Internal Orders versus Project Systems

Hi
My client is currently using WBS elements for capital projects.   Project System is not in scope; thus, we are trying to decide whether we should bring it in scope with limited functionality or use internal orders for capital projects. I'm writing a position paper describing comparison of using project system versus internal order. Can any one of you please help me in providing the differentiating points. And also can you please give a description of capital projects.
Thanks a lot in advance.

Hi,
To begin with Internal order is a cost object like the WBS elements and activities in the Projects.
For the capital Projects following are the Points that should Favor the PS as compared to Internal Orders:
1. Time planning Possible
2. Resourse Planning possible.
3. Capacity planning and leveling possible.
4. Cost planning is possible in detail.
5. Material Planning possible.
6. Budget planning is possible in detail for the various phases of the project.
7. Cost and Budget monitoring is possible at the various phases in detail.
8. For the long term projects the Cash management is possible.
9. Revenue Planning and monitoring is possible in details.
Above all the PS is more flexible in handling all the project related issues than Internal order.
Now its upto one to use the functionality of PS to one's requirement.
In short PS module is like an Expert Doctor than a general physician.
Hope its useful.
Reward points if useful.
Thanks..

Similar Messages

  • Internal Order vs Project System

    Hello expert,
    as you all know the function of WBS Element, Internal Order and Cost Center are similar.
    My question is what kind of environment that made us decide to us WBS element rather than internal order or cost center?
    Thanks

    Cost Cennter is different concpet from WBS and IO eventhoug all are Co objects. Cost Center is one of the master data for CO while as WBS/ IO is purely transaction data.
    WBS is having integration with most of logistic cycle and modules. In WBS hierarchy concpet for strucute as well as budget is the while as not in IO.
    You decide wether to go for IO or WBS most of the case when you are going from IM. IO is more limited to Controlling and not to logistic trasaction .  I think this is the main difference.
    With Regards
    Nitin P.

  • Open Internal Orders from legacy system

    Hi,
    Is there a way to bring over open projects (Internal Orders) from legacy system into SAP?, especially the way to bring over legacy cost information collected on such projects.
    Would appreciate any help,
    Ram
    Message was edited by:
            Ram R

    Hi
    As such you cannot do this. You download your Legacy system data to an excel sheet and then upload the PO details into SAP using  an LSMW etc.
    Regards
    Dev

  • Sales order with project system

    Hi,
    Is any one can explain for the mentioned scenerio pl:
    In production cost by Sales order, is production / process order will be linked for production booking or always is it best to implement the make to order with project systems - Sales & Process / production order is used as WBS element?
    Also, can u pl. exlain me how to activate the same?
    Rgds
    SMK Ganesh

    Hi,
    Is any one can explain for the mentioned scenerio pl:
    In production cost by Sales order, is production / process order will be linked for production booking or always is it best to implement the make to order with project systems - Sales & Process / production order is used as WBS element?
    Also, can u pl. exlain me how to activate the same?
    Rgds
    SMK Ganesh

  • Sales order in Project system

    Hi All,
    Can u tell me please how can we create  a sales order,Quotation in projects and what are tcodes for that.
    As i am here involved in Capital projects i dont have any idea of customer projects ican u pleease let me know the customizing part too.
    Assured of rewarsd points
    Thanks in Advance.
    Regards,
    Abraham.S

    Hi,
    to create quote from project system there is quite a bit of PS ( project system ) SD integration is required. i will try my best to deliver with whatever time i have right now.
    1. t-code -CKCM - your will define easy cost planning here whihc will be your pricing factor in in sales order.
    2. ODP1- you define DIP profile here you will also define your costing elements here. this DIP profile is attached to sales doc type. and on main menu you will find button that says quotation. click on that. this willd irectly take you to quote and from there u can take it forward.
    I hope it helps u little. Though i know its not enough.

