hi to all,
i planned costs for a project using networks and activity elements and material components.  for the activity elements i placed the costs as a direct input and for material components, i input the required quantity and the material number. However, when i looked at the structure overview(CN41), the materials i placed have 0 cost. YET THE TOTATL AMOUNT in the network&activity INCLUDES the cost of the material (quantity multiplied by material price).
Thanks in advance

hi again..
i checked both your suggestions but they have already been carried out earlier so the problem lies elswhere..(but at least i was able to eliminate some of the possible causes..).
allow me to give an example of whats happening in my case..
MY INPUTS:
WBS 1
NETWORK 1
  ACTIVITY 1
     Material Component 1     3 pcs  ( 1 $/pc)
     Material Component 2    10 pcs   (1 $/pc)
     Element 1(cost)             500 $
     Element 2(cost)             300 $
OUTPUT REPORT:(CN41 - Project cost Sch 000)
WBS 1                                  $ 813.0000
NETWORK 1                        $ 813.0000
  ACTIVITY 1                          $ 813.0000
     Material Component 1           0.0000
     Material Component 2           0.0000
     Element 1(cost)                    500.0000
     Element 2(cost)                    300.0000
So if you notice in the report the material is 0 but the total includes the material cost..
thanks!

Similar Messages

  • COPA - Planned Material Cost not appearing in KE30 report

    Hi all
      In COPA planning, I manually planned the Material cost (Material External Price) along with the Sales Quantity and Revenue for two company codes (one plant in each co code). But in KE30 report, I could see the material cost (MEP) values only for one company codeplant. What could be the issue?
      I even tried valuation in KEPM. Valuation step is calculating and populating the material cost in KEPM, but the values are not flowing to KE30 reports. And this happens to only one of the two company codes.
    Thanks
    Vamsi

    Hi Vamsi
    Please check table CE2XXXX, where XXXX = Op Concern.... Here, can you see the plan line items??
    If yes, then the issue is with your report definition in KE30... May be you are restricting values display in KE30 report by virtue of your selection parameters
    br, Ajay M

  • Internal activity material cost not displayed in report s_alr_87013558

    Hi all,
    I have an material attached to the internal activity.
    this internal activity is inturn attached to a network
    which inturn attached to a WBS.
    After the PR and PO creation of the material attached
    the cost report s_alr_87013558 shows values in the
    WBS element not in the network activity to the material
    was attached
    How to catch the cost value to network activity instead of WBS elment
    Can anybody have a clue why it is happening
    Thanks and Regards
    pv

    hi sreenivas,
    thank you for the suggestion
    in budget report the actual and commitment value is pulled
    to respective network activity or wbs element depending upon the account assignment category during the automatic PR
    creation from CJ20n
    In my scenario during automatic PR creation it is Q(project make to order) instead of N(network).
    Can you throw some light to this where in
    i can generate auto PR with account assgnment category N
    for a material attached to network through internal activity
    Note:
    to catch the cost we also need to activate the cost rel indicator in purchasing doc tab for material in cj20n
    regards
    pv

  • Settlement of planned deliv. costs not possible if GR-related data entered

    Hi gurus,
            While doing T-code MRRL if i am entering the GR posting date and ticking the good + delivery check box an error message is trigerd 'Settlement of planned deliv. costs not possible if GR-related data entered'.PLZ reply the reson for this error.

    I Have the same problem them I realise  that :
    This message just appear if i am using doc. selection = 4 .
    tks
    Teresinha

  • Material Cost Not Shown in Production Order if planned with MD50

    Hi,
    We have run MRP MD50 for a sale order item ie FERT material which has BOM Items. All the stock of the BOM items is tranfered from Unrestricted Stock to Sales order stock. FERT ITEM planned order is converted to Production Order and all the BOM items sales order stock is issued against PO & Sales order no with Movement Type 261E.
    After confirmation and goods receipt stock of FERT is shown under sales order Stock of Fert Material.
    We can see the cost of operations but cost of materials consumed against the Production order is not displayed in Production order Cost analysis..How material cost can be displayed????
    If i create PO with out refering the sale order that is normal process i can see the cost of materials triggering in Production Order.
    Can we settle the varience when we are planning against sale order???
    Some one Pl help us.
    John

    Dear,
    Check your variant which showes the cost. See the following report
    KKAC - For Sales Order with Assigned Orders  or
    KKBC_KUN - For Sales Order or
    KOB1 - Actual Costs

  • Raw material cost not coming KE30 profitability report

    Dear Gurus,
    We have two material type for our finished product for one material type without having cost release for current period we can't release the billing document for accounts but in other material type we can release the billing document for account without releasing the cost for current period.
    This occurs with problem that in KE30 we are not receiving the raw material cost & administration cost. Please suggest what should I do to correct this?
    Thanks in advance.

