Intergation: cProject  + Earned value + Project System + Accouting

Hi,
I'm trying to intergrate cProject & Project System & accounting. currently I'm facing some problems:
PS is generated automatically from cProject (Automatically, Task base, WMS, level = 99).
I don't know how to entry actual start date for each WBS. so POC is zero. ==> BCWS, BCWP is zero too. I think actual start date have to be determined by cats or confirmation from cProject but It is not true now.
can anybody help me?
Thank you very much
Long Nguyen

Dear Long
I'm afraid that u may have to manually enter the actual start of the respective WBS element, as SAP works on the principle - actual start of the subordinate activity can be different from the actual start of the WBS Element.
Regards
Murali

Similar Messages

  • CProject & Earned Value progress

    Hi,
    I've seen the earned value report in Evaluation of cProject, but all values such as BCWS, BCSP, ... are zero.
    can anybody share with me documents of calculating earned value in cProject?
    Thank you verymuch
    [email protected]
    Long Nguyen

    Hi Long,
    To be honest, I have never tested the functionality with POC value myself. 
    But the evaluation of cProjects object link is to pull the values from the ERP backend system and display it. The core logic, how to determine such values, is still 'only ' available in the ERP backend system. A similar case is to evaluate the plan, actual costs & budget from the R/3 linked objects. All the information are pulled from the ERP system.
    P.S: Which evaluation do you use?
    Kind regards,
    Zhenbo

  • Difference between SAP cProjects and SAP Project System

    Hi,
    SAP already has a solution PS ( Project System ) for managing the projects in an Organization.
    When there is a solution already existing then why did SAP come up with a new solution cProjects ?
    Can any help me in understanding the main differences and advantages between cProjects and PS ?
    Thanks and Best Regards,
    Priyatham

    Hi.
    I have copied an SAP text below which sets PS, cProjects, (x)RPM and PPM into context.
    In the ninties, the Project System was developed within SAP R/3 to provide a powerful application with full integration into logistics and financials.
    Target groups were industries such as engineering and construction, automotive, high tech or utilities with focus on project manufacturing or large maintenance projects.
    Later on, the need for more flexible and easy-to-use tools supporting the new process methodologies, phased-based approaches, quality gates, and so on, emerged. SAP developed Collaboration Projects and Collaboration Folders (cProjects Suite), which takes these new requirements into account and provides extensive features to collaborate with internal and external partners using a HTML-like interface and Web Application Server technology.
    Thus, cProjects was able to address to a broader range of industries, such as service providers, offering a high degree of visibility and flexibility to support various scenarios from product development to consulting projects. Nevertheless, cProjects is seen as a complementary product to Project System, not as ist successor!
    It always depends on the scenario that a customer wants to cover, which application is the best choice.
    As another matter of fact, combinations of both are also possible.
    In addition to this, the new generation of composite applications was born and SAP xApp for Resource and Portfolio Management provides excellent capabilities to align operational project management with strategic portfolio management.
    The latest developments bring all these three applications tighter together and offers a comprehensive solution for project and portfolio management by covering logistical, financial and human resource aspects and addressing the needs of all stakeholders throughout the entire organisation.
    However, xRPM capabilities are not only restricted to project portfolios but can be leveraged to control all kind of portfolio items.
    Regards / Anders

  • Setting Up Earned Value Reporting in Project Server 2010, Using Hours Not Dollars

    Hello All,
    Are there instructions for setting up Project Server 2010 for Earned Value data capture and reporting?  I'm not certain that we are capturing the correct data to report EVM (i.e., Physical % Complete), and I was unable to find any videos on YouTube.
    Also, I noticed that Project Server 2010 defaults to reporting EV in Dollars.  Can we set it up to report in Hours instead?
    Julie  

