Hi:
In landed costs in 2005 we used to have a facility to allocate the landed costs and while passing a JV - we used to select the corresponding vendor to pass the necessary entry as an account by pressing shift tab.  The new version 2007 does not allow you to select the BP at all.  Is there a way when we import we will be able to pass entries to the vendor (for clearing and forwarding expenses invoices) and debit the corresponding clearing and forwarding expenses.
regards
Manian

Hi
I have gone through the documentation on landed costs and it is not that well drafted as is not conclusive.
I have 2 problems:
1. Previously in 2005 you used to add the landed cost and then later create and post the journal, now it seems that once you add it posts automatically.  Can we stop this in any way and work on the old method?
2. Currency - in 2005 you would change the currency to USD for example when putting in the ocean freight amount etc and all other costs in USD and then change to local currency for all the other costs which are in the local currency.  It does not seem to allow you to do this anymore or is there some tab or button i need to change.  We need this function!
Kindly assist as soon as possible.
Regards,
Shaun

Similar Messages

  • Landed costs

    Hi All,
    This is a question on landed costs for imported materials. I have created a PO for an item having a value of INR 650, [ex.rate u2013 48/-] qty u201310. I have created landed costs after a/p invoice. I gave freight amt as 20 usd, customs  value was 42.26. In fixed costs I had chosen u2018cash value before customsu2019 as 135.42 and u2018cash value after customsu2019 as 177.68. Here I donu2019t know the importance of u2018factoru2019 tab. Now if I see the landed cost document , it is showing u2018expected customs(FC)u2019 as 202.85, freight it has taken as 31.31,  warehouse price as USD 2477 , I had entered u2018actual customsu2019 as Rs.2028.50. On this basis the total is getting changed. How the calculation is happening? Can anybody throw some light on this ?
    Regards,

    Check this document, How To Manage Landed Costs in Release 2007 A
    [https://websmp201.sap-ag.de/~sapidb/011000358700000463992008E.pdf]

  • Broker In Landed Cost Form

    Hi Experts,
                           how can i set a account for different brokers in purchasing -> landede cost.
                          when i enter the landed cost it's not crediting the broker account. what is the solution?
    Regards

    Hi Sandeep,
    Tha Landed Costs will not post to the Broker. This is information only.
    I think this thread will explain this well:
    Landed Cost Payment
    How To Manage Landed Costs in Release 2007 A
    https://websmp201.sap-ag.de/~sapidb/011000358700000463992008E.pdf
    Hope it helps.
    Jesper

  • How to prevent or undo Landed Costs JE transaction in 2007 and 8.8

    Hello,
    My client prefer Landed Cost module in 2005 version as we can choose not to post JE transaction and Landed Cost is only used for recording purpose. However, in 2007 version JE is automated and Freight charges and other costs have already taken in by AP Inovice. Please advise.
    Thanks & Cheers'
    Vince

    Hi Vince,
    I don't think there is option to prevent Landed Costs JE transaction in new version. If your Landed Cost is only used for recording purpose, I would suggest you do not add it to the system. You may put them as remark.
    It is no point to undo JE because it is time consuming and error prone process.
    Thanks,
    Gordon

  • Landed cost - Is it only for Import ?

    Hi All,
    I am using SAP 2007 B PL 08 in country India.
    I would like to know, whether we can use the Landed cost option for the domestic purchase or not ?
    If not, then why ?
    BR
    Samir Gandhi

    Hi Raja,
    Thank you very much for the answer.
    Can u please let me know iwhether I should use Landed cost for following scenario or not and what extra care I should take for it ?
    I purchase a item @ INR 10 QTY 10 from vendor XXX and posted respective PO/GRPO/AP Invoice.
    Then I receive a Invoice from Transporter for INR 10, and I paid commission to broker INR 10 for the same
    transaction.
    Now I wish to
    1.Load this 2 expenses to Inventory
    2.Pay to respective vendor (Transporter,Broker)
    3.Also post above two amounts to Expenses
    After doing above, now I wish to deduct the expense amount from original vendor (XXX).
    BR
    Samir Gandhi

  • Need solutions for Budget, Landed cost and difference in 2005b and 2007B

    Hi all,
    Need help for the following scenarios
    1. How to define budget for Purchase order and cost centers
    2. Landed Cost in SAP B1 2007 how do we do? I am getting an error message stating that Landed cost allocation account is not defined....
    3. Difference in 2005B and 2007B
    Regards
    Shashi

