN 4.0.
When I enter the Tcode /n/tmwflow/proj I receive the waring/error "There is no task list for this project" (/TMWFLOW/TRACK_N114)
If I create my own task list via Task list --> create
I get the warning "You cannot change task lists in the SAP namespace"
What are the steps to define task list for my project?
Do I need to configure SPRO ... --> Extended Configuration --> Schedule Manager?
The second warning I get: "NO CTS projects created yet" or
"The Solution Manager project does not have an active CTS project yet".
How can these warnings/errors be corrected?
Thank you very much!
regardsHi,
Pls click the check button(next to activate button)
see the SLG1 log generated remove the errors shown in red.
One it is done u press the refresh button & thn u cn create the task list
chk
https://websmp202.sap-ag.de/~sapdownload/011000358700000657692007E/ECTS_CHARM_SP12.PDF
/people/dolores.correa/blog/2008/07/26/first-steps-to-work-with-change-request-management-scenario
http://help.sap.com/saphelp_sm32/helpdata/en/0c/5b2160f6fa4b83a3674a210b1cdeb0/content.htm
Regards
Prakhar -
Creation of new task list in CharM not possible
Hello!
I am using SOLMAN 4.0 (SP13 with the newest SP) and the problem to create the task list in Tcode: SOLAR_PROJECT_ADMIN --> System Landscape --> Change requests --"Create task list".
The following error occurs:
The project is not released. Hence cycle can not be created.
/TMWFLOW/CONFIG_UI017
How to solve this problem?
Any helpful information will be appreciated.
Thank you very much!
regards
ThomHi!
Yes, the problem was wrong configuration of systems.
Please try the following:
- your systems in system landscape have the right roles
- your TMS configuration is mandant dependent
- you have delivery as well consolidation routes
You can also run the check for the consistency...
You can write back, if the problem still exist...
regards
Thom -
In inspection lot..task list does not fetch
Hi QM Guru..
when i do UD for fish material. with QA32....in QA32 showing inspection lot no..but when i select line item of inspection lot and click on inspection lot..one window open..when i go inspection specification for task list..when i click on task list....show the massage....
but i all ready created inspection plan from QP01...i have over ther MIC and sampling procedure also
No inspection plan could be found
Message no. QA278
Diagnosis
A task list could not be found for the selection criteria. The inspection setup for this material in the quality management view of the material master defines an inspection with a task list.
System Response
Sample calculation and inspection lot release are not possible.
Procedure
Check the:
Selection criteria
Material/task list assignment
Task list status
Task list usage
Task list usages i have taken 5 for GR
status 4 general release
kindly suggest me why task is not taking...i have already created task list
kindly suggest me
Regards
AqueelDear,
Is this quality Plan is back dated and Lot size should be 1 to 9999,999.
Why are you creating rate routing? check lot for 04 insp type in QA02.
Or for old material just create one new order and test it once again.
You can check the statuses in config.
QM>Quality Planning>Inspection Planning>General>Define Task List Status.
You should find that "4" is in there with all the check marks on.
QM--> Quality Inspection --> Inspection Lot Creation --> Maintain Inspection Lot Origins and Assign Inspection Types.
There is a column called status. For each inspection ORIGIN, you can specify the status of the inspection plan. It appears someone in your system changed the 4's to an X and then created the status "X".
Regards,
R.Brahmankar -
Gmail task list does not pop-out
After installing 3.6.7 gmail task list does not pop out. When I click the pop-out arrow, the task list opens in another tab, not in another stripped down window like it used to. Any ideas?
== URL of affected sites ==
http://Dear,
Is this quality Plan is back dated and Lot size should be 1 to 9999,999.
Why are you creating rate routing? check lot for 04 insp type in QA02.
Or for old material just create one new order and test it once again.
You can check the statuses in config.
QM>Quality Planning>Inspection Planning>General>Define Task List Status.
You should find that "4" is in there with all the check marks on.
QM--> Quality Inspection --> Inspection Lot Creation --> Maintain Inspection Lot Origins and Assign Inspection Types.
There is a column called status. For each inspection ORIGIN, you can specify the status of the inspection plan. It appears someone in your system changed the 4's to an X and then created the status "X".
Regards,
R.Brahmankar -
Transaction for replacing material in task lists
Hi
Do anyone now a transaction that can be used for replacing material no. in already created task lists.
