Material Cost Planning in cProjects (4.0)

Hi Gurus
I'm new to cProjects and PS.
My project has a Phase which I created as a "Material Acquisition Phase". Effectively I need to source Materials for my Project and would like to record this in cProjects.
Is it possible to record the planned cost for this Material in cProjects or is this only possible in PS.
The phase has a WBS Element attached to it. 
If it is possible, what are the steps required to make it work.
Many Thanks in advance
Panduranga

Hi Panduranga,
In cproject, you cannot Plan for Material Purchase. cproject is a estimation tool where in we can estimate the resource cost on role-based.
Through Cproject and PS integration, you can get the same task "Material acquistion" in both cproject as well as in PS.
In PS only, we can plan value for material acquistion where the value will take from Material master same will not happen in cproject as it doesnot have link to R/3 Marial master.
Hope you understood the concept clearly.
Thanks and Regards
Vetrivelan

Similar Messages

  • Network material cost planning price entry without using moving average

    Hi,
    When adding the stock material (internal activity) to a network activity the system takes the moving average price of the material.
    How can we enter the material AND the price for cost planning?
    Note: The reason is that the material being procured may cost more than the moving average price on the system. When a user gets a quote for the material they'd like to enter the quoted buying price instead of the system taking the moving average.
    Thanks
    Kru

    Hi,
    Normally System allow to Edit Material -  Price/Currency  field in network planning instead of  moving average price.
    Please check it may greyed out for edit.
    Regards
    Ahamed

  • Report to display Mat Cost Planned Labour Cost and Over head cost

    Hi Abapers,
    Greetings of the day..
    I need a Report that Display Material Cost , Planned Labour Cost,Actual Labour Cost and Over head value
    where do i start from and what are the tables involving in this report..
    if already done this A code snippet is more helpful...
    Thanks In Advance...
    Thanks & Regards
    Sathish

    Assuming you are talking about Maintenance Order.
    Use table: PMCO.
    Here the line with field VORGA having value KPPS gives the Planned Costs of the Order in the field WRT01.
    Similarly, the line with field VORGA having value RKL gives the Actual Costs of the Order in the field WRT01.
    Also have a look at Tcode KKBC_ORD.
    Jogeswara Rao K

  • Unit costing for materials assigned to activity - for material cost plannin

    The requirement is that material cost to the company will vary depending upon the project/customer. Eg.: Material cost = basic material cost + a % for P&F + 2 % for Clearance + a % for excise + 2 % for insurance + a % for Customs
    It can be a % or a lump-sum value. It can be all the components listed or part of them. This will be project specific.
    Hence the following preference for material cost planning is required:
    1. Material cost based on quotation or Purchase order - If quote/PO is not available, then
    2.Material cost based on unit costing done for the material in the project - If this is not available, then
    3. material cost from material master depending on price indicator i.e. Std cost or Moving average price
    We are working with valuated project stock.
    SAP Help says"
    "Prices are calculated in one of the following ways:
    u2022     Using the strategy in the valuation variant
    u2022     Manually, using the invoicing plan
    u2022     Using unit costing"
    But how to get the cost as per the priority required when these three options are there is not clear.
    I have tried to work with valuation variant in the costing variant assigned to Network. No valuation strategy explicitly refers to unit costing of material.
    During various testings, at times, unit costing of material gets updated as planned cost; at times not. What triggers in also not clear.
    Pl. clarify
    Thanks and regards
    A.Saravanan

    Hi All
    I have psoted to service market place and got the reply; we have implemented also.
    there were 2 suggestiosn:
    1. Valuation price with user exit - (EXIT_SAPLCK21_002) - This user exit has to be implemented; we have implemented - it is working. But this is taking effect when overhead calculation is done - this we rae managing that way now
    2. Alternatively you can try to use BAdI VALUATION_CK.: This BADI is not editable by us now; SAP has not released for our editing!
    The problem is solved although
    There is one more clarification  required:
    As SAP Help documentation: -> Unit costing is used instead of strategy sequence, but not in between steps of strategy.
    How to get this done ? right now we are using the strategy - inbetween steps of strategy with user exit
    Thanks and regards
    A.Saravanan

