Migrate Project Server configurations

Hi,
I would like to export the configuration elements of Ms Project Server 2010 such as EPT, Custom Fields and Lookup from one environment(DEV) to another. I have used Playbook tool for migraition. However, Playbook doesn't work with https site.
Are there utilities, add-ons and approaches to migrate Ms Project Server elements across environments? I would appreciate any help in this regard.

Hello,
For Project Server 2010, Playbooks is the only free tool, others such as Fluent Pro are paid for. The other options you have if Playbooks is failing on your HTTPS site are:
Make PWA access via HTTP using Alternate Access Mapping
Write your own backup and restore tool
Migrate the whole Project Server data and config using the rollover approach.
http://pwmather.wordpress.com/2012/04/10/projectserver-2010-environment-rollover-steps-powershell-ps2010-msproject-sp2010/ - probably only suitable if you are going from Production to DEV etc.
Paul
Paul Mather | Twitter |
http://pwmather.wordpress.com | CPS |
MVP

Similar Messages

  • Steps to migrate Project Server 2007 from SQL Server 2005 to SQL Server 2008?

    We need to migrate Project server 2007 from SQL Server 2005 to SQL Server 2008.
    1. Is it as simple as doing backup and restore of databases and pointing Project Server to the new DB server? Or there are some specific steps that should be followed?
    2. Article at
    http://technet.microsoft.com/en-us/library/dd207290(office.12).aspx is about moving databases from one DB server to another (same versions). At one place, it mentions to
    backup all databases but at another place it mentions that
    You should only back up the Draft and Published databases from the source database server.
    What should be done when moving from 2005 to 2008?
    Regards,
    Amit
    Gupta

    High Level step you can get this form  Tech net or MSDN too
    Shut down the SharePoint servers (App / Web)
    backup all of the SharePoint and Project
    Server databases from the SQL 2005 server
    copy these over to the new SQL 2008 server and restore all of
    the databases with the same names
    script out all of the logins used by SharePoint/PS from the SQL 2005 server and create these on the SQL 2008 server
    script out the Delete expired sessions SQL job from the SQL 2005 server and create this on the SQL 2008 server - or create them manually on the SQL 2008 server
    repoint the SQL server DNS Alias from the SQL 2005 server to the SQL 2008 server, if SharePoint and Project Server was installed using the actual SQL server name and no alias, you can create a DNS alias for the old SQL 2005 server name that points to the SQL
    2008 server. This is so that the SharePoint servers can still connect to the same SQL server name
    Start up the SharePoint servers
    kirtesh

  • How to migrate Project Server 2003 to Project Online?

    Hi Guys,
    Is it possible to migrate Project Server 2003 to Project Online directly? I heard we normally have to take 3 hops for this; 
    1. Project Server 2003 - Project Server 2007 migration.
    2. Project Server 2007 - Project Server 2010 migration.
    3. Finally, Project Server 2010 - Project Online migration.
    Is there a migration tool we can use to simply jump from Project Server 2003 to Project Online?
    Thank You,
    Arnel

    NO, directly you can not migrate. You have to follow the sequence 
    1. Project Server 2003 to project server 2007  
    2. Project Server 2007 to project server 2010
    3. Project Server 2010 to project server 2013 online.
    Unfortunately we dont have nay tool which will help us to do this .
    Microsoft has a virtual machine (2007) that you can use to jump to 2007. Basically the databases of 2003 must be converted to 2007. Once this is done (database at 2007) you can use this database as start point to be converted to 2010.
    Microsoft has virtual machine for 2010 too if you want you can use it rather than creating your own environment.
    Don't use 2007 backward compatibility mode in 2010, we experienced some issues with it. 
    kirtesh