  • Sales Order Vs Project Systems(CNS0--Vl02n--VF01) Value&Status(Partial Disp

    Dear All,
    I need your suggestion in the following scenario:
    This is the Partial Dispatch scenario.
    Here in the Sales Order, we are attaching the FERT; Here we will give the total price of the FERT in Conditions level;
    In the Project Systems level, we are attaching HALB items of FERT.
    Now the flow will be We will deliver each HALB from PS through CNS0; Then by going to VL02N and do PGI; By reffering to these Deliveries,Billing(VF01) will be done for each HALB; In Billing(VF01), Pricing will be given for each HALB (since for each HALB bill will be raised seperately);
    The issue here is that I need to know whether I can have a check so that Cumulatively the Billing Value of all the HALBs is in Correlation with the FERT value in the Sales Order;
    Here I am creating the Bill with reference to Delivery(CNS0-Vl02n) and not with ref. to Sales Order.
    (ii) Also there is one more issue in the same scenario.
    Here the Sales Order status will be In Process . By reffering to the Sales Order I am just raising the Proforma Invoices for Down Payment, against Design/Engineering.
    I need to know how I can make Sales Order staus  as Complete.
    I need your suggestion to solve these issues in a better way.
    regards
    somnath

    Bom dia Marc de Ruijter,
    Não dá para ler sua thread, mas imagino que seu validador esteja desligado.
    No GRC vá em SPRO --> SAP GRC Nota Fiscal Electronica --> Configure System Response for Each Tax Number (CNPJ)
    Para ligar/desligar o Validador basta clicar no check box na coluna Validation.
    Observação: Para correto funcionamento do GRC deve-se sempre utilizar o validador ligado.
    Após isto refaça seu teste, é provável que você receba um erro de validação para a NF-e. Veja em GRC Web monitor -> NFe Detailed View -> Validation History.
    Atenciosamente,
    Fernando Da Ró

  • Re: Internal Order & Project system

    Dear All,
    Please can one give brief explanation of internal Order and Project system.
    1) What is the major difference Internal Order and Project system.
    why some companies use Internal Order
    why some coompanies use Project system.
    Thanks in advace
    Venkat.

    Dear Venkat,
    Internal Order is Sub-module of controlling whereas Project System is entire module in SAP.
    Internal Order will provide information related to cost posted to the order, budget, commitments etc. And in Project system module you can create various projects to analyze company's profitability.
    Substitution between Internal Order and Project system is highly depends upon the size of the Project. Many companies may be using internal order instead of Project in order to trap the cost.
    Project system will provide every minute information pertaining to the project. Whereas internal order will not be able dole out.
    Companies in Real Estate can not substitute Internal Order with that of Project system. Project System module is both heart and brain for Real Estate industry. And companies in other Industries having small value and size of project can use internal order instead of Project system.
    To conclude, Internal Order is narrow concept where Project System is an Ocean
    Regards,
    Chintan Joshi.

  • Internal Order - System Status LKD

    Hi All,
    For an internal order which has system status LKD active, can I mark it for deletion?
    When tried to do so, I get an error message like
    " E BS 013 System status LKD is active (ORD XXX)
      KO 424 Order XXX / Mark for deletion "
    What can be done?
    Thanks ,
    Janani

    Hi,
      if your order is marked for deletion then you can't put it for locked status and it goes other way around i.e. if your order is lkd ,it can't be marked for deletion.
    Reward points if it helps.
    Regards
    Karan

  • Production order-Project system

    Hi
    How can planned order can be converted into production order in project system
    Regards
    Suresh

    Hi
    With manual selection the system lists all the valid task lists that exist for the material at the time of copying and that should be selected according to the selection ID. You can select the required routing from this list.
    Working Without a Routing
    When you work without a routing the system automatically generates an operation. It proceeds as follows:
       If default values have been maintained for the automatic generation of an operation the system uses these values to generate an operation automatically in the order.
       If no default values are specified in Customizing the system generates an operation with the control key 0001 and the operation number 0010.
    <b>If a routing must be selected but no routing can be selected then the system reacts with a termination message and you must carry out order creation again.</b>
    Further information please refer the link
    http://help.sap.com/saphelp_47x200/helpdata/en/b1/c04182439a11d189410000e829fbbd/frameset.htm
    Regards
    Ramakrishna