  • Raw Material Costing with Overhead, Product Cost Planning

    Hi,
    I have an issue applying overhead to purchased raw materials. We need to apply this overhead for only a certain materials. So, I have defined a overhead key/overhead Group, and assigned the group in the material master of the raw material. The overhead is 2% freight on raw material costs.
    In the std.costing variant, I have assigned the costing sheet under Overhead on material components tab of the corresponding valuation variant. I have also included the Freight OH in the cost component structure.
    However, when I run the costing with CK11N for the raw material, it is showing only the raw material cost, not the overhead.
    What could be the problem?
    I appreciate your help.
    Thanks,
    Ram

    Is the overhead rate a percentage type or quantity based?
    Have you maintained both actual and plan rates (1 & 2) under define % based OH rates or Qty based OH rates accordingly?
    Does the validity date (in define OH rates )cover the date of costing?
    Is the Costing sheet assigned to the valuation variant at plant level?
    Is the OH base in the costing sheet includes the cost element of the raw material?

  • Material Costs transfer to PCA Planning

    Dear SAPguru,
    How to transfer the variable cost like material costs to PCA (Profit Center accounting) planning. we have all the materials assigned to Profit center. We also run MRP.
    Thanks in Advance.
    Regards.,
    RK

    Dear Santosh,
    When we upload the plan for quantity, we are expecting the material costs to be derived automatically from material master price or from MRP requirment.
    Thanks
    RK

  • COPA - Planned Material Cost not appearing in KE30 report

    Hi all
      In COPA planning, I manually planned the Material cost (Material External Price) along with the Sales Quantity and Revenue for two company codes (one plant in each co code). But in KE30 report, I could see the material cost (MEP) values only for one company codeplant. What could be the issue?
      I even tried valuation in KEPM. Valuation step is calculating and populating the material cost in KEPM, but the values are not flowing to KE30 reports. And this happens to only one of the two company codes.
    Thanks
    Vamsi

    Hi Vamsi
    Please check table CE2XXXX, where XXXX = Op Concern.... Here, can you see the plan line items??
    If yes, then the issue is with your report definition in KE30... May be you are restricting values display in KE30 report by virtue of your selection parameters
    br, Ajay M

  • Material cost in production order plan cost

    Dear all,
    -we are in sales order cost object with non-valuated stock...
    -we have created two production orders from MRP run. First one is for semi finished material and second one is for finished material.
    Issue-1
    Both production orders not showing material cost in production order plan cost...
    Issue-2
    When i consumed raw material against semi-finished material production order (261-E), system not gnerated any document and material cost not updated either in production order or sales order...
    where should i do changes in configuration to get updated material cost in the production order...
    Best regards
    Kishore

    Hi
    Issue 1 : Check Whether Standard cost is present for header material of prod order, and under control tab of order costing variant for plan is present.
    Issue 2 : Use 261 instead 261E.
    Rajneesh

  • Costing in cProjects 4.0 - Material costs not reflecting

    Hi,
    In cProjects 4.0, i have replicated the cProject to PS project. I wish to capture the material costs in the project. How should i proceed ?
    Please suggest.
    Regards,
    Amit
    9820502246
    [email protected]

    Hi Amit,
    cProjects has not field to caputure material costs.
    You may however, create an additional field and use that to capture material costs in cProjects. You will need to map this additonal field to the material cost field in PS while replicating project from cProjects to PS. I am not sure of how you will do this. See if there is any BAdI that can help you.
    Regards,
    Reema.
    <i>pl award all useful points.
    Do post back if you find a solution.</i>
    Message was edited by:
            Reema Shahbazkar

