Including down payment made to vendor in the internal order

Hi all
My requirement is like this.
We use IM and IO(Capex orders) for procuring and capitalising assets. We are able to assign all the costs of procuring assets (both APC and incidental expenses to the internal order). We use purchase orders and assign the internal order while raising purchase order.
Sometimes we do make Down payments(advances) without raising purchase orders. My question is how to include this down payment made in the internal order. We cannot assign any internal order while making the down payment. But, can we include this down payment made to vendor in the internal order(commitment) while making down payment or after that.
FYI:I came to know that there is some functionality in Controlling (Project systems) where we can assign the down payment made to the internal order after making payment.But, i do not know how to do that.
Pls somebody reply me.
Thank you very much in advance.
Regards,
Vishnu
VST-IT.
Pls somebody answer my query.

The functionality is available in Controlling. I dont know about PS.
I need to know how to do it.
Regards
vishnu
Pls anybody suggest me on this issue.

Similar Messages

  • Ageing analysis for the down payment made to vendors-reg

    Dear Gurus,
    Can anybdoy  explains my  how to do  ageing analysis for the down payment made  to  various vendors.
    Thanks
    C.M.SATHISH KUMAR.
    [email protected]

    OK
    Config t code is OBDF
    Select AP view and due date analysis.
    You need to create a variant for the field BSIK-UMSKZ in program RFKRRE01 which is the program for Vendors for due data analysis.
    In the config you need to make sure create evalution is ticked.
    You then need to set up a variant in program RFKRRSEL, for Vendor analysis, it should be called SAP_VARI.
    Once all of that has been set up, you need to schedule a job to run for RFKRRSEL daily.
    In terms of accessing the programs you need yo use t code SE38.
    and to schedule a job use t code SM36.
    Hope this helps.
    Please award points.

  • Steps to cancle Purchase order after down payment made to vendor ?

    Dear Group members
    Warm greetings !!!!!!
    One of my user made down payment to vendor on the base of Purchase order issued, now the vendor is not able to supply the goods & finally (Returned) refunded the amount & canceled the PO
    How can i process this in SAP
    As in Purchase order, history for Down payment is reflected. Transaction code ME23n
    Finance  don't want to reveres  the down payment made which is made in the month of Jan & cleared from bank a/c
    Pleas advice some me with some other solution
    Thanks & regards IN advance
    Regards
    Shamul heq

    Hi ,
    Clear the advance payment made with the incoming payment from Vendor. this wil make the down payment at PO level Zero you can close the PO after that..
    try out the same in test system and move to production after that.
    rgds
    Murali

  • Payments made to vendor against the PO should appear in PO

    Hi
    Thanks for the reply
    is there is any possibliy so that i can see the vendor down payment and the other progreesive payments made to vendor. Also i want to link the payments made to vendor i.e what all payments is made to vendor aganist the PO should appear in PO in the same fashion as downpayment appears.
    regards

    Thanksfor reply
    But if i am not doing the progressive payment thru downpayments but thru other trancation then how this will be shown.Another point of concern is that if i am doing the  payments F-53 then will i can get the downpayment history from for a particular PO .This is required as finanace guy wants to know how much advance and progressive payment i have made to my vendor against particular PO .
    Need your help and suggestion
    regards

  • BP - Vendor account balance to include down payment made

    Since advance payments to suppliers are posted through AP Down payment module the vendor account gets squared off and does not reflect any debit balance.  So arrive the correct balance in the vendor account one should check two accounts i.e. the AP down payment account and also the vendor account. 
    Is there a way take a report which reflects the advance paid as debit bal to his account (by ignoring the AP down payment invoice booking but instead retaining the advance paid against the AP Down payment invoice).
    Rgds
    Srividya

    Hi,
    To show the debit balance paid in the vendor account make the advance payment entry from the outgoing payment form by using payment on account option. also you can link this payment once you receive the A/P invoice.
    Regards
    Datta Kharat

  • 1099 Report doesn't include Down Payments

    Hi,
    While running 1099 report we figured out that it is not including down payments made to the vendor.  Can anybody please tell me if there is a configuration required for this?  We are on v4.7.
    Thanks.

