Liquidated Damages calculation in Purchase Order
How to capture the Liquidated Damages calculation in Purchase Order in SAP MM module?
I have seen many posting with the answer that this is not standard process.
But this is very important process in Purchasing and Liquidated Damages is very important process, if in SAP standard system it is not available then how we can cater this required.
Regards
Lets assume delivery date is 1 May and the vendor delays the shipment by 10
days, the GR takes place on 11 May. So the vendor has to pay liquidated
damages for 10 days. We can agree in beginning with the vendor how much
liquidated damages will be charged per day.
So now we can create two new fields in PO. One with Liquidated damages
charges/day and one with total liquidated damages. In this field, it should
look for the days difference between the GR date and delivery date in our
case 10 days * Rs.1000/day = Rs.10,000. This formula needs to be inputted in
the total liquidated damages.
Now we can directly get it posted to IR or if we want it to hit the
material cost, we need to add new condition type to calculation schema and
apply this cost to the condition type by ammending the PO.
Hope I am helpfull.
Similar Messages
-
Liquidity analysis (FF7b) and Purchase Order
Hi,
I try to figure out, what controls the values from Purchase Order going into Liquidity Analysis.
is this based on vendor in EKKO (LIFNR) or based on partner roles?
We have a partner role Vendor, a role Sending Party and a partner role Invoicing Party.
Do I have the chance to influence, which partner role is used? It seems that the role Vendor is displayed in liquidity analysis. I would like that the partner role Invoicing Party is used as this is normally accounting department and could be for a number sending parties.
The person creating the invoice does normally not know which is the invoicing party when creating a purchase order.
Thanks!
HeinNo answer
-
Logic for Calculating Pending Purchase Order Receipts
Hi,
I am developuing one report which displays weekly production and inventory coverage details.
I have a problem. i dont know how to calculate the pending puchase order weekly basis.
Can any one help me
Regards
Guhapriyan.Hi Guhapriyan!
In table EKKO / EKPO you find the purchase orders. Be sure, they are still open: EKPO-ELIKZ = space.
In table EKET you will find (estimated) arrival dates -> take deliveries of corresponding week.
Regards,
Christian -
Calculation of Purchase Order TAX in Smart Form
Hi All !
I am facing problem in purchase Order, how to calculate the value of tax in Purchase order .
in KONV Table, I am getting the value of condition type which r maintained on pricing procedure but, we r not getting the condition type for particular TAX code.
How we can calculate the tax. or
Is there any problem in VOFM/formulas/condition value.
please suggest me.
Thanks & Regards
PritiHi Jitendra,
Thanks for your wonderful co-operation. The issue is almost solved. One lat wuery-
We are at present using 20 tax conditions in our tax procedure. But in a single PO we are using only 3 or 4 conditions out of them How can I identify in my program that which tax conditions are actually used in the current printable PO????
I can use table A363 for searching condition records only after identifying the relevent condition type used in a PO otherwise I have to search for all 20 condition types. Please note we are using TAXINN ( condition based) tax procedure.
I am eagerly awaiting for your suggestion. Thanks again,
Priti -
Lot size calculation for Purchase order
Hi all,
I want to purchase Labels which comes in lot qty such as in lot of 100,200 etc.
For that particular items i want to do mandatory qty lot size in PO when buyers places the purchase order.
Can anybody tell me How i can map that lot size for the particular item.
Regards,
AnantHi,
You can done it with change Material Master.
Enter MM02 t-code, enter your material code and select MRP1 view.
Here maintain Rounding value as 100 in material master.
After when your create purchase order system put quantity as 100, 200, 300 etc.
Regards,
Mahesh R. -
Tax calculation in Purchase order
Hi,
i had created new key combination vandor/taxcode/plant/material for maintaining tax. Tax rate maintain in fv11 for this combination. But in Purchase order this value of this rate is not populating in tax procedure.
Thank's & Regard's
Parag LuteHello
Go to OBYZ and select Access seq and select your access sequence and go to access tab on the left.
In that check whether your key combination is there.also select your combination and click on fields tab also.
Then come back to the access page and check whether the eclude tick is checked for the combination given by you. if so remove the tick and save.
Hope this helps
Regards
Gregory Mathews -
Excise duty Calculation In Purchase Order
Dear all
I am facing the problem in exduty calculation in PO
Actually for my clients business process scenario, Excise duty is getting inventorised so for that i have done the config in TAXINN by using Non deductible keys for JMOP and SEC edu cess.
Well now few days back the taxes were calculating in PO (Excise duty +VAT) perfectly also the dutie swere getting inventorised.
NOTE: In my scenario while the goods are received Excise duty is applicable which has to be inventorised whereas while the finished goods are sold no excise duty is applicable..that is my client is not avaling the credit.
