MAS: resolving collisions in productive system

Hello experts,
I've upgraded my mas productiv system to 50sp11 and now I get
the same collsions as in test mas (50sp11).
I've already transported the changelist with the resolved collsion from testsystem
but I still get this collsions in prod system.
Can I set this collsions to baseline now and then I have the same
stand as in testsystem ?
Thanks for help !
Gerd

Hello Wolfhard,
I've checked table changelist and there the changelist for
solving the collision is there in p-system.
But starting mas I still get the popup with collsions.
I've seen the tool blcomparison, but I do not get connection to
the ars_db of the test-system, so I cannot compare it.
I think I must open an OSS.
Maybe you have any other proposals ?
Gerd

Similar Messages

  • How to resolve Collision in MAS 4.0

    Hi All
    I need help on this. We are 2 developers both of us unknowigly made some changes to the same tile in 2 diffrent changlists.
    we are ready to release with lot of additional changes in the change list. It gives an collision error. We don't want to delete the change list. Is there any way we can resolve this collision.
    or at least save one of the changelist?
    Its Mobile Application Studio with CRM 4.0
    Thanks in advance
    Hetal

    Yes it is well possible to resolve the collisions in MAS. that's what called as Concurrent Development. Two users modify the same object,Collsion will result. In such cases, you need to choose which version to be released.
    Instead of writing everything here, I will provide one quick link which explains about how to resolve collisions.
    http://help.sap.com/saphelp_crm50/helpdata/en/25/96033cc68e3f05e10000000a114084/content.htm
    In your case, If you require the changes done by both the suersm then you need to go for Merge option. Please check the above link for more info.
    Best Regards
    Shankar

  • Transformation pointing to Quality Client in Production System Repeatedly

    Hi,
    I need to understand one issue which is explained in detail below step by step.
    1. I created one Customized Data Source(Full Load) and replicated in BW.
    2. Also created Info Objects, DSO, Info Package, Transformation, DTP.
    3. While transporting this modelling to Production(first time), i unknowingly/mistakenly missed capturing the datasource in Transport Request.Sequence of transport was -
    Data Source
    Info Area
    Info Object Catalogue
    Info Object
    DSO
    Cube & MP
    Data Source
    Transformation
    Info Package & DTP
         Now, the moment TR for transformation was transported it threw an error - "Data Source does not exist in Quality client". Then I transported the Data Source TR and after that re-transported the transformation TR production and this error was removed.
    But, there were 2 transformations in production - 1) Pointing to Production, 2) Pointing to quality.
    4. I request the basis team to delete the second transformation(pointing to quality) from BW production system.
    5. After that we captured Data Source and transformation in same TR and transport was successful.
    6. Now, after few days we transported a change to production for same object and the system again threw the same error mentioned in point no.3 above and created two transformations again.
    How to resolve this issue permanently and I also want to know the reason of this type of system behavior.

    Mohammed,
    I did that also - please read my step no.4.
    We are able to delete the transformation which was referring to quality client and then captured D.S & transformation in a single TR and transport as successful.
    Now, after few days I did one change in the same transformation and transported to production.
    System Behavior:
    Error - " No source exist (i.e.,system referred to quality in production)".
    Also again transformation was visible in production which was referring to quality client(which we already deleted with the help of BASIS).
    Now since again the transformation needs to be deleted from production, our basis team is telling us to they cannot delete objects every time in production.Thus,
    1. Is there any option to solve this issue permanently?
    2. Also is it necessary to transport data source along with the transformation which is directly linked to data source?
    Please Note: We have Dev+Quality as one client and Production.

  • Role not displayed in Production system

    Dear all,
    I have CUA set up (CUA is configured in solution manager), and I assigned 10 roles to a user in solution manager using SU01 and selected  Production system while assigning roles and the roles were already existing in production system.but after role assignment to the user, I verified in Production system and I found that they are not reflecting in PROD. Infact, I have done user comparision but still no change.
    Please let me know do I need execute SCUL by selecting the User ID.
    If yes please let me know the steps to execute SCUL.
    Your help is much appreciated!
    Many thanks
    Anil.

    Hi,
    Please go to the Transaction SCUL, and give the user id and the system as the prodution system ID (eg. PRD100). By default the Error, Warnings and Unconfirmed Distribution will be already checked. Do not change them and then click on Execute.
    If you receive the message saying No Data, then it means that the IDOCs for that user were successfully pushed from CUA to the production system.
    But, since the change was not reflected, when you execute, you will be able to see the status where the IDOC is struck. Expand the tree and see the nature of the error, and try to resolve that error. And then select the entire tree and click on the Distribute button.
    It will give you a pop up, let all the checkboxes as it is, and continue. After the distribution is triggered, you will get a message in SCUL.
    Refresh the SCUL data, and you should be able to see the current status of the distribution.
    If all the data is cleared in SCUL, you can log into your produciton system adn check the users roles. New role should be visible there.
    I hope this will clear your doubt. Let me know if you have any questions on this.
    Regards,
    Sneha Vyas.

