Help Costing  Run !!

hello friends,
          I am having  a BOM with 210 items.
I want to run cost estimate for the BOM.I want to know
how and where should i manage the price of BOM items
(in which transaction i should maintain price of BOM items).
ALso let me prerequsites and procedure for running the
cost estimates  .
Kindly help me
Regards
SAM

BOM item Price can be maintedned in Material Master Accounting / Costing  View or Purchase Inforecord. Which price to be
considered is depends on Costing variant.
Product Costing steps...
Step 1:
Header Data – Create a costing run by specifying a name. Also enter description of the same along with date for which the costing run is taken
Finally save this data.
Step 2:
General Data – Select Costing Variant, Costing Version from the available options. Enter Controlling Area and Company Code.
Step 3:
Processing - Selection of Material
Click on the parameter icon, which will open a new window – change parameter window. In this window enter single material code/ range of material/ multiple material code and plant code.
Tick the field “Always Recost Material” and remove tick from background processing. After this save the data and go to the previous screen.
Click the execute button. The status field will show a green signal if all the materials were selected correctly, else will show red signal specifying error.
Processing – Structured Explosion
This step will read the Bill of Material for the selected product/products. Go to change parameter window and remove tick from background processing. Save the data and go to the previous screen.
Execute this step and the status field will show green signal for successful execution.
Processing – Costing
This step will create standard cost estimate for all the materials selected in Selection step and BOM exploded in structured explosion step.
Go to change parameter window and remove tick from background processing. Save the data and go to the previous screen.
Execute this step and the status field will show green signal for successful execution. The materials field will show total no. of materials that were costed.
Processing – Analysis
After costing step is over, a report is generated that enables to process and analyze the costing results. For example, compare the costing run with other costing runs or compare the costing results with a price from the material master.
After this remove tick from background processing field in the change parameter window and return to the previous screen for executing this step.
Processing – Marking
This step will mark the standard cost estimate for the costed products in the previous step. If the authorization field is locked, then it is to be opened by selecting the relevant company code.
This step would enable the results of standard cost estimate to be updated as future price in the material master.
Go to change parameter screen to make relevant changes and then execute this step after returning to the main screen.
Processing – Release
This is the last step in costing run transaction. This step will update the results of standard cost estimates in the material master as the current standard price.
It is to be noted that after releasing a cost estimate for a material in a company code, no marking or release can be carried out again for the current period. Before releasing a cost estimate, is should be made sure that the future standard prices are correct.
Go to change parameter screen to make relevant changes and then execute this step after returning to the main screen. To verify the updated prices, check the material prices in material master.
At every step if there is any error or warning, the log field will display it in detail.
if useful assign points.............
Venkat
Edited by: VenkatSrinvas Konda on May 2, 2008 6:29 AM

Similar Messages

  • Costing Run Error

    Hi All,
    I am currently trying to roll cost for materials but have an error that i can not seem to resolve, i hope someone can assist me and help me understand.
    While rolling the cost for a specific material the MFG Overhead cost is not being calculated correctly, i have looked at the routings for this material and do see where the error might stem from, but i do not think it can be corrected from there.
    The error is that in the routing the cost for MFG Overhead is calculated by adding Labour (1H) and Setup (0.017) and MFG Overhead = 1.017.  The lot size of this material is 300 but when roll up the cost with CK11N per unit the Set up value is 0.003 but the MFG Overhead does not calculate in the same fashion it remains as 1.017 (it should be 1.017/300 = 0.0033 ) This is causing a massive discrepancy in costing.  Now one solution is that the amount can be corrected externally and then update the routing and run the costing, but there will be an issue if the lot size is increased in the future (instead of 300 the lot size is increased to 400, now the routing will have to be change to 1.017/400 = 0.0025).  How can i correct the logic within SAP?  I have tried configuring the costing sheet, but i am not not sure where to change it.  In my costing run i am using costing variant PPC1.
    I have tried being as detailed as possible, and i hope it is coherent.
    I would really appreciate you help and points will be awarded.
    Thanks in advance

    Hi Althea,
    Thank you for your response.
    In the routing we have removed the MFG Overhead and now are using the Costing Sheet to calculate the Overhead.  I think i have updated everything, eg costing sheet, costing sheet components, percentage overhead rates, costing variants.  But now the requirement has changed again!!!! Just when you think you have crawled your way out of a ditch, someone pulls you back in. 
    In the legacy system they were able to calculate overhead in relation to cost centers ( Setup, Labor and Overhead for 403, Setup, Labor and Overhead for 403B and for 407 etc), but in the costing sheet you can only enter one cost center, is it possible to enter multiple cost centers and where would i do that?
    Now i had a cost element for Overhead, but in the cost element category was incorrectly selected as 43 (Internal activity allocation) instead of 41 (Overhead rates) now when i am trying to use select that Cost Element in the Costing Sheet under the credit area it will not allow me to save it.  I have created a new cost element but i am not certain what the impact might be
    Please help!!!
    Thanks in advance

  • CK11n Costing Run does not pull purchasing price from info record.

