How to see planned orders for P3 mrp type products in APO?

Dear experts,
I have materials with P3 MRP type (not planned in APO but in R/3 using MRP)
I have active integration models with P3 and X0 mrp type products for planned orders
however I can not see in APO product view the planned orders for P3 materials,
is this normal or should I see those planned orders in APO?
Thanks for your answer,
best regards
Elynn

Hi,
The following prerequisites must be met so that planned orders can be transferred from SAP R/3 to SAP APO
and vice versa:
1.The material masters must be transferred to SAP APO.
2. PPMs must exist for planning in SAP APO.
3. The relevant integration models must be active.
4. An active integration model for planned orders must exist in SAP R/3.
5.An active integration model must also exist for materials, so that the components of the planned order are transferred.
6.The relevant distribution definitions must be maintained in SAP APO, so that planning results can be
   transferred from SAP APO to SAP R/3.
Thanks,
nandha

Similar Messages

  • I can't see planned order in Long Term Planning Stock/requirements list.

    Hi
    I am trying to use Long Term Planning in SAP.
    I created scenario dates from 01.03.2011 to 03.09.2011. Between those dates i entered planned independent requirements as 300.
    When i went to Long Term Planning Stock/requirements list, i can see all planned independent requirements but i run Multilevel single-item planning and then when i went to  Long Term Planning Stock/requirements list again, i couldnt see planned order for planned independent requirements.
    So what is the problem? Can anyone help me please?
    Thank you.

    HI
    check the planning scenario in MS31 and the PIR assignment in MS31 also check the plant assignement.
    Check In MD61 you have enter PIRs in simulation version and the same version is to assigned in planning scenario
    Also check T code OPU5 for LTP setting for planned orders
    Regards
    Anupam Sharma
    Edited by: anupam sharma on Sep 3, 2010 2:33 PM

  • Planned order for MPS items can be unfirmed in MRP plan

    Hi All,
    I'm using SCP functionality (not ASCP) in MRP module. I run a global MPS first and then use it as supply schedule to drive mrp plans. I noticed that some planned orders (for MPS items) loaded into MRP from MPS can be unfirmed in MRP and I can enter new quantity and new date for them, whereas other planned orders for MPS cannot be unfirmed.
    What is the logic behind it? How to control it?
    thanks in advance,
    Tom

    Hi Ram,
    I don't think that there should be any issue due to the planned order created in the system against the PIR for the next month ....& it will not lead to improper planing even if the demand changes still we are not going for the firmed planned order....... if the PIR changes during the next MRP run then it will adjust the planned order accordingly .....
    Still you want to  restrict the planning to the current month then the simplest way that  I can think of is planning horizon....
    Thanks
    Kaushik

  • How to cummulate sales orders for creating one planned order.

    Hello friends,
    My scenario is make to stock. I use sales orders for creating plan only. I want to cummulate all sales orders of one finish material and create one planned order  for that material when i run mrp. How can i do this?
    Thanks

    Kiran,
    What is the planning strategy you are using?
    Does all the sales order requirment same? If it is same then it is possible. Please explain more in details. If not you need to look at using some perodic lotsize procedure to combine requirments. Like "Daily", Weekly" "Month" etc..
    Regards,
    Prasobh

  • MTO - how to prevent a second planned order for a sales order?