Regards
TomHello TOM,
You can change the material in task list by choosing the change task list transaction and these are :
IA02:Change Equipment Task List
IA06:Change General Maintenance Task List
IA12: Change FunctLoc Task List
Thanks
Naveen -
Task list in hyperion planning dataforms 11.1.2 version
Hi,
I created a task list using administrator account and assigned these task list to user1. I mention a due date and alerts also. Here user1 have appropriate roles to access the dataform and to finish the task also.
Now the issue is, when user1 finished and put the status as completed. But in admin user, those tasks status is showing as Incomplete.
How admin will get that updated status as completed in task list.
Regards,
MadhuHi David Mendele,
Thanks for the reply.
ya as u said i looked into report. but there also am getting status as incomplete using admin user.
First of all i will explain u clearly about this issue.
using admin account i created two task lists and assigned these tasks to user1. for example salary account and salary details ok.
Now i login as user1 and put those task lists status as completed ok.
Then now i login as admin and checked out those Task lists. In this scenario, am not getting those task lists(*salary account* and salary details) status as completed.
It is still showing that status as Incomplete only which is already finished by user1 ok.
Now, how can i get those assigned task lists status as completed automatically using admin user.
I hope u understand about the issue.
Regards,
Madhu
Edited by: 895234 on Nov 30, 2011 8:01 AM -
Dear Experts,
how can i change task list from time type to counter type,
and how can i edit in the task lis and in the maintenance package,
ThanksI am not clear whats the question is. There is no concept of changing from time to counter....I think you want to change the scheduling indicators from time to counter based ? if yes, then you need to change it at the maintenance strategy level. once task list has been created with particlualr startegy, it cannot be revert back...you have to create a new task list for new strategy.
Mahee -
Hi,
i have a question about planning's task list.
I have two users (A and B).
Both of users using the same task list,
but if the user A marks as completed a task, the user B doesn't sees the complete activity flag of user A.
Can i enable the user B to see the complete task of user A?
Thanks
VincentHi,
Task lists status is stored at user level which means everyone can see their own task list status unless they do not share the same user name which is not the most desirable option. Even if there is a way of enabling someone seeing somebody else's task list status I would strongly discourage taking that route as it might possibly require you to touch on the source code, play around database tables etc.
Cheers,
Alp -
Shop papers for MaintPlans/task lists
Hi
Anyone worked on Shop papers for MaintPlans/task lists ?
Tcode OID1
What is the use of this configuration for maint plans and task lists ?
ThanksHi,
Did you maintain more than one entry in OID2 ?
Thanks
Naveen -
LSMW Transaction IA06 - Change general task list
Hi,
I'm using BDC for transaction IA06. But now I've encountered a problem in the maintenace package.
For each GROUP(PLNNR) and COUNTER (PLNAL), there are different number of maintenance package: screen field: RIHSTRAT-MARK01, RIHSTRAT-MARK02, RIHSTRAT-MARK03, etc.
In my source data, the input value is in number which corresponds to the text in each RIHSTRAT-MARK For example, the maintenance package for group PRPMP counter 1 has 1, 2, 3, 4, 8, 12, 16, 26, 52. From my source data, the package is 12, then I will have to check the 6th box.
The problem is, there are different number of packages for each group and counter, and the sequence of package text is dfferent too.
I'm wondering if there is a table that stores the number of package and it's corresponding text for each group and counter?
I've searched the forum, but there seems no discussion about this issue. I'd appreciate any feedbacks from you. Thanks in advance.
LilyLily Wu:
Were you able to find a solution to loading the data maintenance package: screen field: RIHSTRAT-MARK01, RIHSTRAT-MARK02, RIHSTRAT-MARK03, etc. ?? Transaction IA06 (Change General Task List: Maintenance Package Overview), Program SAPLCPDI, Screen 3600. I have searched forum too and do not see discussion on this topic also.
I have a similar situation needing to load Maintenance Package indicator data via IA05 thru LSMW. I have an LSMW using the Standard Batch/Direct Input. It is using Object 490 (Gen. task list) Method 0000 and the program Name is IBIP. I am able to import 2 files. 1 for the Task List Header to Structure IBIPTLST. The 2nd file to the Task List Components IBIPTMAT. This process works, but the requirement is to also load the data to update ("check") the screen field: RIHSTRAT-MARK01, RIHSTRAT-MARK02, RIHSTRAT-MARK03, etc. with the proper 'X's for each component.
