GR qty to match TO qty

Hello,
Please find below process
PO - Inbound delivery - HU - TO - GR
Inbound delivery qty - 10
Hu1 - 7 nos
Hu2 - 3 nos
TO is created for for 7 and 3 nos but now when i confirm TO's GR is created for 10 nos
But my requirement is to create two GR with 7 and 3 qty respectively.
Please let me know the config for above.
regards
Suresh

Suresh,
The process which Frenchy explained is the Partial GR process and I just got that to work on a test system.
Here's what you must activate in the system:
ERP System:
  1.  Tcode BD105 - Add Object Type: BUS2015
  2.  Tcode BD104 - Add Object Type: BUS2015 (message type: SHP_IBDLV_CONFIRM_DECENTRAL)
  3.  Tcode SALE -> Modelling and Implementing Business Processes -> Master Data Distribution -> Serialization for Sending and Receiving Data -> Activate Outbound Business Objects / Activate Inbound Business Objects - Add your partner systems with object type BUS2015
Decentralized WM System:
  1.  Tcode BD105 - Add Object Type: BUS2015
  2.  Tcode BD104 - Add Object Type: BUS2015 (message type: SHP_IBDLV_CONFIRM_DECENTRAL)
  3.  Tcode SALE -> Modelling and Implementing Business Processes -> Master Data Distribution -> Serialization for Sending and Receiving Data -> Activate Outbound Business Objects / Activate Inbound Business Objects - Add your partner systems with object type BUS2015
  4.  Tcode WE20 - For you receiving (ERP) partner system, Outbound Parameters, Message Type "SHP_IBDLV_CONFIRM_DECENTRAL". Add basic type "SHP_IBDLV_CONFIRM_DECENTRAL03"
Question....What is your SAP Release? > 6.00 Package 16. If not, then there is a couple of notes you will need to apply (1330605/1318662/1236023/969403...etc)
Now when you create the TO you must follow Frenchy's procedure. This will create a WH doc (WM system),  Outgoing Idoc (WM System), Incoming Idoc (ERP system) and material doc (ERP system).
Like I said, I've just finished this scenario, so I am still going to a lot of tests for it's functionality we definitely can use.
Cheers,
Hein

Similar Messages

  • Production order produced qty not match delivered qty

    Hello Guru,
    We have problem in two of our Production order, we have produced qty for it 960 CAR for FG material 11205 in the PO, this can be seen 4 times confirmed partial for a series of yield qty of 240 CAR. in the PO confirmation overview. But when we check the documented goods movement 101 for FG 11205, it was only 180 CAR (each for the 4 partial confirmation was been issue) so the total delivered qty will be 720 CAR only. Why thus this happen, even we yield 240 CAR each on series of partial confirmation to the PO. The delivered was only 180 CAR? Please explain how this issue had happen. Where must be the reason behind this issue?
    Due to our closing, we should correct the Quantity as soon as possible. Can we confirm the missing quantity to this PO? Will this correct the delivered amount and consumption? We need to understand the root cause to prevent wrong delivered quantities.
    Thanks for the help and response.

    ellen,
    it seems that the base quantity , and conversion seems problem in this case.
    please check the conversion unit for both routings UOM and opetration UOM, in realtion to base quantity.
    why its different in the 2 work centres you compared?
    Work centre A  the then the quotient is 1/8 and
    Work centre B  the then the quotient is 1/6
    and base values in both the cases are different.
    and if i use to calculate out put in bith cases its showing different values then you put in your post ,
    1584 x 1/8 = 198 
    1530x 1/6 =  255
    just analyze one - one production order for both work centre A and B, whats teh base quantity of PO ?
    whats the quantity you input for yield for operation 0010 in both case and what quantity is available for next operation 0020, it will give you some hint.
    check out and revert back. hope it helps you/
    Regards
    Ritesh

