Hi all,
Due to business reasons, we have unchecked the 'Agree' indicator in the Acct assignment configuration for Asset accounting.   Hence, cost center becomes editable during document posting.
We want the cost center to be editable only for ABF1 t-code and for other asset t-codes like acquistion, retirement, scrapping, transfer etc, we want to derieve the cost center from the master data.
Given the situation, I request experts' input on 2 questions -
1.  Is it possible to have the cost center editable only in ABF1 and disabled in other AA transactions?
2.  If cost center is editable in all the t-codes, what is the implication if the cost center is mismatched with the data available in the master record?
Please provide your inputs.
Thanks in advance.
Regards,
Sridevi

Hi,
The client has many plants, of which only few are running in SAP and the rest non-SAP.
Whenever there is transfer of asset from non-sap plant to SAP implemented plants, we handle the situation as below in the receiver plant-
1. Treat the asset transfer as legacy asset transfer and create asset master record through AS91.  Maintain the cummulative acq value and Cummu depn value till the last period in master data.
2. As legacy transfer is not real time integrated with FI, we are doing ABF1 posting to pass manual JV to record APC and Acc depn. posting.  At this instance, we want the cost center to be manually keyed in.  This is because, we have yet another situation, where we need to have the net book value of the asset at cost center level for our allocation cycles.  Hence,
3. But, for other normal AA transactions, it shd automatically derieve from asset master.
Request your suggestion on achieving the above requirement.
Regards,
Sridevi

Similar Messages

  • Modifying the cost center when posting an MM invoice

    Hi All,
    my client wants to change the Cost Center assignment field when posting an invoice coming from MM process (PR>PO>SES).   I'm now using transaction MIRO to make some test and I see the field is 'not modifiable'. I tried to see if i could sort it out from trx.OME9 but i am not really sure how and if i am in the right way. Somebody can please give any clear advices for this requirment?      Thanks so much in advance,
    regards
    Livio

    HI,
    Just to make sure that there is no confusion here, the changeable indicators DO work if you have a valuated receipt, you CAN change  the assignment, but the postings have already been made and will not be affected by the change (it will simply affect further receipts after the change) and so Shoaib is right in some respects because it is not changing the posting, but the fields can be changed to affect future receipts, even after a valuated GR. (I have done this many times).
    But I think that the problem with this query is the fact that it is a service PO with the item category D. There is additional validation involved due to the complex data of a service PO.
    So I would suggest that you try to change it in the service entry sheet or PO (you may have to reverse the SES first.
    Steve B

  • Change the cost center

    Hi all,
    In a report, I must change the cost center for Purchase Requisition and Purchase Order.
    In my opinion I must use the bapi: "BAPI_REQUISITION_CHANGE" and "BAPI_PO_CHANGE", but I don't know how to use.
    Is this correct ?
    If yes, can someone explain to me how to call them to change cost center ?
    Thank you in advance.

    Hi
    Please refer the below link you may useful.
    BAPI_REQUISITION_CHANGE
    Thanks and regards,
    Syf

  • Why can't I change the cost center in PA0001 using PA30?

    Hi Gurus,
    Please help.  I cannot seem to find the means to enter the cost center in the organizational assignment infotype PA0001.  It is showing as greyed out/display only. 
    As background, these personnel files were setup for time entry.  Other infotypes populated that might be impacting it are 0315.  We are not setup for organizational management within SAP.
    As I remember if I don't populate sender cost center/create infotype in 0315, I can change the cost center in PA0001 using PA30, but if I do I'm greyed out.
    Can anyone provide some insights and a possible fix for this?
    Thanks.

    Try turning it OFF by removing the X and saving it.
    Then check on PA30 if the cost center field is enabled for you to enter.
    If this doesn't work, please put the X back in the table and save it.

  • How to changed the Cost Center Date

    Hi All,
    I have an issue. Cost center is created which have a valid date from 10.01.2009.
    Upon checking my set up in the SAP my default date format it is DD.MM.YYYY.
    It have mistakenly inputted a different date instead of October 1, 2009 it inputted January 10, 2009.
    To resolved: When i went to KS02. I could not edit the valid dates just the master information. And also in KS12.
    Is there a way i could change the valid dates of the cost center?