    Hi,
    If you are on SAP ECC, now we use the Generic Withholding Tax Reporting program for 1099 reporting (Program RFIDYYWT).  It has selection fields for Special GL transaction. Specify the special GL indicator for downpayment in the seletion field and the down payment document should be included in the 1099 report.
    If you are on SAP 4.6c, and using RFW1099M, go to Dyanmic Selection and you will have special GL indicator selection available in Dynamic Selection. Select the relevant Special GL Indicator to include down payment in 1099 report.
    Hope this helps.  If this is useful, pls. award points.
    With Regards,
    Chirag

  • Down payment made & down payment received

    Dear sir,
    Can you tell me the difference between down payment made and down payment received, and give me some examples.
    Thank you very much.
    Faithfully,
    Hangvt

    Hi,
    Down payment is nothing but advance payment..
    sometimes you can make the payment inadvance(that means you have given amount before you receive the goods) and sometimes you will receive the advance payment from customers(you will take amount before you sell the goods and delivered to his premises).
    At the time of receipt Down payment
    1.Down payment request                          - F-37
    2.Down payment received from customer   - F-29
    3.Down payment clearing                          - F-39
    At the time of making Down payment
    1.Down payment request                          - F-47
    2.Down payment to vendors                      - F-48
    3.Down payment clearing                          - F-54.
    Down payments are special gl items and represented by"A"
    Hope understood and you can assign point if you are cleared.
    Thanks,
    Vasu..

  • How to find Down Payment document with vendor details from AW01N

    Hi,
    I am trying to do partial settlement in KO88, for AUC to Fixed Asset. While running the T Code I am getting the following error message.
    Down payment to recipient 100620 0 area 01 amount   13,181,454.04 not cleared
    Message no. AW605
    I went through many threads for this issue and I am trying to clear the downpayment in F-54. But I am not able to find the Vendor details to whom the Down Payment was done, neither the dosument number against which the downpayment has to be cleared.
    I tried finding these details in AW01N. I could find the amount reflecting in the Planned and Posted tab in the first section.
    But was not succesful to find the documents and vendor details from there.
    In the second section in Planned Tab, I am finding some transactions. There I am finding Down Payment mentioned. When I double click on Down Payment in AW01N, I am taken to the document which is a clearing of Down Payment. You can see the below entry.
    81008100
    Fixed Assets Interim
    1,049,371.84-
    30300100
    000000900000 0000
    2,538,367.44
    30520000
    Clg Cap D-Pmts-T-Ast
    2,538,367.44-
    30300100
    000000900000 0000
    1,049,371.84
    30300100
    000000900000 0000
    101,948.00-
    30520000
    Clg Cap D-Pmts-T-Ast
    101,948.00
    Now, how do I know which documents to be cleared to which Invoice and the vendor details.
    Kindly help me with this issue.

    Hi,
    Thanks. Kindly suggest now, how to find the documents and vendor details from there.
    When I double click on any Down Payment in AW01N, I am taken to the document which is a clearing of Down Payment. You can see the below entry.
    81008100
    Fixed Assets Interim
    1,049,371.84-
    30300100
    000000900000 0000
    2,538,367.44
    30520000
    Clg Cap D-Pmts-T-Ast
    2,538,367.44-
    30300100
    000000900000 0000
    1,049,371.84
    30300100
    000000900000 0000
    101,948.00-
    30520000
    Clg Cap D-Pmts-T-Ast
    101,948.00
    Now, I want to clear the down payments in F-54, but how do I know which documents needs to be cleared to which Invoice and the vendor details. Since I am getting error while executing KO88 AUC transfer to Assets.
    Down payment to recipient 100620 0 area 01 amount   12,832,161.41 not cleared
    Message no. AW605
    Diagnosis
    All downpayments were not cleared for the asset under construction for the receiver 100620 0 in area 01. An amount of   12,832,161.41 was not cleared, or too much was cleared.
    You can only completely transfer an asset under construction if you reverse the down payments in the current fiscal year beforehand.
    Procedure
    Clear the downpayments that you want to settle to receiver 100620 0.
    Check screen shot.

  • Down payments to different vendors through app (f110)

    hi frineds how can i make down payments to different vendors through APP in (f110),  where should i configure this settings ? pls help me with t.codes and paths..

    SETTINGS:
    Usually "F" is used for DPR (DOWN PAYMENT REQUEST) and "A" is used for DP (DOWN PAYMENT).
    "F" has as target indicator "A" by OBYR transaction.
    POSTINGS:
    By F-47 You post a DPR.
    During the DPR posting, you have to insert the Target indicator; usually A and the DPR will report F as special indicator. ( Bcoz DPR(F) will target DP, that is A)
    Into FBZP --> All company codes --> Sp. G/L transactions to be paid --> if you insert F, the System will take the DPR previously posted during the F110.
    But if you posted some DPs, these DPs will not take in consideration by F110.
    ALL THE BEST

  • Imported po has been done and down payment made last F.Y and now want cance

    Please help me for below scenario.
    Our client was created Imported PO and down payment made in last F.Y and now some reasons they want to cancel the PO and create new domestic PO with same PR.
    But down payment was cleared and accounts are audited they don't want to reversal the down payment.
    How it is possible to cancel the PO without reversal of down payment.
    and i reversed the DPR remain down payment is same and tried to cancel the PO line item but it is showing below error.
    Diagnosis
    You have attempted to delete or block an item that is not yet closed.
    An item is regarded as closed if:
    o no GR blocked stocks exist
    o all down (advance) payments made to date have been taken into
    account
    o the quantity delivered is the same as the quantity invoiced
    o all delivery costs have been taken into account
    o the quantity delivered is the same as the quantity issued (only in
    the case of stock transport orders).
    Please provide me the posible solutions urgently.
    Best Regards
    Ranganadh