  • PO-   Contract release Qty  not matching with  minimum delivery qty

    Hi  expert,
    I have a requirement   , there  is a  business process  where my   client need  to  replenish the fuel tank every two days . The tank capacity is 100,000 gallon   and supplier supply the fuel  of tank  11500 gallon every time.
    To map this process, we have set annual contact for   1000,000 gallon, We have  set our reorder pint as  50,000 gallon and lot size as HB  .  We have also maintained  alternate unit of measure as 1TRUCK= 11500 gallon.
    When the stocks  falls below 50,000 system create PR and auto PO generate  for  short  qty.
    But we need the short qty should multiple of deliver qty  I,e  11500 x3   = 34,500  not 40,000 gallon which calculate by system
    Am I missing something?
    Thanks
    Dilip

    No I have not maintained  rounding profile. The  qty i,e 40000 requirement calculation based  on  ( Max stock i,e Tank capacity  90000  --  50000 as Consumption qty)= Balance 40,000 qty PR generate  through MRP
    My requirement , System should generate PR for 11500 X3= 34500  Qty instead of  40,000 Gal
    Could it be possible
    Thanks
    Dilip

  • Schedule Release shipmet QTY not matched with line QTY

    the problem is when create schedule release and come to shipment lines and specific in QTY field which come by default from lines i found the QTY less than the line QTY for example i put in the lines (2400) each i found (37.1) and some times i found (.01)
    when try to put QTY manual system say QTY should less the line QTY so i try make arround which is delete the header lines and save then re-enter the line agian then system work normally ....this issue repeated many times with all users and specially when create release 2 or 3 from the planned purchase order so we need to know how we can avoid this issue in the future

    I do not understand the problem description.
    How many lines / shipments / distributions in Planned PO? What is the quantity in each of them.
    What is the quantity in Release Shipment / distribution?
    What is the exact navigation user is trying what is the error being thrown?

  • Inspection Lot Qty Vs Actual Lot Qty

    Hi All;
    I am posting multiple GR's against a Process Order for Eg 1st GR 100 Qty, 2nd GR 200, 3rd GR 300 and after doing this in the Inspection Lot the Inspection Lot Qty shows as 100 and the Actual lot Qty of 600 (sum of GR's) hence the Inspection lot Qty is always less then the actual lot Qty.... is this standard,I was thinking the Inspection Lot Qty gets updated with the Actual Lot Qty and they should match.
    Thanks & Regards

    What is the process order quantity when Inspection lot was created? It should be 100.Usually the process order qty will be shown as the inspection lot qty and the GR qty will be shown as the actual lot qty. That's the reason the actual lot qty is equal to your GR qty. Most of the times, these two quantities are same.
    As said in the earlier response, for incoming goods the GR qty will be shown as the inspection lot qty and during inspection if you find the received qty is higher or lesser than the GR qty, using QAC1 the actual lot qty is corrected. So, always the actual lot qty is the qty received.
    Hope it helps.
    Thanks,
    Ram

  • Report on Contract qty vs. PO Qty

    Good Morning!
    I am in need of getting a report out of SAP that shows the original contract qty and the revised qty of the contract.  My client at times may change the contract in order to create the PO for a larger qty than the original contract stated.  My client is not using BW,  they are using a program that is called stratum.  Thanks in advance for your help and I will definately award points!

    Hello Kimberly,
    You can try this out. Run program "RSSCD150" via SE38 or SE80. In the selection screen, enter :
    Object Class = EINKBELEG
    Object ID = 46* (wildcard for your contract numbering)
    table Name = EKPO
    From Date
    To Date
    Check "display in list viewer" box.
    From the results you should be able to filter out changes to target qty (field KTMNG)
    Hope this helps.

  • Order qty and total confirmed qty in PI sheets

    Dear Experts,
    Kindly suggest the possibility of appearing total order qty and already confirmed qty in the PI sheet, system useually provides the same while performing confirmation through co11n or cor6.
    Thanks in advance for your help..
    Regards,
    Nitish

    Hi Srini,
    The following details are available in the table AFVV,
    Standard value, operation qty & Base qty.
    With this values create a formula Standard value * operation qty/ Base qty , this will equal to the planned hours for that particular activity type. Similarlt planned hours for other activities can be calculated.
    The actual/confirmed hours are available in the table AFRU.
    Regards,
    Senthilkumar