    Dear friends,
    We are working on Make to Order process (Planning strategy group 20).
    No Production/process order is used
    Shop floor uses a different system --> details from planned order is passed to the shop floor system; and finished product is delivered/posted into SAP Sales order stock - through interfaces
    No QM in place
    A typical day-to-day scenario –
    Sales order Qty = 100
    MRP Run à Planned order qty = 100
    Raw materials posted to ‘Sales order stock’
    Planned order is firmed
    For example if Produced qty = 90
    sales order stock of the finished product = 90
    Balance 10 cannot be produced / delivered for various reasons
    Planner posts the raw material to cost center / rejections / own stock etc., and ensures that the ‘sales order stock’ of the raw materials are zero.
    Planner deletes the planned order
    Next MRP run triggers a new planned order for the balance qty 10
    Now, the requirement is to prevent the new planned order getting generated for the balance quantity, during the subsequent MRP run (despite the shortage in the Sales order stock of the finished product).
    The following options have been evaluated –
    Once the final good receipt is done & before deleting the planned order,
    o       Change the Sales order quantity to match the total produced quantity
    o       (or) Change the schedule line category for the Sales order item from CP to CN
    §         Since the Sales order and planned order are handled by different teams, considering the frequency of correspondence/coordination needed between these two teams to get the sales order items corrected, this idea is not accepted
    §         Additional authorization for the planner to change the sales order item is not acceptable
    Include Under delivery / Unlimited tolerances
    o       at the customer (master) level
    o       (or) Sales order level…
    §         In this case, System seems to consider the tolerances only when the  delivery for the Sales order is posted; and not when the sales order stock is received within the tolerance limits;
    §         Considering the time gap between the GR and Delivery of the finished product, this option is not accepted
    Kindly suggest the other options / settings / processes, to meet this requirement
    Thank you for your time and efforts.
    With Best Regards,
    Senthil

    Closing this thread
    Thanks
    Senthil

  • Can MRP only create planned orders for ROH, not for FERT?

    HI all,
    Is there any way to only generate planned orders for raw materials after MRP, forbid creating planned orders for FERT?
    We want create planned orders for FERTs manually.
    Thanks,
    Harvey

    Harvey,
    Yes, that was also my understanding of your scenario. Did you try X0 for Fert?  Run MRP against the entire plant, and MRP will not create any new planned orders for the X0 parts.  It will explode the BOM and create dependent requirements in the components.  In addition, you can create FERT planned orders manually, or using an external planning system, and these manually created orders will also create dependent demand on your components.
    If you are also using Sales orders to consume your PIR, you will also have to look at requirements determination for Sales orders.  This is configured based on MRP type.  If you change existing MRP types, you may have to add SD config so as to continue to pass requirements to MRP.  Your SD resource should be able to help you through this, or I can give you basic instructions if you decide that the PIR/demand/planned order/dependent requirements works to your satisfaction.
    Rgds,
    DB49

  • Unable to release planned order for single line from MRP workbench

    Hi
    We are unable to release planned order for single line from MRP Planner workbench,but Select All For Release is working for all the lines for the item
    User want to release a specific line but no new requisition is generated
    It is highly appreciable if anyone could help to resolve this issue
    Appreciate the Help
    Regards
    VKPK

    It sounds like the release goes through in the workbench but the requisition does not show up in source - is this correct? If so I would check item attributes / flags for purchasing and buy. also have found some items require a purchase price to be populated in master and org

  • How can I set a fixed scrap qty on planned orders created by MRP?

    During production of some specific subassemblies, destructive testing is done that requires us to scrap two pieces per production order.  I know I can set an assembly scrap percent, but what I need instead is a way to set a fixed assembly scrap quantity that will get loaded onto every planned order created by MRP for these subassemblies.  If we can't do this, we can't plan the correct order quantity and eventually end up being short of parts.  I know we can set a safety stock or safety time, but I'd rather just plan the right quantities if possible.
    Is there a user exit, configuration option, or master data setting that will allow me to do this?
    Thanks,
    Randy

    Hi Randy
    This can be solved by one solution. _You can try this._
    You define the same item in BOM again with qty 2 nos. Double click on the item no. Then it will take you to item detail. There in Basic data tab page at quantity data  ( Tick the fixed quantity. ).
    When ever BOM explodes for the header material automatically The item will be exploded 2 nos extra.
    Ex
    The header is Mat X and items is Mat Y. While creating BOM for X give item Mat Y in item no 10. give the quantity as per the requirement.
    And again give item Mat Y in items no 20. give quantity 2 nos and activate the fixed quantity tick as instructed above.
    When ever requirement for Mat X is 100 nos. The plan order for Y will be 102 nos .
    Hope this will clear.
    Regards
      J .Saravan