But now when i m testing again ...i.e i have made the PO and for VENDOR,MATERIAL and PLANT Combination i have mentioned the condition records
JMOP,JSEP and JEC1 ,JVRDaslo i have mentioned JMX1 ,JHX1 and JEC1 as 0% coz i want the excise duty to get inventorised , for a particular tax code (01)
I have selected the tax code in PO but it is not calculating Excise duty though it is calculating VAT perfectly.
what can b the reason..Plz help me in this context
Regds
shaileshi have checked the validity but still it is not working.....also i have created one more material and maintained all the condition but still it is not working
plz help me regdg this
regds
shailesh -
All gurus,
How to capture the Liquidated Damages calculation in Purchase Oreder in SAP MM module?
Is it available in STD SAP or Not?
Upesh.>
Kashif Ihsan wrote:
> Dear Afshad,
>
> I appreciate your response, i would like to know the applicable solution for that, if i have to customized through ABAP then how.
>
> Kindly explain the complete workable solution for that so that after knowing your solution i can implement it to calculate the Liquidated Damages.
>
> Regards
Dear Kashif,
Lets assume delivery date is 1 May and the vendor delays the shipment by 10 days, the GR takes place on 11 May. So the vendor has to pay liquidated damages for 10 days. We can agree in beginning with the vendor how much liquidated damages will be charged per day.
So now we can create two new fields in PO. One with Liquidated damages charges/day and one with total liquidated damages. In this field, it should look for the days difference between the GR date and delivery date in our case 10 days * Rs.1000/day = Rs.10,000. This formula needs to be inputted in the total liquidated damages.
Now we can directly get it posted to IR or if we want it to hit the material cost, we need to add new condition type to calculation schema and apply this cost to the condition type by ammending the PO.
Hope I am helpfull. -
Tax (VAT) on Purchase Order
Hi Gurus,
Please send step by step instructions of setting up VAT calculation on Purchase Order. Your help will be highly appreciated.
Regards,
Kennedy.Hi,
though I have not tried the set up of VAT yet, the below link would be of a help for you.
http://help.sap.com/bp_bblibrary/500/documentation/U40_BB_ConfigGuide_EN_IN.doc
Pravin -
Liquidity forecast - purchase order payment terms
Dear Experts, I have the following issue,
We are using liquidity forecast, but we are having a problem because the system does not take into account when a Purchase Order is created with Installment Payment Conditions. The Liquidity Forecast shows the Planning Date equal to Delivery Date of the Purchase Order, not taking into account the division of the payment term and the days of delay of every partial payment. I would like to know if there is workaround for this issue.
Best regards.Hi Cristobal,
The splitting of payment commitmentment accrding to the instalment dates are not possible. However it is possible to have the first instalment payment date instead of delivery date. But for this the Payment Term definition should take the baseline date as any of the 3 defaults possible ( Doc date/Posting date/Entry date). That means it should not be "No Default".
Below reproduction from note 497381:
"In the installment payment terms, you can enter 'Fixed day' and 'Additional months' for the calculation of a baseline date. In this case, the system updates the entire payment commitment as at the calculated baseline date (fixed day and additional months)."
Please try this and also share your results with us
Shony -
Purchase Order Open quantity calculation.
Hi All..
I would like your help in finding out the logic behind calculating the open quantity for a given line item of a purchase order.
Iam aware that i should go to the EKBE table to see purchase order history. Can someone tell me what are all the conditions i need to consider to calculate the Open quantity.
Iam able to give a value E to field BEWTP (Purchase Order History Category) in EKBE and for all the recieved records iam adding the quantity for movement type 101 and removing the quantity for movement type 102 that finally gives my total GR qty. Then iam doing Original PO qty - GR qty to get the Open qty.
Let me know if this logic is wrong or else is there any other conditions to consider.
Appreciate your help and will reward.
THanks.subtract the PO quantity EKPO-MENGE with the delivery quantity field EKET-GLMNG
Thanks
Seshu -
Purchase order on Liquidity forecast
Hi all,
Today we have integrated the configuration of the the liquidity forecast by sales orders and open items accounting, but it does not consider the purchase orders. Does anyone know how could I configure it in order to consider the purchase orders?
Thank you in advance
Regards.Hi,
I have a problem that none of the PO amount is reflected on cash liquidation, the report only retrieves balances of PO which have been converted to invoice through MIRO.
I found that the configuration is complete, planning group has been assigned to vendor master data. Do you have any idea how planning level in Cash Management connects to Material Management/Vendor?
Or is there something missing that I can't get balance of PO in cash liquidation report?