  • Material Cost Not Shown in Production Order if planned with MD50

    Hi,
    We have run MRP MD50 for a sale order item ie FERT material which has BOM Items. All the stock of the BOM items is tranfered from Unrestricted Stock to Sales order stock. FERT ITEM planned order is converted to Production Order and all the BOM items sales order stock is issued against PO & Sales order no with Movement Type 261E.
    After confirmation and goods receipt stock of FERT is shown under sales order Stock of Fert Material.
    We can see the cost of operations but cost of materials consumed against the Production order is not displayed in Production order Cost analysis..How material cost can be displayed????
    If i create PO with out refering the sale order that is normal process i can see the cost of materials triggering in Production Order.
    Can we settle the varience when we are planning against sale order???
    Some one Pl help us.
    John

    Dear,
    Check your variant which showes the cost. See the following report
    KKAC - For Sales Order with Assigned Orders  or
    KKBC_KUN - For Sales Order or
    KOB1 - Actual Costs

  • Material Valuation-Easy Cost Planning Using Valuation Strategy U(Userexit)

    Hi Experts,
    I am implementing a userexit for <b>CJ20N</b> for <b>Valuation Price with Valuation Strategy U: COPCP005</b>, in that i activated the function exit <b>EXIT_SAPLCK21_002</b> and wrote my logic in that, i want to use project wise material price instead standard price which is stored in a Z table.
    For that i need to identify the project ID inside the function exit, i can get it using the input parameter <b>IMP_AUFNR</b> for WBS with Network, for Easy Cost Planning the same exit is triggered but iam not getting the <b>IMP_AUFNR</b> there, so i want to know how to identify the project inside that function exit.
    Could someone suggest me a way to find out the <b>Project ID or description or WBS elemen</b>t inside the function exit.
    Thanks in Advance.
    Regards
    Karthik D

    Not answered....i did it using enhancement point....

  • Planned material costs not seen in reports

    hi to all,
    i planned costs for a project using networks and activity elements and material components.  for the activity elements i placed the costs as a direct input and for material components, i input the required quantity and the material number. However, when i looked at the structure overview(CN41), the materials i placed have 0 cost. YET THE TOTATL AMOUNT in the network&activity INCLUDES the cost of the material (quantity multiplied by material price).
    Thanks in advance

    hi again..
    i checked both your suggestions but they have already been carried out earlier so the problem lies elswhere..(but at least i was able to eliminate some of the possible causes..).
    allow me to give an example of whats happening in my case..
    MY INPUTS:
    WBS 1
    NETWORK 1
      ACTIVITY 1
         Material Component 1     3 pcs  ( 1 $/pc)
         Material Component 2    10 pcs   (1 $/pc)
         Element 1(cost)             500 $
         Element 2(cost)             300 $
    OUTPUT REPORT:(CN41 - Project cost Sch 000)
    WBS 1                                  $ 813.0000
    NETWORK 1                        $ 813.0000
      ACTIVITY 1                          $ 813.0000
         Material Component 1           0.0000
         Material Component 2           0.0000
         Element 1(cost)                    500.0000
         Element 2(cost)                    300.0000
    So if you notice in the report the material is 0 but the total includes the material cost..
    thanks!

  • Material cost not getting displayed in CN41N

    Hi Gurus,
    When we execute CN41N, Materials assigned to the Network activity are visible but the cost of each material is not getting displayed against it (under Proj. Cost Plan Column) and it is appearing as '0' whereas, it is appearing as an accumulated cost against the activity. I checked SAP notes for this problem, though I could see some notes which are very close to the problem but all are for Release 600 whereas we are using 604 (ECC 6.0). Have anyone encountered such problems or whether the cost will not appear against Material in CN41N.
    Awaiting your valuable suggestions.
    thanks in advance.
    Vinodh

    I have seen planned cost of material against material itself in structure report like CN41, CN41N under following conditions:-
    1. Valuated Project Stock
    2. Material is created using Reservation for WBS or PR+Res for WBS Procurement indicators.
    3. Costing relevancy box ticked for material
    4. Statistical Cost element exists for Inventory account.
    I have not seen planned cost for non-stock item or material with res for network in project. This is purely based on my experience and I dont have any notes or help document to validate my statement.