    Hi,
    But did you succeed to delete it via KS04 or not? If there are postings in this period, then obviously, it won't be possible to delete it and the validity period could not be shortened retroactively anymore.
    Regards,
    Eli
    P.S. OKEON won't help you...

  • Where to change the cost center in material document?

    Hi everyone,
    I have a problem. Last month, I've created a new business area, with its own division and cost center.
    In the test client, the whole process of creating requisition, PO, goods receive, cancel goods receive (return to vendor), create sales order, delivery and goods issue went well.
    But, today, when one of my users tried to cancel goods receive (movement type 102), the following error message was displayed:
    KMXX/KM11 CTR belong to business area M110 not M140.
    Since the PO was created for a stock item, there is no account assignment, so I am wondering if I have missed out something in configuration, especially in defining account assignment for automatic posting? Can anyone help?
    Thank you very much.
    Anisah

    HI,
    There should have been some changes done in the system after thr initial docs were created.
    Please ensure that the said cost centre of interest is assigned to the appropriate Business area.
    The error seems to be an invalid combination of the Business area to the cost centre.
    If not then please maintain the same.
    Hope this helps.
    Regards,
    Prasanna
    Award pls if helpful.

  • Change the cost center in asset master AS02

    Dear Members,
    I need to change the cc of an asset in the asset master, so I read the other discussions and followed the steps AS02 and time dependent, then create new interval. But the CC is locked it cant be modified. The validity of the CC is starting form year 1900 to 9999. Should I change the validity of CC both existing and new one using t-code KS01 first?
    If yes, then what validity date should i put as i want to use both cc, since other expenses are posted to both cc.
    Please help
    Thanks
    Jaidev

    hi
    you may go to asset master >> time dependent tab (AS02) and update new Cost center with date from. only thing is that you cost center should be valid and not locked.
    Regards
    Jomon

  • Can we change the cost element after posted some expenditures.

    Hi friends,
    My client ran the depreciation upto jan 2009, afterthat we found the depreciation GL's are not set the cost element.
    so the Depreciation values were not posted cost center wise, now we want to change the GL's cost element , is it possible, if it is possible what is the steps.
    with regds
    muthuraj.g

    Yes,
    You can create cost element and interface depreciation posting to CO. For missed Depreciation, manual posting in CO can help to reconcile with FI.

  • Change in the cost center group

    Hi,
    Can we change the cost center from one cost center group to another group, when there are some postings in the cost center? If yes, how to go about it?
    help me out

    Yes you can!
    If you are planning to change within the standard hierarchy, Goto OKEON, drag, drop and save.
    Or you can go to KS02 for the cost center, in the basic data, you can give the new cost center group under the hierarchy area.
    If it is just non hierarchy cost center group, then go to KSH2 enter the old group, select the cost center, delete save, then go to the new cost center group and include the cost center.
    It does not matter whether it has been posted or not. It is just a grouping. But caution must be exercised. and there shall be a valid justification for doing so. Because the cost center may be used in various cycles. So better to check where and all the cost center is being used and then do the change.

  • Change to cost center in time dependent data. Can I rerun depreciation YTD?

    I need to change the cost center in October (Period 10) Period 9 and prior are already closed.  I thought that since I put the Interval for the new cost center as 1/1/11 that it might do and adjustment in October reversing the depreciation posted for the old cost center and put the YTD depreciation in the new cost center, but it did not.  it only posted the current month depreciation to the new cost center.  Is there any way to do this?  Thank you very much.

    Hi.  Thanks for your reply.  I went into the ABAA screen, but I am afraid to process this transaction because I do not understand what is going to happen.  I cannot find any documentation that explains this.  I have already changed the cost center on the asset and run depreciation.  It posted the current month depreciation to the new cost center, but it did not make a correction to the prior periods.  I am not creating a new asset, i just want to reclass the prior months depreciation (in the current year) to the new cost center.  In case it will help I provide some details:
    Asset acquired 5/1/11 Depreciation posted to Cost Center A From May - Sept $1,796.06 per month x 5 = $8,980.30
    Before posting Oct depreciation, I went to Master Data - Time Dependent - and changed the cost center as of 1/1/11. So I now have two intervals: From 1/1/1900-Cost Center A, and From 1/1/11 - Cost Center B. I then ran the regular depreciation for Oct. It posted Oct Depreciation of $1,796.06 to the new Cost Center-Cost Center B.  My total YTD depreciation is now $10,776.36, but it is split between two cost centers.  I need to move the depreciation from Cost Center A to Cost Center B for the prior months.  If it was a Journal Entry, I would do it as follows in the month of October, so my YTD numbers would be correct.
    Debit Depreciation Cost Center B   $8,980.30
    Credit Depreciation Cost Center A $8,980.30
    Then when I run my October numbers it would show zero depreciation in Cost Center A Year To Date (and negative 8,980.30 in month of October)
    If i follow the steps you propose, what would be the result?  Thanks so much!