  • Internal order settlement to G/L account

    Dear All,
    User has created one internal order 650002012 and the settlement profile is created settle to G/L account S882000000. this is a cost element category "1" (Loss on contract cancellation & co).
    In the internal order The Responsible cost center is DA01D89998 (Validation & Eng Admin-St) the profit center for this "DA01".
    In the internal order the Requesting cost center is DA26ZPSHRD (Shared Cost Center for Deltron), the profit center is "DA26"
    in the settlement profile when i double click on the settlement rule, he has assigned the Cost center DA01ZPSHRD (Shared Cost Center for Ko) and the profit center is "DA01".
    But when he execute the T.C "KO8G" the system is showing the error is " G/L account requires an assignement to CO object".
    1. The receiver G/L account has created as a cost element. is this correct?
    2. In the allocation structure do we have to select the "By cost element check box" or do we have to give the secondary cost element in the settlement cost element field.
    Please give the sugessions to solve this problem.
    Thanks and regards,
    Rao.

    It sounds like you are a little confused on how internal order settlement works.  If you want the internal order to settle to a G/L account then you must enter the G/L account number in the settlement rule in the internal order.  To do this, click on the settlement rule button in the order, select category G/L and enter the G/L account number.  In order for you to be able to select G/L as a settlement object the settlement profile you've assigned to the order must allow this.  Check the settlement profile and make sure that G/L account is listed as settlement optional or settlement required.  Also check the allocation structure that is attached to the settlement profile. In the allocation structure you must have an entry under the settlement cost element for receiver category G/L.  Here you should specify a cost element of type 22 as the settlement cost element.
    When you make those settings you will be able to specify the receiving G/L account in the internal order.  The system will then credit the internal order for the settlment amount with the credit posted on the category 22 cost element specified in the allocation structure.  The debit will appear on the G/L account you specified in the internal order's settlement rule.  Normally, the receiving G/L account would not be setup as a cost element.  if you do set it up as a cost element you will need to use an automatic account assignment setting (OKB9) to specify the cost object that it will post to.
    thanks,

  • Internal order - error message M7064 when trying to post GR in MIGO

    Hi All,
    When trying to post GR against an internal order in MIGO system gives error message M7064
    "Document 000009000030   does not contain any selectable items"
    I'm not familiar with CO orders. What shall I check and how? Could you please help?
    In KO03:
    Status of order: REL  DLV  GMPS SETC VCAL
    Allowed transactions: I can see e.g. RMRU, RMWA, RMWE, RMWF
    Isn't it possible hat somehow the status of the order controls it? But how?
    Please help.
    Thanks,
    Csaba
    Edited by: Csaba Szommer on Feb 3, 2010 4:21 PM

    HI,
    I'm not sure if you got a chance to look at the long text of the error message, which shows the possible reasons and procedure to follow. You may want to check if any of these reasons applicable in your case..
    Diagnosis
    The document or document item entered cannot be adopted.
    Possible reasons for this are:
    The document items have already been processed
    (Suggest zero lines indicator set?).
    the document items have been deleted or are blocked.
    the document items have been created for a different plant.
    (for reservations only) movements are not yet allowed for the reservation items.
    (for reservations only) the document items are retrograde components of the order. These are posted using the order confirmations.
    A confirmation must exist for the document items.
    The document items must be released first.
    The document is an R/2 document.
    Procedure
    Make sure your entries are correct.
    If the system has already processed the total quantity, you can set the Suggest zero lines indicator. The system will suggest the quantity zero for the items that have already been processed.
    If you have entered a particular item, cancel the item. If you do not enter an item, the system searches all of the open items in the document.
    If the document is a purchase order, production order or a reservation, you can enter search criteria in the dialog box.
    You access the dialog box by choosing Enter with reference on the initial screen.
    If the document is an SAP R/2 document, you have to cancel it manually by entering the reversal movement type.
    Hope this helps.