  • Inactive Transformations and DataSources in Production System.

    Hi Experts
    We are working on BI 7.0 engine within Solution Manager.
    We had some issues with DataSources initially while transporting BI Objects from Devp to Prod. We logged it into OSS and followed their procedure to redo the transports.
    In the process, the issue was resolved but 2 New Transformations are created one for each Data Model (since I have only 2 InfoCubes) automatically and is the working model now.
    Actual Transformations from Devp became Inactive in Prod and also there are 2 Inactive DataSources which are also from Devp. 2 New DataSources are again from Devp.
    When I tried to Delete these unwanted Objects from Prod (I asked the Basis to Open Prod for me though this is not the best practice), it is asking for a Request ID. Also, since the Project has Gone Live already, I am scared if I might disturb the Production System.
    Kindly, advise what best could and needs to be done.
    Thanks,
    Chandu

    Initially, we implemented BI-HR module with standard content, which 3.x content (transfer / update rules)... in parallel we also did transformations & DTPs (BI 7.0 model).
    Since, client wasn't sure with conversation of transfer rules (has lots of routines) to transformations & DTPs . So we transported both the models to prod sys... We created daily load process chains with transformations & DTPs... The actual plan was, if PC loads fails, then to go for manual loads of 3.x model...Fortunately 7.0 models was successful...
    Then one month later, we deleted those transfer / update rules and 3.x datasources from prod sys, on the weekend (process chains runs only week days) without any issues...
    We captured those deletion requests and deleted them from SE09 by unlocking them in SE03.

  • OPEN ITEMS EXTRACTION (FPBW) cancel in productive system... HELP

    Hello!
    I have received this message when I executed FPBW transaction, Open items extraction for BW... I have looked in Notes OSS but nothing... Could you helpme please? Do you have any idea what was the problem??? I think it is Basis problem in Database, but I am not sure, please it is urgent, because the error was in productive system---
    The exception must either be prevented, caught within the procedure    
    "FETCH_CURSOR"                                                        
    "(FORM)", or declared in the procedure's RAISING clause.               
    To prevent the exception, note the following:                          
    Database error text........: "ORA-01555: snapshot too old: rollback segm
    number 169 with name "_SYSSMU169$" too small"                         
    Internal call code.........: "[RSQL/FTCH/DFKKOP ]"                     
    Please check the entries in the system log (Transaction SM21).                                                                               
    You may able to find an interim solution to the problem                
    in the SAP note system. If you have access to the note system yourself,
    use the following search criteria:                                                                               
    "DBIF_RSQL_SQL_ERROR" CX_SY_OPEN_SQL_DBC                               
    "SAPLFKKOP03" or "LFKKOP03FR1"                                         
    "FETCH_CURSOR"

    Hi,
    How you resolved this issue?
    If you are having the solution for this please share with me as well.
    and one more thing, how can we schedule these two jobs in background for daily loading the data into DFKKCIBW and DFKKOPBW.
    Please share these two things with me.
    Thanks in advance.
    Srinivas

  • No data in Production system

    Hi Experts,
                         I have a very critical query. In  my 0Employee master data for some  employees their Personal area and personal Subarea are maintained for certain valid period in Quality system but for the same employees  for same valid periods it is not maintained in the Production system.
    The above mentioned data is there in PSA as well as in the data target in Quality system
    The above mentioned data is there in PSA of Production system but only not in the Data target (0employee)
    Please Resolve my issue ASAP
    regards,
    Khan

    Data s there in Production PSA except for some employees.
    This is only in production system
    but in Quality the data is there for all employees in PSA as well as Data target.
    Regards,
    Khan

  • Inactive DataSource in Production System

    Hi Experts,
    I have  a situation where DataSource inactive once I initialise infoPackage.we transported from Development to Production and it was active (green) in Production System.I tried to initialise infoPackage then I got the message
    DataSource 2LIS_13_VDITM  must be activated.How can I resolve the issue.Please throw some light on this issue.I am in a position like golive soon.your help will be appreciated and awarde

    Hi,
    1. Replicate the datasource at Application component Level. i.e. If your datasource is in an application component say, BW then right click on the application component "BW" and select "Replicate Metadata".
    2. If you have transfer rules then activate them with program "RS_TRANSTRU_ACTIVATE_ALL".
    SE38 -> RS_TRANSTRU_ACTIVATE_ALL, if you are not able to do it, ask help from your basis to do it, they will have option to do changes directly in prodution itself.
    Also chk Note 1056060 - DataSource: Reactivation in the production system
    Hope this helps,
    Regards
    CSM Reddy

  • In Production system Infocube mange screen selection changed

    Dear Experts,
    I have problem with my production system.
    Problem:In Prod system for all the Infocube settings has changed may yesterday because of that we are not able to see in the manage screen Tranferred and Added records colums.
    Could you please suggest how to overcome this situation in production system and also why it was happend suddenly?
    Regards,
    Kiran.