    Hi,
    I have material which is a semi finished product (Material type: SEMI) and is purchased from a fixed vendor (specified in the source list).
    The costing run does not pick up the purchasing price from the purchasing info record but
    instead incorrectly picks up the standard price from the material master (Costing 2 view).
    Can you please help me solve this issue?
    Thanks,
    Ketan

    Execute OPL1
    or
    SPRo>>IMG>>Controlling>>Product Cost Controlling>>Cost Object Controlling>>Product Cost by Order>>manufacturing Order>>Check Costing Variants for Manufacturing Orders (PP)
    Select the costing variant in the table from "Change Costing Variant: Overview" Overview Screen
    Click Detail Button
    Click Valuation Variant Button in the Control Tab
    Change View Valaution Variant Detail Screen Appears
    In Material Valuation Tab Set Price from Purchase Inforecord as Priority 1 if you want to use Price from Purchase Inforecord for semi-finished product during CK11N
    You can list down Priority 2 to 5 depending on your requirement
    This would solve your problem
    Edited by: Paul Pandian on Mar 17, 2009 3:01 AM

  • Costing run with values for material from info record.

    Hi All
    there is requirement with my client, that when i run my costing run the values of the components in BOM should be from the latest purchase order.
    For this i am maintined valuation criteria as price from info record and sub strategy as gross price from PO.
    When i am create a PO the info record is created automatically in background. So when i run costing run the value is picked correctly.
    Now when i create a PO with same material from diff vendor the info record is generated, but on costing run it picks the value from the info record of earlier vendor. For this i go and check the conditions tab in info record, ensure its balnk and save it. Again generate new PO and then run a costing run. This time the system reads the latest info record.
    My problem is that i want to ensure that during the costing run, system should read the latest info record w/o manual intervention. System behaviour is not consistent when there is multiple vendor and same material info records. Sometimes it pick up the value and sometimes it refers the old info record.
    Can any one help me out in resolving this issue. Its critical.
    Regards
    Rakesh

    Hi!
    Generally first info records will be created with vendor, then PO will be created, based on info records price, price will be updated in PO.
    If you have more than one vendor for same material, you have to create info records for each vendor. then you need to maintain source list, where you can fix the vendor. If there is no fix vendor, then you can do schedule agreement with vendors, where you have to give proportionate percentages again each vendor.
    Now for costing run :
    1. if you have only one info record, the price will take from that info record.
    2. if you have more than one info record, you need to mantain source list, where you can tick the fixed vendor, then system will take price from that vendor info record.
    3. if there is no fixed vendor and you have maintained scehduel agreement with weightage to vendor, then higher percentage vendor info record price will be picked up.
    4. if you have more info reocrds, not maintianed source list or schedule agreement, price will be picked up from first info record ( based on info record creation date).
    5. if you have a schedule agreement, but you have given equal weightage for example 50% and 50%, then also system will pick up from first info record.
    i think it is clear now.
    regs,
    ramesh b

  • How to ignore the material with error in costing run ck40n

    Hi
    Pls, advice how to ignore parent material form costing run if the components of that material have errors. I need to run the costing run excluding erroneous parent item. Is any configuration on this..
    Pls help..
    K

    Hi Kesharika Goona... 
    If you want to exclude any material from Costing Run, there are two ways...
    1. Go to Material Master, Costing1 view, take the check box "Do Not Cost". If you opt for this check box, the system will not consider this material for costing.
    2. Where you run the standard cost estimate in CK40N, once you save you costing run with the parameters like Costing Variant etc, When you select the "Parameters" agains the Flow step of "Selection", you will be asked to give the inputs like Material Number, Plant etc.
    There, against the Material Number, on the extrem right side, you will see a arrow, press that arrow, and there you can see a tab "Exclude Single Values". There you have to give the material number which you want to exclude from the costing run press "Execute" icon on the botoom-left corner of that pop-up window..
    If you still face problem, pls revert back
    Srikanth Munnaluri

  • Import Duty added to costing run CK40n

    Hi all,
    We are looking to have the system automatically add the import duty on materials imported from outside of China into China during the SAP costing run. Was lookign at using CK74 additive option to set this up in the costing run or maybe somewhere in MM-PUR?. Has any one done this before or have any information on how to set this up please?
    Cheers

    Hi sree-
    You can use x-plant material status indicator during costing run. you can set up all the parts that are active with an indicator and use this indicator during cost run. you will find this indicator in dynamic selections.
    Hope this helps...
    RNarayan