    Dear Ranganadh,
    For closing/ cancelling the PO, main prerequisite is "There should be no open transactions against that line item."
    So unless you reverse/ cancel the downpayment, you can not delete the line in PO
    Umakanth R

  • The amount of down payment must be less than the invoice amount

    Hi all,
    Our customers are using SAP 2007-PL15 and SAP 2007-PL41.
    When we want to create a down payment for a sales order, and we want to pay the entire amount of the sales order, including tax, we have to put an amount inthe TOTAL field of the Down Payment window since by default, the down payment amount is the total of the invoice before applying tax.  The DPM is
    higher than 100% (strange but I think it's normal since the down payment is not planned to take the tax in consideration).
    Then, we create an incoming payment for this down payment. It's ok.
    Then, we create an invoice based on the sales order we have paid with the down payment. It's impossible to use the down payment for the invoice... why that ? We receive the error 'The amount of down payment must be less than the invoice amount'. This causes big headaches to our customers !!
    Could you explain us what to do please ?
    thanks,
    Luce

    I'm very sorry, I have a similar question in dealing with AP Down Payment Request Linked to AP Invoice,  my case like this:
    1. I created 3 AP DPRs,their amount are each 100,000 RMB(for example, their document number are 10,11,12). then do the outgoing payment fully paided.
    2. I created a AP Invoice with the amount 150,000 RMB(for example, this AR Invoice document number is 5). I use the buttom"Total Down Payment",and selecet AP DRP No.10 and 11. When I click the buttom"Add",an error shows:
    The amount of down payment must be less than the invoice amount
    and I don't know how to continue.....
    Many Thanks
    Kam
    (PS:My English is poor,forgive me please. Shall I Speak in Chinese? then I can describe this question more clearly.)

  • Down payment problems Customer/Vendor - Assign default cost elements

    Helo Gurus,
    ive tried to execute TC: F-29 Customer and F-48 Vendor down payments.
    I enter all the data needed and additionaly Internal Order.
    Then i get a message saying:
    Maintain default revenue element in controlling area 5000
    Message no. FI661
    Diagnosis
    CO down payment update is active in controlling area 5000.  You must therefore maintain a default cost element and a default revenue element for down payments.
    Procedure
    Maintain the default cost elements for down payments for controlling area 5000 in the Project System implementation guide.
    The maintenance is done in TC: OKEP (project system)
    I created two revenue Cost elements and tried to assign them there, but it says CE are nore primary CE.
    I changed it from revenue to primary, then it says that CE isnt revenue...
    weird stuff
    What could be the problem?
    Regards
    Laurynas

    Hi,
    Please refer to SAP Note 388843.
    Regards,
    Srinu

  • Down Payments to Stcok Vendors

    Hi,
    I need to create a down payment for stock vendors, If I create an invoicing plan but then I get this error saying "Invoicing plan not possible in case of GR-based invoice verification".
    My scenario is that do make down payments to Stock vendors based on POs, is there any other way of nadling down payments for stock vendors.
    thanks

    Hi Rose,
    For the purpose of Down payment to stock vendor,there is no need of any invoice plan......
    General process in industry is........
    Step 1: Create  a down payment request by Purchse dept in F-47. System treats this payment request as a statistical item and there won't be any financial impact....
    To have a better control generally, purchase people creates this Down payment request against the Purchase order.
    Step 2 : Make the down payment in F-48 against the Down payment request. In this way we can have a control on down payments....
    Now cash or bank will be credited and vendor would be debited.
    Check in T code F-48 there is a small tab button on the top of screen to select the D P Request.
    Step 3 : Post invoice in MIRO
    Step 4:  Adjust the Down payment in F-54.
    Thanks & Regards
    Ravi C

  • Down payment for Stock Vendors

    Hi,
    I need to create a down payment for stock vendors, If I create an invoicing plan but then I get this error saying "Invoicing plan not possible in case of GR-based invoice verification".
    My scenario is that do make down payments to Stock vendors based on POs, is there any other way of nadling down payments for stock vendors.
    thanks

    Use transaction F-48 to create the down payment for Vendor.
    than once you post the invoice it will know off the downpayment amount when the FI people clearing the invoice you posted.
    You can post down payment aginst vendor with PO also.

  • Down payment made no due date

    HI all,
    is it true that if we post down payment made (F-48) there will be no due date and no symbol for it in FBL1N?
    thank you

    Hi
    F-48 is for actual down payment made. Where as when you create a DP request in F-47 then you mention the actual due date for making the payment. But when the same is directly done in F-48 why the due date is required. Also it would reflect as spl Gl transaction in FBL1N