    Hi,
    Thanks for your prompt responce, but nowthing was happend like system refresh or package upgarede.
    Could you please suggest me any other ways to resolve this issue.
    Regards,
    Kiran.

  • Data Mismatch problem in Production system

    Dear Experts,
    We have been encountering serious data mismatch problems with our source system since 29th Dec 2010.
    We have realized this mismatch only on 11th Jan 2011. So, we have deleted entire data from 29th Dec 2010 onwards to 11th Jan 2011. Then we tried to load delta again as per our Process Chain sequence. Since then, our production system has become very inconsistent. We found that the entire data from 29th Dec 2010 to till date is started giving mismatch.
    Our system got damaged in terms of data drastically. If I delete any bad requests from our Cubes & Data Store Objects, the next time when we try to load data, cube & Data Store Objects is showing the deleted request no. is not updated properly. Because of this, our Process chain is daily failing to complete and giving so many technical errors. We are totally confused to restore our data from 29th Dec 2010 to till date.
    Can any one please help us to restore our data fully and Process Chain to run successfully...............?
    Thanks in Advance,
    Suman

    Hi Suman,
    I understood that you are using 3.x version of BW
    such kind of issues occurs if you distrub the delta sequence by deleting the requests without making them red.
    you can resolve this two ways......
    1) Go to reconstruction tab of the DSO and CUBE, select all the req from 29th Dec 2010 thru 11th Jan 2011 and reconstruct them. once they appear in the request tab. make all the requests to red (set the QM status to RED) one by one and delete them from the CUBE and DSO.
    This should set the delta status  back to 29th and you will be able to run a repeat delta from then in your next delta.
    2) Go to RSRQ and give the SID or the Request ID one by one that it is giving you ( request no. which is not updated properly)
        Mke the QM status as RED for all of them.
    Since you have already deleted them from the targets, just changing the QM status to RED will be sufficinet.
    You have make the QM status to RED inorder to inform the system that the requset is incorrect one and has been deleted.
    Once it is set to RED, system will not prompt any req and say "request no.# not updated properly".
    i suggest you the second option.
    Once you resume the delta load, it should run successfully.....and if you feel some data is still missing from 29th Dec 2010 thru 11th Jan 2011, just run a full repair load the get the data back.
    If your Datasource is of LO extraction u may need to fill the setup tables to perform full repair.
    Please let me know if the Datasource is of LO extraction. Also let me know once the issue is resolved.
    Regards,
    Sudheer.
    Edited by: Sudheer Kumar Kurra on Jan 22, 2011 7:58 AM
    Edited by: Sudheer Kumar Kurra on Jan 22, 2011 8:03 AM

  • FSE2 - Change Financial statement version in production system

    Hi,
    I have an requirement, my client wants to change the financial statement version from FSE2 transaction in the production system.
    For this I made FSE2 and V_T011 as current settings in SOBJ transaction and executed the transaction FSE2 which is still giving error message of "Client 032 has status 'not modifiable'".
    Can any one let me know how to make it happen? so that user can able to maintain the financial statement version from FSE2 transaction in production system.
    Thanks in advance.
    Regards,
    Abdul

    Hi Abdul,
    I am not sure if the problem has been resolved or not but if you can follow the steps below I hope your problem will be solved.
    First, find out that what application area and message number are issued when you try to modify the financial statement version. To do this, go to t-code FSE2 in your production system. Once message pops up click on help button beside the exist button to display the long text of the message.
    Usually this message number is FE146 which means the application area is FE and the message number is 146. (I know you know this )
    In order to switch off this message, go to T-code OBA5, enter APPLICATION AREA 'FE" and press enter key. Now click on NEW ENTRIES button, enter the relevant settings Msg: 146, leave user name blank, Online "-",  Batchl "-", Standard "E". Press the enter key again and click on Save button.
    You can now go to the Production client and attempt to modify the financial statement version by going into T-code FSE2. Enter relevant financial statement version and click on the EXECUTE button. When you make your changes and click on SAVE, you will see a message that "Client xxx has status 'not modifiable'".
    If you press Enter key, the system will display a message saying that financial statement version has been changed and your changes will have taken effect.
    I hope this way your problem will be resolved.
    Let me know if this help
    Thanks
    Naseem