  • CO/PP - Costing run - raw material cost component

    Hi
    In the costing run how raw material cost is taken?
    is it the material moving price/
    or calculated separately?
    Please help

    i think this depends on the costing variant defined in the order type
    in the costing variant, this come from the valuation variant
    for process orders you may check the following txns COR4, OPL1, OPN2

  • How purchasing master data setup impact CO costing run

    Dear all,
    Question 1:
    Could somebody out there, if you have this area of integration knowledge with CO, tell me the detail process and logic of how, when a costing run is perform, the master data in the Material master fields of Procurement Type and Special Procurement Type; Purchasing Information Records; and Source List impact the successful of costing run?
    Question 2:
    CO guy complaints that there are missing PIR and source list for following type of material setup in material master:
    A) procurement type - F, Special procurement - blank (i.e. third party)
    B) procurement type - F, Special procurement - NON-blank (i.e. can be intercompany, subcontract, vendor consignment),
    Hence Costing run unable to determine the price. Is it a valid complaints
    Regards,
    Daniel

    Hi,
    Though Costing is realted to the price control , cost lot size and valuation class in Material master.
    It almost equvalent dependent on Special Procurement type also is costing view and MRP view.
    Do refer the effect of special procurement type in costing in belowHelp Link
    https://help.sap.com/saphelp_46c/helpdata/en/7e/cb7f5643a311d189ee0000e81ddfac/content.htm
    Do refer the basisc of standarad costing estimates in below Link
    Basics of SAP Standard Cost estimate- Understanding the flow of cost settings-Part 1

  • Cost estimate/costing run

    Hi
    What is the difference between cost estimate and costing run?
    Thanks,
    Nivi

    Hello Ram,
    There are 3 steps in Costing Procedure. They are
    1. Creation of cost estimate
    2. Marking of cost estimate
    3. Release  of cost estimate
    Once you release cost estimate, then only system will update the required fields in the database and can be used for transactions.
    Hence, cost estimate means, it is just estimated total cost of the product and Costing Run means which inclusive of all the above three steps to complete the total process.
    Please let me know if you require any further clarifications.
    Thank you,
    Regards,
    Santosh
    Reward points if helpful.

  • Global Costing Run

    Hi -
    We've implemented a Global Costing solution with plants and stores located all over the world  - does anyone have experience in how we can 'automate' the Costng Run to run on a global scale ?

    Hi sree-
    You can use x-plant material status indicator during costing run. you can set up all the parts that are active with an indicator and use this indicator during cost run. you will find this indicator in dynamic selections.
    Hope this helps...
    RNarayan

  • Strange issue encountered when doing costing run

    Dear experts,
    I encountered a strange problem when doing costign run use CK40N.
    I created a costing run on 23.12.2010 In the costing  run the validity was set  from 01.01.2011 to 31.12.2011, I did all the steps except release, all steps were done successfully
    I released costing run on 01.01.2011, but when I hit a material to check the costing date, found the costing was only avaliable to 31.01.2011 not 31.12.2011.
    I was wondering if any actions or modifications done will affact on the costing date of material?
    Have you ever meet this problems?
    Please give me some help.
    Thanks for your time and concern.
    Regards,
    Anna

    Hi Sarada & ajay
    Thanks for your comment.
    The most strange thing is...
    When I display costing run, the valid to date is 31.12.2011, but in material, it shows 31.01.2011....
    I did test again, to change the valid to date in CK40N of the costing run, but the result is, date in material alway the same with what displayed in costing run in T-code CK40N.
    One more information, we usually do costing run per month, and we just change to valid date to end of year from 2011.
    At first I thought it might have some relation with modifications to costing variant, but after doing test, the modifications will not affect.
    The valid date in material should always be the same with what displayed in costing run.
    And after the first step 'Selection' in costing run, the date will not be changed.
    So I could not come out with any idea with issue......

  • PP/CO issue - Costing Run.

    Dear SAP GURU,
    Understand that there's Material Cost Estimate Without Quantity Structure.
    Really appreciate you guy can share the following :
    From CO/PP Point of view,
    1) Can we Costing run without BOM but with Master Recipe ? Since there's Work Center & Activity type.
    2) Before Costing Run , What if Production made misstake created , Release & Confirm the Process Order ?
    3) Cost Estimate with Quantity is to calculate non-order-related, What if Order related ?Should we use Cost Estimate witout quantity structure?
    From PP Point of view,
    4)What's the major problem that will affect the BOM Explosion during costing run ?
    5) What is Major issue will impact Costing Run (beside Master Data) ?
    Thank you.