    Hi Julie,
    If you allow to jump in to complement Dale's excellent reply and comment some of your concern...
    5. The status date is a fundamental parameter while talking about the EVM (it is ANYWAY a key setting for tracking projects with MS Project). The EV field will take into account actuals up to this date. Meaning that if your project plans have been updated
    by the PM on tuesday and you are running the analysis on friday, you set the status date to tuesday and the uncomplete work between tuesday and friday will not be considered as late work since you are running the analysis as of tuesday. The status date can
    be set from the "project" tab either in the project information dialog box or directly in the project tab, status group.
    6. MS Project proposes 3 EVM tables by default. A table is a predefined set of column which composes a view, together with a Gantt chart or a timephased grid. If you go to the view tab, click on "tables" then "more tables",
    you will find EV, EV cost indicators and EV Schedule indicators tables which will display the out of the box EVM fields calculated by MS Project based on the costs, actuals, Baseline, status date.
    Then about the cumulative data, you might be refering to S-curves which are a representation allowing you showing the cumulative values of the EV. To do that, you'll have severals ways:
    Use the cumulative calculated field in the visuals reports
    Create
    Dashboards from the report tab using the cumulative data (actual, Baseline, cost)
    Create
    MDX mesures in the OLAP cubes for cumulative data and create excel reports
    Develop custom SSRS reports
    Buy a 3rd-party addon
    Finally please let me give you an excellent reference for the EVM in MS Project with EPM Central blog articles:
    http://www.epmcentral.com/msproject/evintro.php
    http://www.epmcentral.com/msproject/evprereq.php
    http://www.epmcentral.com/msproject/evterms.php
    http://www.epmcentral.com/msproject/evexplain.php
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Project system tables for getting baseline and forecast values

    Hi all,
    I am new to Project systems and currently i am having the PS report.
    I need to pick the following values based on project definition (proj-pspid):
    --> historical baseline values like:
    1) versions
    2) created by
    3) created on
    --> historical forecast values like:
    1) versions
    2) created by
    3) created on
    Can you please let me know the tables and fileds for fetching the above values.
    Regards,
    raviraj.

    Hi,
    IMAK Appropriation requests - general data
    IMAV Appropriation request variant
    IMPR Investment Program Positions
    IMPU Texts for cap. inv. program positions
    IMTP Investment programs
    IMZO Assignment Table- CO Object - Capital Investment Prog.Pos.
    PMCO Cost structure of maintenance order
    PRHI Work Breakdown Structure, Edges (Hierarchy Pointer)
    PROJ Project definition
    PRPS WBS (Work Breakdown Structure) Element Master Data
    Check with tables

  • XRPM, cProjects and Project Systems link in BI

    Hi Guys,
    We are implementing a RPM solution in our BI 7.0 system. We have a requirement where we need to link RPM data with cProjects(Project, Task) and Projects Systems (Status, WBS Elements, so on) data.
    Could some one give me the links/documents related to linking the above objects.
    Thanks in advance
    Srinivas.

    Hi Neelam:
    Check Project system tables like PROJ etc and create a View for the fields you want.
    Use this View as your datasource to extract data.
    Thanks,
    Jagadish B V

  • CProjects - Project Systems Linking and other features

    Dear All,
                  I need inputs on how to integrate cProjects with Project Systems. Also i need information on the what are all the information we can integrate between these two.
                  One more important thing is i am seeing the Services, Details Data and Controlling links in My cProjects system. Where as i found Account Assignment, Costing links in one screenshot of Documents. And both are for cProjects 4.0. Why this difference is showing up
                  And one generic question is, what is the requirement for these kind of scenarios. And pros and Cons of both the systems.
    regards,
    rajesh.
    Edited by: Guest on Feb 14, 2008 5:59 PM

    Hi Srini,
    Thanks very much for the links. However, I've already gone through the standard documentation in SAP and they are a bit too high level/vague for me. I have considerable experience in xRPM, cProjects Suite and have good grasp of project management concepts, tool and techniques. My knowledge of PS is somewhat limited though.
    What I am specifically looking for is what type integration options and scenarios are available. For example, cProjects can have phases and tasks defined. How would these integrate with for example WBS elements and networks in PS? What are the things you would do in cProjects and not PS and vice versa? Hope my question is clearer now.
    Appreciate any further information you may have on the above.
    Thanks,
    Lashan

