Hi,
all my stuff is make to order production.So sales order generates requiremets and i cinvert it in to production order.
My problem is the configuration is in such a way that i can not release a production order untill all the components are available.
and since they are all produced against a sales order I have to make individual and collective indicatior in material master as 2.
there are few materials this indicator missing.
So they always show materials i as not available in the production order .Hence i can not release my order.
I know its because of the individual and collective indicator.
but if i go and change the the indicator to 2 in the material master its impact can be seen on the future orders.
I am having problem with the production orders that are already in creation status.
I can not release them even the material is available.
is there any other way to solve this problem.

Deepu,
Suggestion for existing orders, processing
In the change of the order using CO02, go to the Component Overview screen and in the Component overview screen Currently the components would be defined with Special Stock Indicator "1" - Please remove this and make this field blank. Once this is done, system would consider the available stock.
The other option is to make a stock transfer of the unrestricted component stock to sales order stock using MB1B transaction and movement type 411 or 412 E i think. Please check.
Another Option, Since the order is not yet released yet. Your Material master defination changes can be effected to the order by executing Read PP Master data functionality.
Regards,
Prasobh

Similar Messages

  • Process Order Material availability check error

    Dear All,
    At the time of i create the process order after that i push Material availability button system give me the following error log.
    Please provide me the solution how can i resolved following Error.
    "No control data maintained for checking group 01 and checking rule Z1"

    Dear,
    Go to OPJK and maintain the setting for rule Z1 and group 01
    Then go to OPJJ here select your plant and order type then Business funct.1 for order creation then in side assign checking rule Z1 and remove the tick mark for NO check then repeat same setting for Business funct.2 same rule and remove no check.
    Then material master assign the same group after that create the order and check.
    Regards,
    R.Brahmankar

  • Work Order Material Availability Check Customizing

    Hi,
    I am currently trying to set up material availability check in the work order before saving. I am testing it by entering a material in the work order for which there is zero stock. Then clicking on ORDER > FUNCTIONS > AVAILABILITY > CHECK STOCK MATERIAL. However SAP would return 'All checked materials in order 100000317 are available' in status bar.
    My customizing is as follows:
    Define Checking Rules (SPRO):
    PM     Checking rule for plant maintenance
    Define Scope of Check (OPJJ):
       Availability Check: 01 (Daily Requirements)
       Checking Rule: PM (Checking rule for plant maintenance)
       Availability check: 2 (Check availability during order release)
        Stocks
        Include safety stock: X
        StockIn Transfer: X
        Incl. quality insp. stock: X
        Replenishment lead time
        Check without RLT: X
        In/outward movement
        Incl. purchase orders: X
        Incl. purchase requisitions: X
        Incl. dependant reqs: X
        Include reservations: X
        Include sales reqmts: X
        Include deliveries: X
        Incl. planned orders: X (check all planned o)
        Incl. production orders: X (take all production)
    Define Scope of Check (OIOI):
       Plant: (Corresponds to Work Order)
       Order Type: (Corresponds to Work Order)
       Check material availability when saving order: X
       Check rule: 02 (Corresponds to material being used)
       Release Material: 3 (No release if parts are missing)
       PRT Availability: No check
       Capacity Availability: No check
    I would appreciate if you could indicate if I am missing something in the customizing or if there is some sort of error. I would like SAP to display a system message on the status bar stating that this material is not available once the user enters this material.
    Regards,
    Nikolai

    I'am facing the almost the same problem. Could anyone tell me:
    1. How to make material availability check work  during Work Order creation?
    My requirement is Work Order can not be created when it has missing parts. I have set the config to '3' can not created when is has missing parts, but it still does not work.
    I have implemented SAP Notes 1148139 on my system (SAP ECC 6 Ehp 5) also, but still does not have any effect.
    I must not set the config Res./Purch Doc creation to 'immediately', because it does not fit to my user requirement. Is there anyone knows how to solve this requirement?
    2. How to make  information message/ Availability check screen appear when sparepart is missing, without clicking Availability Check button? for example: appear when clicking Save button.
    Thank you
    -amoonra-