  • 2 Problems after migration Project Server 2007 to 2010

    Hi Everyone!!
    I have 2 issues after migrate MS Project Server 2007 to Project Server 2010, in fact i had a lot issues, but i can solve almost all, so after solve all issues, just is pendings 2 issues very rare:
    Backgrounds:
    Migrated from: Windows Server 2008R2 - SQL Server 2008 R2 - Proejct Server 2007 with WSS 3.0 - All updates are up to date (CU is up to date) and all platform is ok
    To: Windows Server 2008R2 - SQL Server 2008 R2 - Project Server 2010 SP2 - SharePoint Server 2010 SP2 - All updates are up to date (CU is up to date) and all platform is ok
    3 Servers in the Farm, ---->  1WFE-1WAPP-1DB
    Issues:
    In the Project Center, some migrate Project don't show the icon with image about project documents, risk and issues although that project effectively have documents , risk and issues
    In "Server Settings" , in section "Operational Policies"  in "Project Sites" almost all projects don't show the URL with Project Site
    For the issues 1 and 2, i tried some things:
    Re publish all projects (approx 700 projects) with a script via PowerShell available in technet
    Run the Wizard Again
    Rebuild Solution
    Restart the all Servers in the Farm
    Restart Services ----> IIS - Project EventService - ProjectQueue - SharePoint Timer
    and  i can't solve it yet!!!
    Please Any Ideas?
    Erick Gutiérrez PMI Membership #ID 2089740 MTCS - Microsoft Project Server Managing Projects

    Have you restored content DB successfully?
    for point 2 have you performed:
    have you synchronized project site under server setting -->  operational policies --> Bulk Update Project
    Sites 
    http://pwmather.wordpress.com/2012/10/08/projectserver-2010-bulk-update-project-site-issue-ps2010-msproject-sp2010-sharepoint/
    after doing this publish all the project which are having issue it may solve your 1st issue.
    You can check if below condition is applies to you (PWA 2007)
    You may need to use the WSS site re-linker tool –
    now built in to Server Settings in PWA as “Bulk Update Project Sites”.  If you have changed URL die to a different port then re-linking should get your sites in order. In upgrade scenarios the “Previous Site Path” Web application might show as a GUID
    in the drop down – however it still works and will re-link the sites.
    http://technet.microsoft.com/en-us/library/cc197498(v=office.12).aspx
    kirtesh

  • Project Server Migration from 2007 to 2010

    Hi Team,
    I am migrating project server 2007 and wss 3.0 to sharePoint 2010 and project server 2010. I am using full database attach upgrade method. The provisioning process end up with failure and uls logs showing the below mentioned errors.
    ULS Logs can be found at the below mentioned link
    https://onedrive.live.com/redir?resid=AC01B07FAACAFC5!534&authkey=!AM1v2WSkbUQx-t8&ithint=file%2ctxt
    I am looking for help, and i really appreciate if some one can help me sorting this out.
    Regards
    Kashif
    Kashif Saeed

    um...
    > Upgrade session finished successfully! 0 errors and 0 warnings encountered.
    not sure what you're asking
    Scott Brickey
    MCTS, MCPD, MCITP
    www.sbrickey.com
    Strategic Data Systems - for all your SharePoint needs

  • How to Migrate MS Project Server 2007 to 2013

    Hi
    Can any one share some reference for migrating Project Server 2007 to 2013.
    As in general process--
    We can take the backup and and restore it in 2013 environment.
    How to migrate Portfolio Server?
    After restroring any steps need to be followed.
    Please guide.
    Thanks
    Geeth If you feel that the answer which i gave you is Helpful please select it as Answer/helpful.

    Hello,
    For Portfolio Server 2007 options, review this guide:
    http://www.microsoft.com/en-us/download/details.aspx?id=20815
    Also see:
    http://blogs.technet.com/b/projectadministration/archive/2010/07/21/anouncing-project-portfolio-server-2007-migration-documentation-to-project-server-2010-just-released.aspx
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS

  • Move Project Server to a new Server Farm

    I would like to migrate Project server environment along with Project and Resource Data from one server farm to another farm. The environment has customized with custom Enterprise Templates, fields and lookups. Servers in the earlier farm are in a different
    AD (Active Directory) environment. So, the new server farm would be in a new Active Directory.
    I would like get the key steps and procedure to move Project Server across the two environments. Would the Database attach and detach process work? Any help in this regard will be appreciated.