  • Several plan orders for the same day

    Hi SAP Experts,
    In my company we have a requirement to produce the same finish material in two work centers, using different BOMs. This was achieved through production versions for production orders. Now we need to plan (Indipendent requirement & Plan orders )the material based on these two BOMs.
    We enter the indipendent requirement in MD61. I have given the production version against the requirement (In schedule lines tab). However i am unable to give two different requirements for the same day in different production versions.
    Then i tried using different planning versions and assigning the different production versions to different plan versions.
    Although my indipendent requirements are taken in different production versions(As I can see in MD04). When i run MRP plan orders are raised as the total of the requirements and in only one production version.
    Please, Can some one help me to find a method to raise different plan orders for the same day in different production versions???
    regards,
    Madhushika

    Dear All,
    I tried  quota arrangements as a solution for above mentioned problem. What i require is to devide the PIR for a particular day in to two equal parts in two different production versions so that two plan orders will raise in equal quantities for the same day in two different production versions.
    With quota arrangement what i get is alternative plan oders in different versions in diffrent days.
    For example If my PIR are
    Day 1 = 1000
    Day 2 = 1500
    Day 3 =  500
    Day 4 = 1000
    what i get is
    Day 1 = 1000  - prd ver1
    Day 2 = 1500  - prd ver2 
    Day 3 =  500   - prd ver1
    Day 4 = 1000  - prd ver2
    What i want is
    Day 1 = 500 -prd ver1
    Day 1 = 500 -prd ver2
    Day 2 = 750 -prd ver1
    Day 2 = 750 -prd ver2
    Day 3 =  250 -prd ver1
    Day 3 =  250 -prd ver2
    Day 4 = 500 -prd ver1
    Day 4 = 500 -prd ver2
    Hope its clear to you all.
    Please advise me how to configure the system according to this reqirement.
    Best regards,
    Madhushika

  • Consolidate Planned Orders for Past demands

    Hi Experts,
    I have come across the following requirement. So, please follow the Screen shots.
    You can see that MRP Run has created 2 planned orders for the separate 2 demands (One is for 11.02.2014 and another one is for 15.04.2014). But when you look at the demands, you can see that these are old demands. How can we configure the system to have only 1 planned order for the qty 101 by having the date as latest finished date.
    So for an example.
    I want to have one planned order for 101 giving the date as 05.08.2014.
    I'm open to any valuable suggestions as I've a sand pit client to do some testing. Just want to show you the setting for parameters for determine the Basic Dates. ( I have a  clear idea what the following settings do)
    Thank you very much.
    Kind regards,
    Ishara

    Hi Ishara,
    Please check in MRP1 tab the lot size data (weekly, monthly,...). I think that your setting is monthly. For this reason you have two pl.orders created one for February (10 EA) and the other for April (91 EA). If you want to have just 1 pl.order choose min/max lot size equal with 101 EA.   
    Also check in MRP4 tab, section BOM explosion what is your individual/collective setting (should be collective).
    Thanks.
    Regards, Marius

  • Planned order for Negative stock

    Hi All,
    Negative stock set up is active at storage location level. Due to this setting I got some  negative stock in storage location.
    MRP is creating additional planned order specific to negative stock qty other than planned order created for that day requirement.
    How to get only one planned order for entire day requirement including negative stock?
    we have daily lot size in mat master.
    Thanks.

    Negative stock "requirement date" is immediate (day of MRP run). The other daily requirement that you may have, may be for a date other than "today", and this is why you get 2 planning proposals.

  • Planned order creation via MRP depends, If we change Delivery date in STO

    Hi,
    Planned order  creation via MRP depends, If we change Delivery date in Stock transfer Order.
    I created STO with delivery date as 31.1.2012 and when i checked MD04, i can see Planned order created on 27.2.2012 with the same above STO quantity .
    Now when i changed the delivery date as 30.1.2012 and runned MD03, and then checkd MD04, planned order disappeared.
    Why Planned order got created when STO delivery date was 31.1.2012 and when I changed the delivery date in PO, planned order disappeared.
    MRP profile details :
    Plnd delivery time   1
    GR processing time   1
    Planning time fence  38
    Tot. repl. lead time 38
    Can you please let me know why system is beaving in this manner?
    Regards
    Utsav

    Hi,
    Normally , MRP runs based upon the requirements.If your STO is created for a date , system checks through the availabiloty check wheather there exists any stock for that date to get deliverred in the supply plant .If there exists for that date the stock , planned order will not be created.If no stock available then a planned order will be created in MRP.
    cHECK the availability check parameters assigned to material master in supply plant.
    Regards,