  • Regarding Change in Cost Center after Advance payment

    Hi,
    PO is created, against that PO Advance payment is given and payment is given to Vendor of advance.
    Now query is that the while generating PO wrong cost center is entered, and user want to change that.
    How we can solve this problem ?
    Regards,
    Akshata

    Hi,
    You cannot change the cost center in down payment entry, but can be changed in PO.
    Then again you have to use KB61 to do transfer posting from one cost center to another, since this will only post an internal CO ducment to adjust the balances from one cost center to another, assuming that CO update for Controlling is active in your system.
    Use down payment accounting document no in KB61.
    Regardz,
    Srinu

  • How to change in cost center?

    Can some body please explain:
    How to change the depreciation expenditure charged from one cost center to another? Since the depreciation has been posted for the 2 months that have been closed, is it possible still to repost line items?
    To change the cost center thru KB61, is accounting document necessary?

    thanks for your reply!
    Actually the cost center is being changed from Aug onwards ,so the Depn posted to the old cost center for July needs to be reposted to the new cost center using KB61 taking the reference of accounting doc from KSB1 for the old cost center.
    But when i am using KB61 to repost the depn , system gives the error message " Transaction Repost CO Line item has been locked"
    ie July period is already closed.
    I do not have the authority to open the closed periods and repost. Is there is any other way?
    Also, once the reposting is done, Cost center can be changed for the assets thru AS02 so that system automatically posts the accumulated depn to the new cost center

  • Table for change in cost center in Kb61

    Dear friends,
    I changed the cost center using t code KB61, From which table i can get the details of change in cost center
    Rgds
    Madhavan

    Hi,
    KB61 will post the document with the change from old cost object to new cost object in CO documents, so you can check the following tables for this posting.
    CO document Header: COBK
    CO document items:COEP
    CO summary table:COSP (or COSS)
    best regards, takashi

  • Is it possible to change the cost centre assigned to profit centre?

    hi all ,
    We have a requirement to change the old profit centre which was assigned to cost centre , with the new profit centre ... is it possible ? ... is there any problem in doing so ?... what will be the effect of this ? ...
    thank u ... in advance

    Hi,
    u can only change the cost center assigned to profit center before any document posting,
    If even single document is posted or any other postings has done then u cannot change it.
    Regards,
    Pavan.

  • Automatic change of Work Center during Confirmation.

    Happy New Year to all!
    Just want to ask if anyone of you encountered the scenario during confirmation in which the backflushed work center was changed. The user claims that they did not do any changes during confirmation nor did they change manually the order itself. The confirmation happened last December and they only noticed it this month when they were checking the reports.
    I did not configure their system so that they can change the Work Center during confirmation. By default, the work center is grayed out during confirmation.
    Hope to hear from some of you soon!
    Thanks and regards,
    jLmendoza
    Edited by: John Luis Mendoza on Jan 4, 2011 3:15 AM

    Dear
    If your production order operations are re-scheuled and dispatched after Capacity Avalaiblity check in cm21/cm22/cm31 etc  , then during the dispatch of operation ,  you have option to change Work Cnetre , time , date based on the selection option in Startgy profile (CM31/CM21-Enter the WORK CENTRE /Order )  and check wether work centre is changed.
    One more option may be in Order Change in CO02-Operation Overview -Operation -Work centre -Here user may change the Work Centre .
    If you have Order Change management active then you can trace the same .
    Refer : Production order change history
    Otherwise , there is not such confirguration in SPRO where work centre can be changed automatrically during confirmaiton because it will grade out based on the ste of confirmaiton default screen in OP00.