  • GR Qty more than Delivery Qty in Production Order

    Hi
    there are a amazing Production order that GR Qty more than Delivery Qty of finished goods in this production order.
    there are some data in this production order as below:
    Order Qty = 2680
    Delivery Qty = 2680
    Tolerance = 0
    However, to my surprise, Material documents list there are 3500 Qty has been received related this production order. I have check all material documents related this production order. the total GR Qty is 3500 more than 2680.
    I know when I do GR for this production order if Total GR Qty exceed Order Qty, So, SAP will not allow me to do. because the Tolerance = 0.
    Anybody can tell me, how to deal with this error?
    Thanks
    Henry

    Hi Henry,
    If you do not want to restrict the quantities while confirmation, make the changes as required.
    Related to Material master, work scheduling view the under/over delivery tolerance should be zero and unlimited delivery tick should not be active
    While creation of production order (if manually created) under delivery or over delivery tolerance should be zero and unlimited delivery tick should not be active.
    regarding configuration, in OPK4 for plant and order type the following confirmation parameters are to be maintained
    Hope this will solve yours, come back if required.
    with regards
    Ram Kumar

  • In Import: Duties should calculate on GR qty not from PO qty

    Hello,
    We are Procuring the materail from Foreign Vendor.(By Import Procedure).
    We will get all taxes in PO Invoice tabs... and we are all getting in MIGO.
    But the PO is for 100qty then i will receive only 50 qty in MIGO... But In MIGO the Duties are all showing is for 100Qty why? iam only taking the 50qty in MIGO.
    In MIGO in Import the Duties will consider for GR qty not from PO qty?
    Regards
    sapman man

    the duties of cvd u have to enter manually so at that time u can do it
    also after  gr of ur goods system will give pick up the quantity as per gr only inmiro
    1.Create material master of import goods.
    2.Create vendor master record of import vendor and Customs clearing vendor.
    3.Maintain CIN settings.
    4.Maintain J1id.
    5.Maintain Pricing procedure SAP standard JIMPOR..,maintain required conditions..JCDB,JCV1...
    6.Assign the schema to respective import vendor in Purchasing view of VMR.
    7.Create import PO ,check in conditions of JCDB, JCV1 the customs clearing vendor(Indian vendor) and percentage is assigned..This can be done by In condition tab select condtion then click on display,then enter.
    Save the PO.
    8.MIRO --Capture Bill Of Entry.(Commercial Invoice No.,).Customs clearing first .Here CVD will b converted to BED.
    9.Capture Excisse invoice--j1iex.
    10.MIGO.
    12.Post Excise Invoice.
    13.MIRO...Payment to vendor(import vendor)
    regards
    kunal

  • Itu2019s showing confirmed qty more that order qty in sales order

    Dear Guru's
    I am working on production server issue; the issue is delivery has been created more that sales order qty.  When I am seeing sales Oder schedule lines itu2019s showing confirmed qty more that order qty in sales order what could be the reason can any help me on this.
    Regards
    DNR

    Hi DNR,
    first up, appreciate if you can use your real name instead of DNR , I'd love to see your actual name.
    Coming to the question, a deliery can be created more than the ordered quantity. And if you pick whats delivered - that can show as confirmed too..
    Standard SAP just throws a warning indicating this over delivery. And incase you want to prevent this happening - you can trigger an user exit to change this warning to error.
    Config is also possbile if you have setup your cust mat info record or sales order to check over delivery and set the item cateogry for delivery. You can go to t.code 0VLP( Zero VLP) select Over Delivery -  'B' for delivery item category.
    Regards
    Sadhu Kishore

  • Subcontracting charges for the processed qty not for GR qty

    Hi Friends,
    We know the subcontracting process having scrap involvement. BOM created for 1000kg of semi finished goods for which Raw Material required is 1200Kg and scrap generation is 200kg (-ve qty BOM). PO raised on supplier for 1000Kg of Semifinished goods. Carried 541 for 1200kg of Raw Material. GR with Mvt101 for 1000Kg triggers Mvt543 for 1200kg of Raw Material supplied and Mvt545 for 200kg of scrap.
    Here one will be able to pay SC for labour charges towards 1000kg only (based on PO and GR qty). While as the SC has processed 1200Kg of Raw Material. How SC will be paid for his actual work of 1200Kg?
    Thanks