  • CNS0 - Material availability check

    Hi Experts,
    Now, we have some problem for material availability check.
    For example :
    Stock : 10 pce
    1. we create outbound delivery for 6 pce for Network / Activity : A / A000
    2. we create outbound delivery for 4 pce for Network / Activity : B / B000
    3. Now we create outbound delivery for 5 pce for Network / Activity : C / C000 , what we expected is there is an error message to tell us " only 0 PCE of material XX available " , but now, there is no message, outbound can be generate without any message.
    Could you pls help me to know where might be problem ? where I should check ?
    Best regards
    Shubin

    Hi Nitin,
    thanks, but seems the problem is not here, I guess it is a material availability check issue.
    BR , Shubin

  • Material Availability Check Upon Confirmation

    Hello Everyone,
    I had a question regarding Material Availability check.
    Here My raw material and Semifinished Goods are Backflushed during confirmation. My client wants to check material availability check upon confirmation of production order. System should not allow Confirmation if no stock is available. Is there any way how I can do this?
    I know we can perform material availability check upon release and prevent the same, but user does not accept this since change in production order is possible even after release.
    Any suggestion would be greatly appreciated.
    Sincerely,
    Aji Kurian Mani

    Hi,
          you can configure this in the confirmation parametres --OPK4.In General individual entry tab Error handling/logs tabmake a tick for the Goods movements --Termination for the Incorrect Goods Movts.
    Termination of Confirmation if Incorrect Goods Movements Controls if the confirmation is terminated in the event of incorrect goods movements
    If these incorrect goods movements are determined by inventory management, then the option of correcting these errors is offered in the error handling
    If the correction is not successful, the confirmation is terminated
    Thanks,
    Rajanikanth

  • Longer time for Material Availability check while creation of prd order.

    Hi guys,
    I am facing a weird problem while creating production orders thru CO01.
    I enter the component and plant and I am also using the forward scheduling option.
    for some reason, SAP is taking a long time for material availability check when I hit the release button.
    Sometimes its taking more than an hour. Its happening with few specific BOM's, and I have checked the master data but I could hardly find a problem in master data.
    Can someone suggest me some tips ??
    Thanks & Regards,
    Sashivardhan

    Hi,
    Please check the Availability check control maintained for Components it should be 01 or 02. Also check the issue storage location maintained or not. You can maintain issue storage location in BOM in Status/lng text tab in Production Storage Location.
    Hope this will help.
    Regards,
    Navin

  • Material availability check be switched off for during dispatching of order

    Hi All,
    Material availability u2013 can the material availability check be switched off during  dispatching of production order but kept when order is created? 
    Is there any implications on availibilty check.
    How can we do this?
    Regards,
    Vidyasagar

    Dear
    If you want to do Material Availablity Check only at the time of order creation , please choose Availability Check Business Function 1  with your order type  /plant combination .Keep No Check  in Capacity  and do not assing  the Overall Capacity Profile Here .
    Where as keep the Capacity Overall Profile for Production Order Type with Availablity Check  -2  and Mark No Check to material availablity  option in the same .
    In OPKP -make sure that you have Capacity Profile assinged and do not mark Confirm Partial Available Qty .
    How ever , in capacity requirement , material availablity is the intregrated part  and while dispathcing production order with in the available capacity of any operation in work centre , system tries to make sure the materials are available for processing just before actual operation starts .
    Check in CM21-Setting-Strategy -Dispatch Control -Check if you have option to un-check the Material Availability .
    Regards
    JH

  • Material Availability Check in Process Order Issue

    Guys, I need some help in understanding the folowing issue:
    I have a FG and 2 components.I created a process order and tried to release the order. Automatic availability check is done and a dailog box appeared to list out the missing parts. Missing parts list shows both the components. But one of the componet has unrestricted stock to use in the storage location. why did the availabity check show missing part for that component?
    I checked pp checking rule and it says for business rule 2 "no check" is unchecked. so that means checking is done. and this pp checking rule is assigned in OPJJ and also assigne dto the material master of the component.
    please let me know if you need more information. Thx