I have found suggestions to use the IBIPMPAC (Maintenance Packages) structure to load. But this structue is looking for a 2 character field (i.e. KTEXTZYK01, KTEXTZYK02, etc. of type KTEXTZYK). This looks like the data that would be used for Maintenance Strategies Cycle Lengths found in IP11.
Any assistance in loading the Maintenance Package indicators is helpful. Thank you in advance.
Jim -
How to display list of TCodes with Change Documents enabled
Hi
I have 42 transaction codes (e.g. QA11, QA12, QE51N, QE01, QE02, MM01, MM02) and I want to verify if "change document" logging is enabled for the critical data elements in these transactions.
I'm aware that you can individually check "change document" setting per table via SE11 > Enter Table Name > Technical Settings > “Log Data Changes” option. Given the number of transactions (with multiple data elements) I need to check though, is there a table in SAP where the field, table, tcode and existing change document setting can be viewed?
Thanks
T-code
Description
MM01
Create material
MM02
Change material
ME01
Maintain source list
MSC1N
Create batch
MSC2
Change batch
QA01
Create inspection lot
QA02
Change inspection lot
QA11
Record usage decision
QA12
Change usage decision
QA14
Change usage decision without history
QA16
Collective usage decision for OK lots
QA32
Inspection lot selection
QAC1
Correct actual quantity in inspection lot
QAC2
Transfer inspection lot quantity
QAC3
Inspection lot – reset sample calculation
QE01
Record results
QE02
Change results
QE51N
Work list: results recording
QM01
Create quality notification
QM02
Change quality notification
QP01
Create Inspection Plan
QP02
Change Inspection Plan
CS01
Create BOM
CS02
Change BOM
CC01
Create Change Master
CC02
Change Change Master
SU01
Maintain authorizations
SE38
Execute program
COR2
Change process order
CC22
ECM Change Object Management Records
MMDE
Delete all materials
COR1*
Create process order with material
QA08*
Mass change of quality management inspection data
C201*
Create Master Recipe
C202*
Change Master Recipe
C298*
Deletion of Task Lists without Archiving
QPR4*
Process Physical-Sample Drawing
COEBR*
Batch Record Approval
QPR1*
Create physical sample
QPR2*
Change sample
CV01N*
Create Document
CV02N*
Change Documenthi Raphael,
you can also use following two table to view the change log at data element level:
CDHDR - Change document header
CDPOS - Change document items
e.g. give the table CDHDR in SE16N enter your transactions field "TCODE", and date parameter, you can see the results.
Regards
Javed -
Error in solution manager; no active task list exists in sap change manager
Hi,
i have created a correction in Solution manager but when i want to set it in status in development i receive the message below
No active task list exists in SAP Change Manager
could you please help me?
thanks
C.cmarrone wrote:Hi,
This says taht your ChaRM configuration is not complete. You need to rectify these errors to work in ChaRM.
>
> listed below the detail of the errors:
> Error in background job for program RSGET_SMSY error message No active job found
1. Please activate the Landscape fetch job for RSGET_SMSY from SPROSolution ManagerBasic Settings-- Schedule Bgd jobs.
> No RFC connection for system CIA client '000'
Please maintain a connection from solution manager to the transport domain system . I belive this is CIA.
> No CTS projects found for project ARC_AM_001
Recheck the transport configurations.
Rajeev
Maybe you are looking for
-
Illustrator CS2 stopped launching
My OS is 32 bit Windows Vista. My CPU is a Core 2 Duo. Adobe Illustrator CS2 used to work on my computer, but now it won't launch. It also won't reinstall or uninstall. I went to the Windows Control Panel for uninstalling programs. When I highlighted
-
Photo taken do not appear in Photos on iPhone anymore !
Hi, Interesting: this morning I updated to the latest version of iTunes and sync OK. Right after that, pictures I take, or screenshot, do not appear anymore when i go into the Photos App and check CAMERAL ROLL. There is a PREVIEW of the last photo an
-
I saw some discussions that seemed somewhat like what I have experienced, but thought I'd post this separately just in case. I have three AppleTV units. Two are wired, and one uses WiFi. The two wired ones work just fine, but using AirPlay for music
-
Oracle ADF compatibility with Web logic Server 12c
Is Web logic Server 12c support Oracle ADF. If yes please share details.
-
Why upgrade from Former Budgeting to Budget Control System (BCS)
Dear experts, My customer had upgraded his system to ECC6, and still uses the "Former Budgeting". I want the customer to consider implementing BCS instead. Please let me know where I can find the list of differences between FB and BCS, and the advant