  • Importing parameters not available in Production system

    Hi Experts,
    I am facing an issue after moving my objects into Production system.
    I have created a calss and which contains five methods. Each method contains itsown importing parameter. There is one method to send mail, which contains three importing Parameters. I have captured this class and the methods in a TR and basis team moved this TR into production system.
    The TR has  moved successfully into the production system. But when I checked the Parameters of the class SEND_EMAIL has only one importing parameter insted of three.
    Again I created a new TR and captured all the objects related to Class, which contains class definition, methods etc.
    I have moved it to quality system successfuly. When I checked in quality i can see the three importing parametrs in SEND_EMAIL method.
    This TR has moved to Production successfully. When I checked in production I can see only one importing parameter in SEND_EMAIL method.
    But it is showing same active version in Quality and Production.
    Please suggest me how can I resolve this issue?
    Thanks
    Pradeep.

    Dear Pradeep
    First you check the parameter which u are sending that are already in prd server exist or not
    some there are some thing we can see which are available in qua those are not seen in production
    see in se06 and try to modify the exact component to modifaible state
    check sp pack of qua and prd are one and the same
    check kernal rel level in both
    check chmod  and chown are same in both
    Regards

  • Solution - only productive system are displayed in DSWP

    Dear all,
    I have created 4 Solutions.
    In each solution - which has a "Productive System" as Leading Role of the Solution,
    only productive systems are displays when I start my DSWP transaction.
    Example :
    1. Solution Name : Sol_ER
    2. 3 logicals systems are assigned to this solution :
        Z_ER_CRM_SERVER_50 ==> D12 - Q12 and P12 are assigned to this logical component.
        Z_ER_ERP_60 ==> D11 - Q11 and P11 are assigned to this logical component.
    3. When I start DSWP and I choose Sol_ER as SOLUTION, only P12 and P11 SAP systems are display.
    I need to have all SAP sytems - D12-Q12-P12 and D11-Q11-P11 display in my SOLUTION.
    Thanks in advance for your input.
    Best regards
    CP2009

    Dear CP2009,
    Only productive systems are "Put in Solution" automatically.
    QAS, TEST, DEV systems need to be explicitly "Put in Solution".
    If you go into the solution, in change edit mode, and right click on the systems that are not showing up when the solution is used, and select "Put in Solution", then visually the SID should be highlighted green, and now available in the solution.
    I hope this information has been helpful and resolves this problem.
    Regards,
    Paul

  • EIC- Data Inconsistencies in Productive System

    Dear EIC Experts,
    Have a query regarding data inconsistencies in the productive system. I will illustrate with an example,
    An Activity was created and a follow up activity created on that and assigned to a resolver group.
    There is an entry in SCMG_T_CASE_ATTR with Status 20 (Allocated)
    and an entry in THREIC_ACTIVITY, with a whole load of data like creator org unit and owner org unit missing, all it has are the activity categories and the user id.
    An entry exists in THREIC_FOLLOWUP with all relevant fields filled but Worlflow ID is blank. The status in this table is 40 (delivered).
    So it looks as if no workflow was created and it did not go to anybody to action. And the activity cannot be closed and is just lying there, as the owner cannot take any action till the follow up status becomes completed.
    1) What could be the possible reasons for this to happen? I have already checked that workflows are all activated and there are other activities being raised and clsoed just fine.
    2) Is there anyway I can use any utility tools to correct the data in the back end in such a way that thia activity can be clsoed down?
    I have a few hundred activities like these (from 30000 overall activities) which cannot be closed because of various data inconsistencies. Any ideas are appreciated.

    Hi Harish
    I have worked on multiple EIC implementations and I have never had this issue though the follow up functionality has been set up correctly and by the details in your email my guess is that it is not at your location.
    It is possible to fix these 100 or so and set them to closed but it is to much to type out in this forum.
    I would check out www.eicexperts.com as they are experts in EIC and they may walk you through it as they are very helpful.

  • Background Job Running long time in Production system ???

    Hi guys,
    I have custom report which runs normally in 20 minutes.  i am executing this report every day.  but when i execute the same report yesterday it took 5 hours.
    i did the performance trace ....the sql statements are in acceptable range only. i don't see any major time consumption. 
    since it's in production system  we can't debug the active job....
    can u guys, throw light on this issue.
    Note : there are many posts related to this already in the forum, but not helps to resolve my issue.
    Regards
    Girish

    Giri,
    You can use STAD (or older one SE30) to have a trace of the program if you have that access and will be a great help in finding the problem.
    If you can't due to some reason, then next time job runs for long (while in ACTIVE state), check SM50 regularly to see that the is process hanging on a table fetch, check that any of the DB table is not getting frequent locks in SM12.
    Also, you should check that if your job does any table update, is there any new index created in prod system for that table.
    If you can't find anything, then take the necessary access in Prod from basis temporarily and debug the job to find exact issue.
    Regards,
    Diwakar