    Hello All,
    For better clarity please refer below scenarios which will take you more closure to the requirement:
    PO
    PO Qty
    Oun
    Net price
    Curr
    Per
    OPU
    1000
    kg
    100
    GBP
    1200
    Kg
    GR based payment
    Processed Qty
    Semifinished
    Scrap
    GR Qty
    Oun
    Payment as per GR
    Desired payment to SC
    Diff in Pay
    Scenario 1
    1200
    1000
    200
    1000
    Kg
    1000 x 100/1200 = 83.33 GBP
    1200 X 100/1200 = 100 GBP
    @17GBP
    Scenario 2
    1200
    900
    300
    900
    Kg
    900 x 100/1200 = 75 GBP
    1200 X 100/1200 = 100 GBP
    25 GBP
    Scnario 3
    1200
    1100
    100
    1100
    kg
    1100 x 100/1200 = 91.67 GBP
    1200 X 100/1200 = 100 GBP
    @8GBP

  • GR Qty greater than Confirmed Qty

    Hi All,
    We have created Purchase order with Internal order as account assignment. When ever we are doing MIGO, System is giving the error " GR Qty greater than Confirmed Qty".
    Please help.
    Thanks
    Subrato

    >
    Subrato Chowdhury wrote:
    > The MIGO is happening whenever we are deattaching the internal order. The PO Quantity is same MIGO Quantity.
    Can you expalin more this line whenever we are deattaching the internal order ?

  • WM Picking Qty more that Delivery Qty

    Hi Folks,
    I have a case as below.
    Sales Order Qty - 100 CS
    OBD Qty - 100 CS
    Picked Qty in OBD - 120 CS.
    WM Picking was done for excess Qty of 20 CS in the same Transfer Order (which was created against the delivery).
    I tried to test the issue in Quality Client but there I recieved an Error "Total for assigned quantities exceeds quantity to be removed" .
    I really don't understand why system allowd the picking of quantity more than delivery quantity in Production Client.
    Any guesses pls.
    Thanks

    Hi,
    Change to 1, copy WM qty as delivery qty and do the cycle in Quality.
    Surely it will work.
    Or
    Also check
    check in picking strategies Indicators  
    Fully stock removal requirement active and
    Return stock to the same storage bin

  • Standard Packing Qty vs Minimum order Qty

    Dear All
    In Inforecord when I am maintaining Standard Qty and Minimum Order Qty
    system is objecting me by giving an error
    That  Minimum order qty must be less than Standard Packing Quantity can we avoid the error message
    kindly help me in maitaining the Inforecord.
    Regards
    Chaitanya

    Hi,
    This is standard system behaviour, see below extract from documentation:
    Standard Purchase Order Quantity
    Quantity of the material that is normally ordered from this vendor.
    Use
    The standard purchase order quantity serves as a basis
    for computing the effective prices in vendor evaluation.
    for determining the price if a price/quantity scale applies
    Example: standard quantity 100 pcs.
        Scale prices: 1-100 pcs. $10.00/ 101-200 pcs. $8.00
        Price determined on basis of standard quantity: $10.00
    Dependencies
    The standard quantity may not be less than the minimum order quantity.
    I fail to understand why would you have any problems with the fact that the minimum order quantity must be less than the standard quantity.
    Maybe it is because you interpret Standard order quantity as standard package quantity!
    Regards,
    Mario

  • Requirement Qty more than BOM Qty

    Hi,
    I have a scenario, in my Component Overview of Prodn Order, Requirement Qty of Components in Prodn Order is Different than BOM Qty.
    I checked the exploded Qty in CS11, CS12 and CS13. But the Reqt Qty vary with BOM Qty.
    Note: No Scrap is maintained
    Please guide.
    Thanks in advance,
    Harris
    Edited by: Harris Panchal on Feb 17, 2010 6:58 PM

    Hi,
    1. surely there is a mistake happening at your end.
    2. System is robustic on this kind of transactions
    Check the below items
    1. if any scrap has been maintained at the assembly level for the header material in the material master
    2. If any scrap has been maintained for the materail at the BOM item level.
    3. check if the unit of measure is same and any relationship is maintained.
    4. Also do re-xplode your CS11 and check if it works fine as per your expectation..if it is giving any issue in the production order , it should also give the same here..
    kindly validate and let me knwo the feedbakc
    reg
    dsk