  • Order cost plan in report CN41N

    Hi Gurus,
    Would appreciate if any one of share what is  'Order Cost Plan" in report CN41N.
    Infact, the values displayed in Order cost plan column neither coincide with either Project Cost Plan nor Actual cost displayed.
    Looking forward to hear and thaks in advnace.
    Thanks,
    PSR

    Hi PSR,
    Order Cost Plan in CN41N is PM Order Plan Costs figure.
    If you create PM Order and assign WBS Element/Project Def in Additional Data Tab of PM Order after planning Material services system will consider WBSE as Costing object and Plan and Post cost on WBSE. It will appears in CN41N in Order Cost Plan column.
    Please check
    Hope this will help you.
    Regards,
    Swapnil Kharul.

  • Assign direct material cost to value field in copa while issue to Prod orde

    Dear All,
    My requirement is like this:
    There are some 16 material groups from A to P each containing some materials(finished goods).
    I want to allocate overhead to different material groups(Charecteristic in copa) in COPA using the periodic assesment cycles. I am able to allocate overhead(admin & sales cost) to different value fields in copa from different cost centers.
    I want to analyse the product cost and also the profitability of each material group in COPA using Report painter. Iam able to pull all the costs which i assign to value fields using assessment. But, i am NOT able to get the direct material cost which is issued to production orders using BOM.
    My question is whether we can assign the direct material cost to any user defined value field(material cost value field) while the material is being issued to production orders. Is there any automated way where we can directly assign the direct material cost to value field in copa while issuing the material to Production orders.
    Pls explain me whether we can do it. if yes how?
    Thank you very much in advance.
    Regards,
    Vishnu
    VST-IT.

    PA is a Profitability analysis tool. That means it gets updated when a sale is made, not before. (Except for settlements and assessment of overheads.)
    Goods issues for production gets updated in CO-PC, and needs to be analysed there. If you don't, you loose all the inbuilt tools for variance analysis, cost estimate comparisons, Wip Calculation etc. To the best of my knowledge, a Profitability Segment cannot be used as a cost object in Production Planning, because amongst others, you need to be able to capitalise the produced materials to stock at the end of the production run, or to WIP at the end of the Financial period,which is not possible with PS.
    Similarly, overheads are recorded in CCA and needs to be analysed there.
    If one goes against these big groupings in SAP, you always run into problems.

Maybe you are looking for

  • Restarting after upgrading to Leopard

    Hi, everybody. Here's my problem: I just upgraded my iBook from old Panther to Leopard. Everything seemed to be fine and after the upgrading theiBook told me to restart: well, it doesn't start again, I just get the grey screen with the apple and the

  • Can anyone help me solve my problem trying add GUI to Inventory program?

    Here is my code in which I am receiving a couple of errors. package inventory4; import java.util.*; import javax.swing.*; import java.awt.event.*; import java.awt.*; public class Inventory4 extends JFrame implements ActionListener {     private class

  • New Thread not Creating a new Process

    When I create a thread and start it, it doesn't make a new process (as in a process that one can see in the Windows Task Manager) . I have another program that does make another process, and I did the exact same code, but this program isn't working r

  • A numbers spreadsheet suddenly cannot be opened. What can I do?

    Using numbers I suddenly found out that a spreadsheet cannot open. ( It cannot even downloaded from icloud).How can I save my data?

  • Can't use Function keys after creating curves adjustment ?

    After I create a curves adjustment layer, the Function keys are disabled.  Every Function key changes the cursor to an eydropper.  You must first click on the left-arrow at the bottom of the pallette to exit the curves adjustment.  Is there a way to