Thanks a lot -
Automatic Calculation of Input Tax in a Purchase Order
Hi SAP Gurus!
Good day! Please help with my problem. During my creation of a Purchase Order, I will have to indicate what Tax Code to use. In this case, I use "Input Tax 12%". On the Item Condition TAB, the calculation of the input tax is not reflected. How can I customize this, in order for us to see the breakdown of Taxes automatically?
Thank you.
MikHi Mik,
If you maintain the tax codes in the system for your company code then the tax codes will be picked automatically in PO through FTXP and the same is reflected in PO.In Invoice tab you have to give tax code, then in Condition tab, the values will be calculated as per the condition values maintained for the tax code.No need to maintain any thing in pricing procedure.
If your tax procedure in TAXINN, you have to maintain the condition records for the condition types ( JMOP, JEC1, JSEP etc..), then only the values can be shown in PO in Condition tab.In TAXINN, the tax code has to be assigned to the company code.
Regards,
Gangadhar Y -
Reg. Calculated tax values in Purchase order
Dear All
I have to print tax percentage and value applicable in Purchase order. In po, at item level by clicking <i>invoice view</i> tax code appear as 3C besides button named <i>TAXE</i>S. on clicking <i>TAXES</i> different value of tax and excise with percentage appears. all these appears thru komv structure. i want to print these vales.
by click <i>Where used Structure KOMV</i> there appears many object /classes. but i dont know how to use these. kindly provide me solution to fetch these values.
thanks/regards
ManjitCreate Tax code in FTXP
Let us SAy A1 --Note : for purchasing it should be input tax only
Then in FV11 Create condition record with plant material and vendor combination with cond type as JVRD
Maintain the TAx rate as 4 % or whatever is applicable
also enter the Tax code as A1 which u have created for ur tax procedure TAXINN
SAve it
Create a PO for the same material,vendor and plant combination
and enter the Tax code as A1
I think with the above details ur tax should get calculated
regards
shailesh -
Purchase Order condition isn't calculating the value of refundable tax
Hello Experts,
When i am inputting tax in invoice tab at item level footer in Purchase Order, and after that when i am calculating the taxable and the total amount the condition tab isn't displaying the tax value, the condition type is NAVS of tax in condition tab. Kindly suggest me i want to calculate tax.
Thanks
HarmandeepHi flora
Just get through the sequence .
see the table fields ...
1. From EKKO table take an entry which is having pricing conditions.
Now in the fields list check out for field EKKO-KNUMV(document condition number).
2.Take this condition number and now goto table KONV.
Give the document condition number in the field KONV-KNUMV and execute .
This will lead to a list of document condition numbers and some other fields .
3.Now check for field KONV-KNUMH ,KONV-KAWRT(quantity) and note the value KONV-KWERT .
(Remember this is at header level).
This is ur condition record number.
**comments
Now from document condition number we got the condition record number (KNUMH).
4. now since u want the item level tax procedure go to table KONP and give the condition record number and execute .
This will give u a list of details .
Now concentrate on KONV-KAWRT (scale quantity) KONP-KBETR(rate) as this table will store Pricing per UNIT so product of these two will give u the total pricing tax, for a particular condition type say PR00 .
For that particular condition item .
Check the pricing procedure .
See t-code VK13 and check the pricing procedure .
From me23 check the same PO num select the item and check the pricing conditions applicable .
Select a particular pricing and goto condition->analysis->analysis pricing ,
Better take help of a SD functional consultant in the process.
regards,
vijay.
Maybe you are looking for
-
Hi Everyone, I am getting an error message: An error occurred while trying to connect to a web service, when my InfoPath form tries to load. The last few days, it only spits this error message in the morning and around 12pm-1pm it resolves itself an
-
Can you boot from an external USB hard drive? (Neo2 Platinum)
As I'm tempted to get a 160Gb drive for Linux and AMD64 XP installations. But obviously it needs to beable to boot from it. Thanks
-
Debug Assertion from javaw.exe
I'm getting a Debug Assertion Failed from javaw.exe: (Windows 2000) jre1.4.2\bin\javaw.exe File: dbgheap.c Line 1044 Expression: _CrtIsValidHeapPointer(pUserData) This occurs on one of my native DLL method calls. Here's the scenario: I've got a set o
-
Autofill form text fields from database
I have made a form in asp code with text fields. Behind this page is a database (access). This database contains static information and does not need to be updated. It is only for output. In this form, there are some text fields to be filled in. Refe
-
Hybrid Tablespace model after R12 upgrade
Hello, I have done with the upgrade process from 11.5.9 CU2 to R 12.1.1 successfully, the instance is up and running. However, after checking the DB objects, I found that the old tablesapces have alot of DB objects. as shown below. Can I rerun the OA