    Dear you are absolutely correct if you uncheck No check box in material availability in Order control OPJK  per plant and order type that no automatic material availability check is to be executed for the specified business transaction (order creation or order release).
    But further please note that the option of calling up a material availibility check manually and also of executing a collective availability check is not affected by setting this indicator. This indicator is also ignored if you work with Assembly orders and you have defined in Customizing for Sales Orders that a material availability check is to be carried out.
    Cheers
    kK

  • Material availability  check for production order

    Hello,
    Is there any functional module to check the material availability of production order. So that it can be used in developments.
    Regards,
    Ganesh

    Hi,
    Following are the available Function Modules for avaibility checks in Production orders,
    BAPI_PRODORD_CHECK_MAT_AVAIL -  BAPI: Execute Material Availability Check for Production Orders
    And for Process Orders,
    BAPI_PROCORD_CHECK_MAT_AVAIL - BAPI: Execute Material Availability Check for Process Orders
    Regards,
    Dhaval

  • Material availability check not being executed

    First of all: I’m an SD consultant with limited knowledge about PS
    At our current client are we facing an issue with the material availability check in project system orders, created through e.g. CJ20N. The client mentions, that the availability check on the components is not being executed and therefore is effecting their operations
    I did check SAP OSS and found the following OSS notes:
    01774744           Planning quantity of PIR is not getting updated properly
    01745038           BAPI_NETWORK_COMP_CHANGE is updating PBED-PLNMG incorrectly
    01774657           BAPI_NETWORK_COMP_CHANGE is not updating PBED-PLNMG –III
    Those notes were also implemented
    Did find transaction CJBN and did some testing, but did get the message
    BL 001
    Availability check not activated
    I did check transaction
    OPJJ and everything looks good.
    OPJK and everything looks good
    At this point I’m totally clueless on how to resolve the issue.
    If you would have any suggestions, pointers or remarks: they would be appreciated.
    Thanks and regards,
    Jan Pel

    Hi,
    Can you please check whether the configuration of material availability check in PS is proper and in place or not. Please check the following sap help link on material's availability check in PS:
    Material Availability Check - Material - SAP Library
    Regards
    Saurabh

  • How to make material availability check work during Work Order creation

    Hi Experts,
    Kindly advice about these matters:
    1. How to make material availability check work during Work Order creation?
    My requirement is Work Order can not be created when it has missing parts. I have set the config to '3' can not created when is has missing parts, but it still does not work.
    I have implemented SAP Notes 1148139 on my system (SAP ECC 6 Ehp 5) also, but still does not have any effect.
    I must not set the config Res./Purch Doc creation to 'immediately', because it does not fit to my user requirement. Is there anyone knows how to solve this requirement?
    2. How to make information message/ Availability check screen appear when sparepart is missing, without clicking Availability Check button? for example: appear when clicking Save button.
    Thank you
    -amoonra-

    Hi Maheswaran,
    I have implement the prerequisite notes. (Notes 790219 and 1034962). Do you know why it is still does not work?
    Thanks
    -amoonra-

  • How to address missing parts during material availability check

    The system prompts that a particular component is missing during material availability check of a production order. Said component is available in the system upon verification in MMBE.
    We noted that the goods receipt date of the material is way beyond the requirement date, hence the system still prompts that it is missing.
    What we did to correct this is to change the basic start date of the production order thus changing the requirement date of the material.
    The resolution unfortunately, brought another problem, another planned order was generated, which consequently generated another purchase requisition.
    What is the proper way of addressing the missing parts prompt during material availability check?