  • Sales Order Vs Project Systems(CNS0--Vl02n--VF01) Value&Status(Partial Disp

    Dear All,
    I need your suggestion in the following scenario:
    This is the Partial Dispatch scenario.
    Here in the Sales Order, we are attaching the FERT; Here we will give the total price of the FERT in Conditions level;
    In the Project Systems level, we are attaching HALB items of FERT.
    Now the flow will be We will deliver each HALB from PS through CNS0; Then by going to VL02N and do PGI; By reffering to these Deliveries,Billing(VF01) will be done for each HALB; In Billing(VF01), Pricing will be given for each HALB (since for each HALB bill will be raised seperately);
    The issue here is that I need to know whether I can have a check so that Cumulatively the Billing Value of all the HALBs is in Correlation with the FERT value in the Sales Order;
    Here I am creating the Bill with reference to Delivery(CNS0-Vl02n) and not with ref. to Sales Order.
    (ii) Also there is one more issue in the same scenario.
    Here the Sales Order status will be In Process . By reffering to the Sales Order I am just raising the Proforma Invoices for Down Payment, against Design/Engineering.
    I need to know how I can make Sales Order staus  as Complete.
    I need your suggestion to solve these issues in a better way.
    regards
    somnath

    Bom dia Marc de Ruijter,
    Não dá para ler sua thread, mas imagino que seu validador esteja desligado.
    No GRC vá em SPRO --> SAP GRC Nota Fiscal Electronica --> Configure System Response for Each Tax Number (CNPJ)
    Para ligar/desligar o Validador basta clicar no check box na coluna Validation.
    Observação: Para correto funcionamento do GRC deve-se sempre utilizar o validador ligado.
    Após isto refaça seu teste, é provável que você receba um erro de validação para a NF-e. Veja em GRC Web monitor -> NFe Detailed View -> Validation History.
    Atenciosamente,
    Fernando Da Ró

  • CProject / Project System / Project Solution Manager

    Hi Everyone,
    I am very much new to SAP and doing my first semester in Masters of ERP (SAP). I am very much interested in project systems basically Implementation, Reporting, Time Management, Analysis etc… I wondering if any one can help me how to and where to start it’s quite confusing when these forums talk about cProject, Project Solution Manager and Project Systems please give some info like books, links or documents where i can develop my skills especially practical examples.  I really appreciate al of you guys time and patience.
    Thanks
    Durga

    No worries, found it.
    Thanks anyways,
    Regards
    MK

  • CProjects & Project System

    Hello Friends,
    I want to use the projects that created in Projects Systems(PS) in cProjects and also the vice-versa.
    Could you tell me the procedure to do this?
    Thanks & Regards,
    Senthil.

    For creating project from PS to cproject use the following method
    What you can do is Create a cProjects Project usinga Badi in PS on save.
    where you can use FM BAPI_BUS2172_CREATE to create Project.
    Also when you make changes to PS project use Badi on save to transfer the changes to cProjects projects.
    You can use Function modules like:
    BAPI_BUS2172_CHANGE
    BAPI_BUS2173_CHANGE
    BAPI_BUS2174_CHANGE
    BAPI_BUS2175_CHANGE
    and so on
    vetrivelan.

  • Earned Value Analysis in cProjects

    Hi,
    Does anyone know how to do progress analysis using earned value in cProjects? Please help.
    Thanks,
    Thang

    Hi,
    Does anyone know how to do progress analysis using earned value in cProjects? Please help.
    Thanks,
    Thang

  • Linking of cproject & project system

    hi guru
    Can somebody please let me know the the Configuration steps & the entire process of linking Projects created in Project Systems & cProjects? How can we view the Projects in cProjects which we create in PS and vice versa? Waiting for your reply at  earliest.