    Dear,
    Don't ask too many questions in one thread also this thread is relevant for CO forum So please use correct forum.
    1) Can we Costing run without BOM but with Master Recipe ? Since there's Work Center & Activity type.
    Yes you can.
    2) Before Costing Run , What if Production made misstake created , Release & Confirm the Process Order ?
    See In this case system will do the valuation as per the price given in material master.
    3)What's the major problem that will affect the BOM Explosion during costing run ?
    There could be many problem but few listed problems are Lot size validity date, Status of BOM. Cost relevancy indicator.
    4) What is Major issue will impact Costing Run (beside Master Data) ?
    Same as per question 3.
    Hope it will help you.
    Regards,
    R.Brahmankar

  • New costing run within same period for relased cost estimate

    Hi All
    Once we have run the costing run. The price is marked and released. Then If we have to again runthe costing run, system says price for the priod has been released and doesnt allow to proceed.
    How to overcome this? Cant we run costing run as and when required and multiple times release it in the same period?
    Please help me
    Regards
    Rakesh

    Hi Rakesh,
    I would like to know what is your requirement of running the Standard Cost Estimate for second or third time in the same period...?
    If you feel that, Standard Cost which was marked and released needs to be updated as per the changes in BOM, Routing etc, you can still do it...
    First, go to transaction code CKR1 (Re-organization of Cost Estimates), select the parameters like company code, plant, material (for which you want to reverse the Cost Estimate), select the radio button for "Current Standard Cost Estimate" and execute.
    Then, Current Standard Cost Estimate will get reversed. You check for confirmation in the respective material master -- Costing 2 View whether the Current Planned Price has become blank or not.
    Then you do CK11N and CK24 again for marking and releasing....
    Try this and pls revert back for further explanation...
    Srikanth Munnaluri

  • Selection List for Costing Run

    Hi guys
    I vaguely remember that there is a place where I can create a selection list on only the materials that I want to cost in CK40n, but I cant seem to find it any more.
    I tried the CKMATSEL - Create  transaction, but when I go to execute the Selection in CK40n, I dont see what I created in CKMATSEL...
    Is there any other way or am I doing something wrong in the CKMATSEL screen?
    Thank you
    Rukshana

    Hi Rukshana,
    Pls go through the following which may be of help...
    1. If you want to exclude the Materials from a single Costing Run...
    If you want to exclude some Materials from Costing Run, when you select the Materials to be costed in the "Selection Parameters" of Costing Run, press the Arrow button for additional selections, click on "Exclude Single Values" and mention the Materials which you want to exclude from the Costing Run.
    In the selection, you can select all the Plants (Plant 1 to Plant 4). By this, system will exclude those materials which you mentioned from all Plants when you run the Cost Estimate.
    2. If you want to exclude the Materials from being costed on permanent basis...
    Go to MM17 (materials mass maintenance), select the "Fields" tab, "Find" - "NCOST", select that row, press "Execute". Now, select/give all the Materials which you want to exclude from being costed, mention the Plants and "Execute". You will see the list of Materials which you have mentioned and on the right hand side, you will see the column with "NCOST" field. Mark "X" for all materials there.
    This NCOST field is nothing but "Do Not Cost" check box in "Costing1" of Material Master. By this, system will understand that, whenever Cost Run is done, all these materials should be excluded from being costed.
    Srikanth Munnaluri

  • Unabsorbed balance after actual cost run

    Hi gurus
    I am facing problem in Production cost center there is unabsorbed balance after actual cost run
    kindly help me.

    Thanks all.
    I have solved it.

Maybe you are looking for

  • Unable to log on through SAP GUi

    Hello Gurus, Issue: Unable to logon through SAP GUI after giving the username and Password. When the user name and password is entered the system gets to the process mode but hangs in the same stage. When i check the R3trans -d the following is the r

  • CRC Error on installing 10.2.0.1 on Linux

    I've downloaded the 10.2.0.1 full Grid version for Linux and tried to install it on Oracle's Enterprise Linux.... I keep getting a CRC error on disk 2....has anyone else seen this ? Thanks Bernard

  • Wi-Fi not functioning correctly

    As others have reported, my wi-fi will not stay active, but instead EDGE overrides. I have a functioning and high signal from my Linksys WRT54G. I followed previous advice in threads that suggest the DNS IP address must be put in of my provider or an

  • Local hyperlink in JEditorPane

    I set a HTML page from String variable to JEditorPane. I;ve got som hyperlinks to this page like <A NAME="AAAAA"> Link I need to handle such a link. I set editable to false and implemented hyperlink listener, but event returns null URL when calling g

  • Subtotals in Discoverer

    Can anyone help me with calculating subtotals in Discoverer. I know discoverer offers subtotal by break in Region or Dist Value. Or like CD, DVD etc. What I want to achieve is subtotal of all used products as below CD 120 USED CD 100 DVD 80 USED DVD