    Thankyou Jasper,
    Landed cost problem has been solved.
    Regarding Budget set up My client need Budget at costcenter level. i.e Cost center wise they want the budget. As of my knowledge to do this we need to activate Account segmentation right?
    Without doing that is there any other way where we can set Budget cost center level also?
    one more thing, there is a check box of purchase order, Goods Receipt and Accounting at the time of setting up Budget in General setting? what it is for?
    Regariding difference in 2005b and 2007B I was not able to get documentation on this.
    Regards
    Shashi

  • Invoice for landed costs

    Dear forum members,
    I'd like to know how can I create an invoice for a landed cost document linked to a GRPO. How can I link an invoice from - e.g. the transporter company - to the landed cost document I've created?
    Any suggestion?
    Thanks in advance
    Victor Cau

    Hi Gordon Du, Manuel Barreto
    Gordon:
    My conclusion, and as I understood from Robert Czik's postings (Links), is that in B1 2007 there is no way one can post an invoice for the landed costs document. So if I receive an invoice from the company that took the items from the airport to my company, the only way to create an invoice in the system is starting a Purchasing process from the beginning (PO then GRPO then IN).
    Thank you very much.
    Manuel:
    I think there is a missunderstanding from you. But any way, I thank you for your attention.
    Thanks & Regards
    Victor

  • Landed Costs cannot be added for FOC item

    Dear Expert,
    Good morning, recently our Company have upgraded to SAP Business One 2007 A (8.00.178)  SP: 00  PL: 42, when we add a landed costs with FOC item, the system does not allow us to add the document.
    Please help.
    Regards,
    Ng

    HII
    Can you post the error what you are getting
    You can refer to the Documentation on Landed Costs 2007A  if it is helpfull to you
    https://websmp103.sap-ag.de/~form/sapnet?_FRAME=CONTAINER&_HIER_KEY=701100035871000520489&_OBJECT=011000358700000463992008E&_SCENARIO=01100035870000000183&
    Good Luck
    Rizz

  • Project in Landed Cost

    Hi All
    In 2007 B Landed Cost document, the system will pass a automatic
    journal entry. i am not able to select project field in the row level
    of the landed cost document.
    In client business scenario, he will import all goods based on projects
    and he wants to know how much revenue and expenses are getting on that
    project. Could you suggest me how to follow the scenario for Landed
    Cost.
    One landed cost Document can be based on multiple GRPOs  created for different projects.
    Ex:-
    Having 4 GRPO's with project A, B, C and D respectively.
    When i am making a landed cost document.
    I will select all this 4 GRPO's into one landed cost document.
    My price distribution will be based on weight and volume.
    At present Journal Entry
    Raw material -- --- -- -- --- --- Debit
    Transport    -- --- -- -- --- --- Credit
    I Need
    Here i need to distribute the price project wise
    Journal Entry
    Raw material -- --- -- -- --- --- Debit for project A
    Raw material -- --- -- -- --- --- Debit for project B
    Raw material -- --- -- -- --- --- Debit for project C
    Raw material -- --- -- -- --- --- Debit for project D
    Transport    -- --- -- -- --- --- Credit for Project A
    Transport    -- --- -- -- --- --- Credit for Project B
    Transport    -- --- -- -- --- --- Credit for Project C
    Transport    -- --- -- -- --- --- Credit for Project D
    Edited by: Siva Reddy P on Jan 19, 2009 5:38 AM

    Hi
    Sir
    What i want to say is that for every landed  cost u have to assign a G/L account 
    and for every G/L account (expenses and revenue only ) u can predefine the Profit Centres 
    so for example the landed cost is 'A' you can assign 'X 'G/L Account to it so u can assign  ' Y 'Profit Centres  to 'X' G/L account it means whenever you SELECT  landed cost 'A'  in Landed  document with 100 Rs it will hit Profit Centres ' Y '
    You have assign distribution rule actually  so if  Y1  and Y2   are Profit center and u have to assign landed cost IN 20: 80 ratio u can do it by defining a distribution rule
    Avtar Singh Saini

  • How to Cancle Landed Cost

    Dear All CAn we cancle Landed Cost in SAP B1 2007 B

    Hi,
    You can't cancel created landed cost. For more detail about this, read the sap note 1081792. This note is particularly for B1 2007A but can also be used as a reference in B1 2007B.
    However, you could create a manual JE to reverse the JE of created landed cost.
    If you want to correct or edit the created landed cost, you could use landed cost --> copy from --> landed cost. If the landed cost is closed, you can't edit it except cancel its JE only.
    JimM