    Hi
    See this help data
    http://help.sap.com/saphelp_cpro31/helpdata/en/c5/923e4045796913e10000000a1550b0/frameset.htm

  • Earned Value with Project Web App 2013?

    Hi folks,
    Earned Value in Project Client is quite fine, the choice of calculate against actual or status date is a nice feature. But using Project Web App I lack the option of setting the status date - is EVA in Project Web App 2013 really restricted to the actual
    date? Or is the status date set automatically by approved task updates?
    Thanks
    Olaf

    Hi Olaf,
    Unfortunately the status date cannot be set from PWA, and there is no automatic update behind. The intent is that the PM updates the status date and the tasks in MS Project Pro and the team members and executives can consult EVA from PWA.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Change Table Fields in "Costing" in with Project System (PPM 5.0)

    Dear Gurus;
    I need to know, how can I change fields in "Costing" with Project System (Project Management in tab name "Accounting").
    The integration works well, but I need to view the values of: Actual, Plan and Commitment.
    In the Standard way, just only can see the Plan (with the colum "Costs").
    Please, help.
    Best regards.
    Mariano.
    Edited by: Mariano Sabiche on Apr 27, 2011 3:17 PM

    Hi Mariano
    The particular screen you are referring to will only show the planning on Easy Cost Planning due to the labour costs and revenues planned on the cProject.  You can use the services&deatil on the assignment - click on the WBS assigned to get the detailed list of services for the assigned WBS element.  You can then click on Detail Data to get detailed data on the assigned WBS element.  If you want a report with all the data, best use the BW cubes for that to combine cP and PS data.
    Hope this helps
    Regards
    Duan

  • Business Content Project System

    Hi Friends,
    Can any body provide the link for   Businees Content for Project System module in BI 7.0?
    will assign the points.
    Thanks in advance.
    Regards
    SAP

    thanks for ur reply. i assigned the points.
    I can see lot of Infocubes are duplicated like
    Dates (Identification Using External ID) and Dates (Identification Using GUID)
    Earned Value (Identification Using External ID) and Earned Value (Identification Using GUID)
    what is the diffrence bet ween External ID and GUID.
    Cleint will use two types oe he can choose either of one?
    Please provide some use ful documents  PS Extrators.
    I have been assigned to PS Module in BI 7.0
    I am extractind data from PS module.
    Is there any diffrences extracting data from Ps system compare to LO and FICO modules.
    Will assign the points.
    Thanks in advance.
    Best regards
    SAP

Maybe you are looking for

  • G//L Report Displays NO Budget Data

    Hi Friends, In one of my G/L report, i need to display Actual Data & Budget data. Actual Data is coming from 0FIGL_C01 cube and Budget data coming from Flat File. When i execute the query based on G/L Account, i'm getting all the data both for the Ac

  • Convert from PSE10 to Lightroom - metadata concerns

    After one too many frustrations with PSE, I've been looking for an alternative program.  I don't care about editing - metadata (Organizer type features) are my focus.  I looked at a few non-Adobe programs - a big problem with them is I can't import m

  • Exported JPEGs Distorted in Shadow Areas

    I own a Nikon D7000 and I shoot 14bit RAW. In Lightroom 3.3 the preview images were distorted, only in development mode the images were fine. I reported to Adobe on this and they seem to have fixed this issue. In Lightroom 3.3 -- and still in 3.4 --

  • How Can I get personal java example source?

    i want to know how to program with p-java. How Can I get personal java example source? and where can i get them?

  • Oracle Provider connectivity issues in 2008 server (for Standard Users)

    Hi We're using Windows 2008 R2 server and installed a VB application. The application has the capability to connect to Access, SQL Server or Oracle Datbase using OLEDB providers. When I login as "Administrator", the application connects to all three