    Hi
    Not able to understand why you are using BAPI & function module.
    It is a simple function of avaialbility check.
    For this you have to fill the availability chk field in material amster of all components &  givecheckinh rule  inOPPQ .
    After creation of process order, you can check COR2 it self.
    It is a std functionality.
    It should definitely work.
    Regards
    YMREDDY

  • COHVPI Material Availability Check

    Hi All
    I am using COHVPI for collective check of material availability:
    1. For all packaging material it checks and show me the log if there is material shortfall, however for Batch managed semifinish product it does not show shortfall if there is any! ( I am using batch strategy to pick batch automatically, but dont think it makes any difference here)
    2. Also, after the Material Availability check the order status stilt l remains MANC, rather I expect it to change to MACM.
    Can you guys please suggest any solution for this!
    Thanks in advance
    Rahul

    The status MANC suggests that a dynamic availability check is not being executed.
    Check if the same occurs in COR2 as well as COHVPI. If so, you then need to check if availability check is actually switched on for the material;
    First, check if a checking group has been assigned to the material master and ensure "No Check" is not selected in transaction OVZ2.
    Then check the checking rule assigned to the order type in transaction OPJK. Here, you can check if a check is executed during release or during creation. It may be you have only activated a dynamic ATP check at order release for example and the orders being processed in COHVPI are CRTD.
    Also, You should check tranaction OVZ9 to ensure the availability check is checking receipts that you expect it to check.

  • In t-code COHV: is it possible to take out material-availability-check?

    Hi Friends,
    In t-code COHV: is it possible to take out material-availability-check?
    Regards,
    Will.

    Dear Will,
    Yes
    Check this link
    [COHV u2013 AV Check |COHV  Mass processing of production order and planned order;
    Regards
    Madhu

  • Material availability check not consider the MMBE stock correctly

    Dear Experts,
    Thanks for your continuous support.
    I have one clarification ,at the time of process order raised COR1 - Click Material availability check after that massage had come in all material check available , but system wise some of the Bill of materials having not stock in MMBE ? What is the reason for the issue, with out stock material also given the status ok in ATP.
    At the time of confirmation i have put some loss qty , where is the way of display in loss qty after that confirmation.
    I need the report for one month process order confirmation list with order qty, confirm qty, delivered qty, &Loss qty ? Loss qty details only i am seeing kindly give the guidance if any t.code for display loss qty against the process order.
    Thanks,
    N.Umapathy

    Hi N.Umapathy,
    "Click Material availability check after that massage had come in all material check available , but system wise some of the Bill of materials having not stock in MMBE ? What is the reason for the issue, with out stock material also given the status ok in ATP."
    There can be an available quantity even if there is no stock in MMBE for that material.
    A simple example:
    Production order created with component X.
    Component X has a required quantity of 100.
    There is no stock in MMBE for material X.
    However, there is a planned receipt of stock (maybe in the form of a purchase document for example) of 100.
    In this case, it is possible that the availability check will confirm 100 is available even if it is not in MMBE.
    Another contributor on here, Jürgen L has written a very good blog on this here:
    Unrestricted use stock not equal to available stock
    Hope this helps.

Maybe you are looking for

  • Mini DVI video adapter doesn't plug into MacBook

    I purchased a Mini DVI video adapter at the time that I purchased my MacBook in late 2007. I planned to use it later to connect to a larger monitor. I also purchase a MacBook for my wife in late 2008. I recently realized that this Mini DVI video adap

  • Improt queue error

    Hi All, i am using two system landscape ecc6.0, i had configured TMS and, and also established rfc. my problem is that when i tries to import the queue from DEV in PRD server its throwing an error An error occurred when opening the source file for re

  • Problem with the package execution

    Hi Guys, I am getting the problem while executin the package for 1 of the interface named PRE_SYNC_EX_ARMY_VEH_DEL. I am looking in the operator as at the first session task is in the process(running mode) with "DROP FLOW TABLE" as the message while

  • Gateway access denied

    hi, I have an application on a different domain and my gateway is on a different domain.I am accesing an application on that server from that gateway but I am getting Gateway Access denied error. Please help me thanks in advance dhawanmayur

  • Bbm won't launch after update

    I need help I downloaded the update and it won't load I can't find it Solved! Go to Solution.