  • How to trace planned order data after it has been converted into production

    Hi, There,
    The planned order has been converted into production order.
    However, I need to trace if this planned order is generated by MRP
    run or created manually. I can't get any planned order info from
    table PLAF. Any input?
    Regards,
    Nancy

    Hi,
    Once fully converted, the Planned Order data will not be available in the Table : PLAF.
    If it is available, then You can have the details with the Time Stamp and User data from PLAF.
    But, the refrence will be available in the Production Order.
    You want to make a Track of the Planned Order details and the Quanity, then you need to have/create Z tables so that the data will be availabe.
    This is how most of the Organizations keep a track of the Planned order data.
    Hope this helps..
    Regards,
    Siva

  • Setting nedded for creation of Planned Order for Dependent Requirement.

    Hi PP Gurus,
    I have a one material for which I m running MRP which have three Components.
    I m using strategy 10 for FG and SFG also.
    When I m running MRP for FG the system is creation planned order for FG, but not for SFG even though no stock available for them.
    I m using lot size EX for all SFG.
    Please Help.
    Thanks in Advance.

    Dear ,
    You should maintain proper MRP related parameters for both FG and SFG.Check all the MMR parameters :
    1.MRP Type -PD for FG/SFG
    2.Procurement Type -E  for FG/SFG
    3.Planning Startegy -10  in FG
    4.BOM/Routing Explosion -Keep it Blank
    5.Indiviaul/Collective Indicator -not applicable as it is MTS  so keep it blank
    6.Validity of BOM /Routing should be corrcet before MRP run in MD02-NETCH , 2,1,3,3,2
    7.What is the Lot Sizing Set up-EX in OMI4-Scheduling Tab -Requirement date =Delievery Date and BOM Validity Date  .
    Ref .Re: MRP not plalned for dependent components
    8.Check in MRP4 -MRP Dept Requirement Parametre should be balnk for plalling the SFG  in MMR of FG -MM02
    I hope this issue may be with BOM explosion as per the validity and lot size -schedueling set up .
    Hope this will be useful
    Regards
    JH

  • Multiple planned orders for a requirement

    Hi,
           We have PPDS MRP with NEW shelflife w/ lot size profle run for product and produces multiple planned orders for the the requirements.
    I have a requirement of 4,750 and 14,976 in the system and available stock 86,966.
    The system creates two planned orders with 34,632 and 26,771 PCs.
    Why is the system creating two order instead of one??
    The min. lot size is 1876 and rounding is 936.
    can somebody tell me what factors the system is considering??
    Thanks.

    Hi Visu,
    Which lot size procedure you are using , please check in lot size tab in Product master, it should be lot for lot.
    if it is lot for lot , please change it to by period and weekly , is it change the planned order quantity ?
    Manish

Maybe you are looking for

  • Printing presets!!!

    I am running OS X Mountain Lion on a new macbook pro retina display. i am pretty happy with it, but some things are just driving me insane. If you can help to solve some of those, then you could look at some of my other posts, but....i digress. Anywa

  • Schedule a report with custom datasource cause "failed to open connection"

    Dear all,       I have a BOE enterprise Xi 3.1 SP 2.3 running on a RED Hat Enterprise kernel 5.3 with tomcat as web server. I have a report design with crystal report designer. The report default use JDBC as connection to Oracle 11g database. If I se

  • How do get rid of this webkit2webprocess file eating up memory and crashing my browser every time

    This file is definitely bugging me I have tried everything but every time this file starts eating up memory and slowing down the computer isthere a solution for this we have the i5 coming out nowbut this has been constantly nagging and isee somany is

  • Placing the ux3 Shell in sap.m.Page causes its header to disappear

    Hi Community, I want to have a common Navigation Links for the complete SAPUI5 application , so my preferred choice was ux3.Shell. But while placing the ux3.Shell in sap.m.Page , its header is overridden by that of page . How to avoid this ? Or is th

  • Region automation Q

    I'm using an m-audio oxygen 61 and have some knobs and faders assigned to interact with Vienna Instruments. I've been able to record MIDI data from these controllers, but I'm currently unable to find a way to edit one of them. With region automation