    Hi,
    I already assigned costing key to material type (FERT,HALB) but bifurcation of COGM not flow to CO-PA.
    In T.code KEPR
    1.All F/V i maintained as 3 is it ok or i need to maintain it 1 or 2.
    2.In T.code KE4J
    Record type = F i maintained for FERT,HALB category materials & assigned in Costing key
    Earlier before release i assigned in T.code ke4i
    Condition type             Value fields
    VPRS                          Stock value
    Then some value flow to copa
    After i release i removed stock value from ke30 report and added material cost ,sub contracting cost,material overhead but no value flown CO-PA.
    Pl check
    Regards,
    Debashis

  • MSCI planning transaction - planning data have not seen in the report

    Dear expert,
    We are updating the sales planning via transaction MC88. So my goal is to see the results in the reports MCSI, but I have not seen the planned quontity. I have only seen the Actuals.
    Please help me how to set up the system in order to see planned data in the report.
    Thanks in advance.
    Best Regards,
    Slavisa

    Hi,
    The report will say "No Data Available" only when the selection of variables doesn't match with the data exists in the InfoCube.
    Or when the condition is activated with the setting wherein no data found in the Cube.
    Apply the condition or variable selection for which the data exists in the backend(Cube).
    Rgds,
    Murali

  • Material cost not getting displayed in CN41N

    Hi Gurus,
    When we execute CN41N, Materials assigned to the Network activity are visible but the cost of each material is not getting displayed against it (under Proj. Cost Plan Column) and it is appearing as '0' whereas, it is appearing as an accumulated cost against the activity. I checked SAP notes for this problem, though I could see some notes which are very close to the problem but all are for Release 600 whereas we are using 604 (ECC 6.0). Have anyone encountered such problems or whether the cost will not appear against Material in CN41N.
    Awaiting your valuable suggestions.
    thanks in advance.
    Vinodh

    I have seen planned cost of material against material itself in structure report like CN41, CN41N under following conditions:-
    1. Valuated Project Stock
    2. Material is created using Reservation for WBS or PR+Res for WBS Procurement indicators.
    3. Costing relevancy box ticked for material
    4. Statistical Cost element exists for Inventory account.
    I have not seen planned cost for non-stock item or material with res for network in project. This is purely based on my experience and I dont have any notes or help document to validate my statement.

  • How to include Material Cost in the SD report

    Hi,
    I am working on Cube 0SD_C03 for the Sales and Distribution Report "Sales Contribution - Product Wise u2013 KPI" where I have to show the following information which are given below.
    1. Total Sales Qty.
    2. Total Sales Value
    3. Total Material Cost
    For third one I do not know how to include this in this SD report.
    so please tell me about this if anybody has idea about this?

    Hi Francisco,
    Note:
    your xml should only have
    <URL>http://dbxserver.dbxprts.com:7778/pls/apex/f?p=134:1:::NO::P1_ID_CONSTANCIA:1183</URL>
    Show me your sample XML , i can help you.
    What is your expected output ? PDF or HTML ?
    here it is.
    option1:
    If the XML data includes an element that contains a hyperlink , then you can use that element to create dynamic hyperlinks at runtime.
    a. insert hyperlink from word menu
    b. In the Type the file or Web page name field of the Insert Hyperlink dialog box, enter the following syntax:
    c. {ELEMENT_NAME_WHICH_HAS_URL_LINK}
    where ELEMENT_NAME_WHICH_HAS_URL_LINK is the xml data element name
    option2:
    create a form field, you can add it
    <fo:basic-link external-destination="http://www.google..com">
    <fo:inline text-decoration="underline">google Link</fo:inline>
    </fo:basic-link>
    or
    <fo:basic-link external-destination="{ELEMENT_NAME}">
    <fo:inline text-decoration="underline">google Link</fo:inline>
    </fo:basic-link>
    or
    <fo:basic-link>
    <xsl:attribute name="external-destination"><xsl:value-of select="ELEMENT_URL"/>
    </xsl:attribute>
           <xsl:value-of select="LINK_NAME"/>
    </fo:basic-link>

  • Planned delivery cost not updating Through Invoic02 idoc

    Hi,
    We are using Inbound IDOC (INVOIC02) to create invoice. The enhancement that we are looking to do is to use the indicator Goods/Service items + planned delivery costs which is seen when we manually post invoices using MIRO. Can you please let us know of any inputs in this regard.
    For your information - the current functional module we are using to post invoices received through EDI is IDOC_INPUT_INVOIC_MRM and the message type is INVOIC. But this does not seem to help us in case of goods which has got a planned freight attached to it.
    Thanks
    Shasi

    Hi Experts ,
    Kaindly provide me your inputs ..
    Thanks
    Shasi

  • Costing in cProjects 4.0 - Material costs not reflecting

    Hi,
    In cProjects 4.0, i have replicated the cProject to PS project. I wish to capture the material costs in the project. How should i proceed ?
    Please suggest.
    Regards,
    Amit
    9820502246
    [email protected]

    Hi Amit,
    cProjects has not field to caputure material costs.
    You may however, create an additional field and use that to capture material costs in cProjects. You will need to map this additonal field to the material cost field in PS while replicating project from cProjects to PS. I am not sure of how you will do this. See if there is any BAdI that can help you.
    Regards,
    Reema.
    <i>pl award all useful points.
    Do post back if you find a solution.</i>
    Message was edited by:
            Reema Shahbazkar

  • Material costs not captured in production order

    Hi all,
                After clicking 'Cost order' (Ctrl+F7) in production order header screen, if i am checking the cost component structure(Goto->Costs->Cost comp. structure) of production order, only the operation costs are captured. The materials costs are not captured here. Please suggest me in this issue.
    Regards,
    Krishna Chandra.