  • AUC - Internal order values to upload

    Hi,
    We are doing master data upload.
    We have created BDC to upload the Internal order from legacy system to SAP.
    Can any one please help on how to upload the Internal order Balances (with Asset under constructurion)
    Thanks,
    Sudha

    "Can any one please help on how to upload the Internal order Balances (with Asset under constructurion)"
    What is the actual problem?
    Assuming you want historical balances for each period on your Internal Order. One option is to:
    Post a take-on journal for each month of the Internal Order:
    Dr  P&L Exp (Capex P&L Account) with Internal Order
    Cr 999999 Opening Balance takeon GL (Balance Sheet)
    Run settlement for each month:
    Dr AuC
    Cr P&L settlement account with Internal Order
    Assumes you use a separate P&L settlement account otherwise you need to create a report painter report to report on the P&L Capex account if you don't (i.e. report painter separates settlements and actual expenditures ect in columns for the Capex account).
    Above process is painful if you have many years of data. Otherwise you can pick the end of the prior fiscal year to post the bulk of the Internal Order Value then settle it, carry forward the AuC by standard asset module closing, and then post each period as above for the current Fiscal Year.
    You would then need to exclude these figures from the Trial Balance for the remainder of the opening Balance postings at Go-Live.
    Anyone with a better idea?

  • Closing of old internal order with costs

    Hello,
    we have an old internal order in the system that has to be closed.
    Due to rounding differences / currency conversions there are still costs (balance 0,01) on the order.
    Therefore the order cannot be closed and settlement is not possible as the postings are out of rather old periods and the settlement structures and master data do not fit anymore.
    Is there a possibility to close the order? A special report or something?
    Technically it is closed (TABG) but we need to set the status BABS.
    Thank you for any help & regards
    Britta

    Hello,
    unfortunately the posting that causes the balance is out of the year 2009.
    I changed the settlement rule to "GES" and to a cost center but the system does not want to do the settlement.
    The error says that I have to do the settlement in 2009.
    Thanx for your help,
    Britta

  • Any BAPI or FM to release an Internal Order

    Hi,
    I am uploading internal orders from legacy system to SAP. The default status that is required for these internal orders as released.
    Is there any BAPI or FM to release an internal order?
    Rgds,
    Ashish

    Hi Rau,
    Thanks for your input.
    Well, doing at order type level will set the status released for those orders too which will be created into SAP system.Here we need to set status released for only those which we are uploading from legacy.
    Planned to used BAPI but since for settlement rule i am getting only two fields category & settlement receiver which are not there in BAPI interface structure thus going for a custom program which will use BDC.
    Rgds,
    Ashish

  • Internal Order Reprot name ?

    hi all,
    Is there a report in SAP that would give me a list of active Internal Orders,
    Also, I need the Profit Center to appear in the above requested report.
    Regards
    Kumar

    Hello,
    Please check if there are any standard reports available at
    Controlling -> Internal Order Accounting -> Information Systems -> Master Data
    Otherwise,
    Go to TSTCT table in SE16
    Language EN
    Tcodes S_ALR*
    Maximum Number of hits 99999
    Now Ctrl+F (Find)
    Order / master data etc.
    Hope you will find the relevant tcode.
    Regards,
    Ravi

Maybe you are looking for

  • Vendor Line Items

    Is there any std BAPI or FM to get Vendor Line Items? Is there any database Table which shows all  Vendor line items (open and cleared)? Note : table BSIK shows only open line items. Thanks in advance. Points will be rewarded.

  • How can i disconnect my iphone from my ipod?

    im using same account for my iphone 5 and ipod. now i want to sell my ipod to my friend and want to disconnect it from my apple account. how am i suppose to do that?????

  • Ipod wont turn on help please

    last time i tried to turn it on, the logo came up but was surrounded by blue, not black. now it wont turn on at all and is not read by anything. ive tried the reset several times. still doesnt work. its just off and not responding. can any one help?

  • Global Policy Link Does Not Open A New Browser Window in IExpenses

    Hi All, On 11.5.10.2 version Global Policy Link which is located at the top of most iExpenses pages is supposed to open a dynamic web page (Core policy manuals) on a new browser when someone clicks on it. Currently this link, when clicked on it, brin

  • View Menu Tree Report?

    Seems like there used to be a concurrent manager request you could run to print all the submenu and functions in a menu tree. Is that still around? Can't seem to find it. The menu tree viewer shows what I am after, but does not have a print option.