  • Create Invoice from multiple GRPOs with Landed Costs

    Hello all, again,
    Sorry to bother again, but this one seems strange to me. Consider the following business process:
    1) One Purchase Order is created in SAP, and sent to provider (no journal entry)
    2) Several partial deliveries are received and posted to inventory (inventory @ invoices to be received)
    3) Partial deliveries are pulled into Landed Costs document (inventory @ invoices to be received)
    4) Steps 2) and 3) may be repeated several times
    5) Invoice of provider is received, with the total amount as per PO
    Now in step 5, I have no possibility of "pulling" the PO from step 1), neither pulling the GRPOs created in step 2), because they were used in the Landed Costs document. It is also not possible to "push" the PO to Invoices (only the open amount would be pushed, not the delivered amount). It is only possible to push a single GRPO to Invoices, resulting in lots of manual work and incorrect representation of provider's invoices (1 PO is delivered in up to 100 different shipments of varying quantity).
    The only reasonable solution I see at the moment, is to use a service invoice and post it directly to the "invoices to be received" account. Or do you have any other ideas/solutions?
    Thanks for your suggestions,
    Joerg.

    I should is correct. Yet it is not possible. I am using 2007 SP00, PL 47.
    Do you think I should send the issue to SAP? Do you know of any notes about this issue?
    Thanks,
    Joerg.

  • Fixed Asset procedure For acquirsion Throught Landed Cost

    I Have To Import A Fixed Asset From Foreign Vendor.But How Can i Able Charge Landed Cost To That Asset.means Simple Landed Cost procedure just Cost the Charge to Inventory item But How To Fixed Asset
    Regards
    Naveed

    Naveed,
    Landed cost only supports inventory item in current system design.  You need to do it manually for Fixed Asset.
    Thanks,
    Gordon

  • Landed Cost not showing in Inventory Audit

    I have a query that goes against the OIPF/IPF1 tables to locate all Landed Cost transactions for a particular item. To test/verify the query, I ran the Inventory Audit report for the item. There are transactions returned from the query that do not show in the Inventory Audit report. Is there any reason or circumstance under which a Landed Cost Transaction would not show in the Inventory Audit report. I checked against all warehouses. This does not seem to be a singular event in that I have found random occurences of this for different items yet the majority of the time the Audit Report returns all entries.

    Dear Cristian
    Please check the Following things.
    1)First check audit report for a Single Product.
    2)Select all warehouse in Audit report.
    3) Check you landed cost entry if your JV not pass in landed cost, so landed Cost not reflected in you audit report. (Auto JV not pass in SAP 2005 Version)
    Please check and Let me Know.
    Regards
    Mangesh Pagdhare.

  • To add cost in already posted Landed Cost document

    Hi experts,
    i have created an landed cost against an GRPO and added my other costs against the GRPO, and then i have made an A/P invoice against the document, now my GRPO has been closed and the payment to the party has been done.
    Later to add some cost against the landed cost, i am trying to use the landed cost option under copy from button by selecting the same vendor. but the earlier landed cost entry is not available for selection.
    Kindly guide me with this process.
    Regards
    Pradeeo

    Hi,
    It is not possile to change the posting period in a posted document, alternatively you can park the document form the external system and it can be posted in SAP after review by the user.
    Thanks and regards
    K.R

  • How to reverse landed cost on open A/P Invoice

    Dear Support
    Please be so kind to assist wiht the following issue: I need to reverse landed cost from a open A/R Invoice #  72223
    Purchase Order #  125025
    Goods Receipt # 16426
    Landed Cost 15332
    A/P 72223
    If i select the A/P invoice and copy to A/P Credit memo and preview the journal remarks first, the following error occurs
    "Quantiy falls into a negative inventory"
    My Question however are if I do proceed with this function, will this rectify the landed cost?
    Please view the screen shots attached for investigation as well as the journal remarks on each document
    Inventory Posting List:
    The reason for not posting to the stock account is because the AR Invoice was been done before the landed cost has been processed:
    At the time of landed cost there were no stock on hand, this has been the reason why the amount has been posted to the Price difference ledger account  and not the stock account.
    Your response will be much appreciated
    Kind regards,
    Ilze Fourie

    Dear Nagarajan
    Thank you for your response, much appreciated!
    Attached please find the screen shots
    Kind regards,
    Ilze Fourie