    Hi everybody..thanx for the replies..i want to clear the following things to u,
    1. Costing variance key is PPC1 for planned and PPC2 for actual.
    2. I have maintained the prices in the material master - MAP for child items & Std for the header item.
    3. This is happening for all the production orders
    4. I have kept the costing relevancy for all the materials in the BOM.
    Apart from these please give me the possible inputs to solve the problem.
    Regards,
    Krishna Chandra

  • Credit Memo not seen in Reports

    Hi all
    My customer has a custom report which shows all the SD billed orders. The selection screens are Sales Doc# DocType, Industry Code, Material, Sold-to-party, Plant, Sales Order etc etc (all non Mandatory fields)
    My problem is, any credit memos created with Order Type CR does not show up in the report. Can some one please tell me where this is controlled and how it can be made active?

    Hi,
    Kindly check the program logic for this report, I mean to say that see if there is any logic written for this report which excludes the credit memo documents. To be more specific about this try to see if there is any restrictions written depending upon the billing document type.
    Hrishi

  • Additive cost not seen in production order and while settling hits PRD

    I am using additive costs for my product costing via CK74n.
    Cost estimate looks good since I have the valuation variants setup to include additive costs.
    But when I see the production order that is being created, all others costs are being considered except additive costs. They are recognized but not as a line item instead as a variance. When I settle the order the costs actually hit price difference account and not even the GL account that I had assigned for the additive cost. SAP did not consider the cost as variance even if it was showing up as variance initially. This as I understood is partly because of the settlement rule that I have in place which tells SAP to go and settle on the material (which is standard SAP to do since I want all the costs from the production order to settle on the eventual material going into stock) so SAP went on to settling on the material. Since the material is set as standard price the variance is being booked as a price difference entry.
    Ideally I would have expected the additive cost getting debited to the order and credited to the gl account that I assigned for the additive cost. The eventual cost (incl. additive cost) should hit the inventory.
    Am I missing a step?

    Hi Sapluver,
    Appreciate your prompt response..Please see my response in italics
    Few queries related to your post.
    1. So your standard cost got two part, one with quantity structure ( materials, labor, OSC etc) which the system cost automatically and one manual part, which is your additive cost. While costing system picks up this manual part from CK74N.
    I hope this part you got correct. Yes, the cost estimate is reading from both the qty structure and the additive costs and the cost roll-up is coming up correctly
    2. Now in actual cost controlling, i think System is not sure how to valuate your additive cost actual part.I agree, the additive cost does appear in the cost analysis section of the production order but does not show up as a line item initially. Instead it comes up as a difference item right in the bottom of the screen after totals have been displayed without any line item reference. As if the system is not sure how to display the line item. Once I have done the material issuance confirmation to the order, the additive cost got picked up correctly as I have set it up in the cost component structure as material overhead but again shows up only as variance
    Which method you used to debit your production order with additive cost, is it a normal journal entry or through some automatic posting through routing ( example OSC through Purchase order/Good Receipt).I probably need to understand your point more clearly? I am not manually debiting the production order at all for the additive cost. I was expecting SAP to debit the order the same way it does for overheads. Overheads too initially show up as variance but then when we run the overhead calculation KGI2 the overheads costs get debited to the production order. Was expecting similar behavior for additive costs. I am receiving the finished product from the production order into stock via MIGO goods receipt movement type 101. I was expecting the debit to happen perhaps at the time of settlement via CO88 but here the system posted it to the price difference account via account key PRD. This I understand the system did because the settlement rule is set to post all the costs on the material and the material has the valuation control as standard price; so the system is seeing the additive cost as a price difference hence posting it to the price difference account.
    System is unaware of the additive cost from actual cost point of view, there is no specification to additive cost from costing variant for actual cost. So you have to debit the order with the additive cost part.So do I manually debit the order with the additive cost? What about the price difference additive cost sitting on the order? Would appreciate if you can tell me the process steps for posting this correctly
    regards
    Sapluver

  • How to get report for cost estimates material cost only

    Hi Gurus,
    We have requirement in sales order costing that we need to develope report which shows only Material cost for all BOM levels.
    Normally at lower levels cost of Material and activity cost will be treated as Material cost for next level. Here I want to consider only material cost not activity cost at lower levels
    Pls suggest the logic and tables for exploding BOM and fetching material cost only.
    Thanks
    Sneha

    Sneha
    If you tick the "Roll up" indicatorfor each cost component  in Cost Comp Str OKTZ, then overheads do  not get added to the material cost... This is my understanding about it.. Is it behaving some thing different in your case??
    br, Ajay M