    Abhijit,
    I personally did not have to do this, but it seems to me that there needs to be a trust set up between both AD Environments. Also, the service accounts will need to have appropriate access on the restored databases.
    Please refer this link for more information:
    http://www.experts-exchange.com/OS/Microsoft_Operating_Systems/Server/MS-SharePoint/Q_27154301.html
    Alternatively, you could use a third party tool like FluentBooks to migrate the data. Still think that the AD users need to be migrated first.
    Cheers,
    Prasanna Adavi, Project MVP
    Blog:
      Podcast:
       Twitter:   
    LinkedIn:
      

  • Approvals on Project Server 2013 - An unknown error has occurred

    Migrated Project server 2010 to Project server 2013.  All the quick launch pages were working after I completed the migration. Started the process of publishing projects and statusing/timesheets to update project. 
    Now I see "An Unknown Error has occurred".   Tried all my solutions for Project Server 2010 without success.
    Event log looks clean.
    Has anybody seen and resolved this issue?
    Cheers!
    Michael Wharton, MBA, PMP, MCT, MCSD, MCSE+I, MCDBA, MCC 2011, MCC2012
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

    We are having the same error with an on-premise install of Project Server 2013. This is the error from the ULS logs.
    04/24/2013 06:50:58.90    w3wp.exe (0x18C0)    0x1D0C    Project Server    Task Statusing and Updates    c3bn    High    PWA:https://projects.geocent.com/commsec,
    ServiceApp:Project Server Application Service, User:i:0#.w|geocent\john, PSI: System.NullReferenceException: Object reference not set to an instance of an object.     at Microsoft.Office.Project.Server.BusinessLayer.Statusing.StatusApprovalsQueryInfo.AddAllTimesheets(DataTable&
    dt, Dictionary`2& timephased, List`1& actualDates)     at Microsoft.Office.Project.Server.BusinessLayer.Statusing.StatusApprovalsQueryInfo.TryLoad(LoadApprovalType method, DataTable& dt, Dictionary`2& timephased, List`1&
    actualDates), LogLevelManager Warning-ulsID:0x6333626E has no entities explicitly specified.    c9e7149c-070d-5035-0dca-bda3580b7d07
    Not very helpful. Any ideas?

  • Project Server 2010 - M(one to another)

    Hi,
    Can anyone send me the steps for migrating project server 2010 from one server to other server?
    Also please let me know some of the known issues during migration.
    Regards,
    K.Gokulraj
    K.Gokulraj

    Hi,
    Since I'm not a DBA, I'm not going into much technical details, but this is quite a common backup/restore procedure which is well documented.
    Please find a few links as reference:
    http://azlav.umtblog.com/2011/06/07/project-server-2010-database-restore-part-i/
    http://azlav.umtblog.com/2011/06/09/project-server-2010-database-restore-part-ii/
    http://technet.microsoft.com/en-us/library/dd207290(v=office.14).aspx
    http://technet.microsoft.com/en-us/library/ff961887(v=office.14).aspx
    Hope
    this helps.
    Guillaume Rouyre - MBA, MCP, MCTS

  • Bulk Project Site option isn't working in project server 2010 migrated from PS 2007.

    Hi,
    I am doing a test migration from epm 2007 to epm 2013. 
    So first, i need to migrate the project server 2007 to project server 2010. i have 2 separate environments for EPM 2007 and EPM 2010).
    there is no problem in migration process and i successfully migrate entire PWA 2007 to 2010, except Workspaces (Project sites).
    Bulk project site option is not helping. I have tried 4-5 times with different PWA 2007 databases (PWA1, PWA2...) but this option did not work. and errors in queue are WSSWebDoesNotExist(16405) and GeneralQueueJobFailed(26000).
    Then next time while migrating all over again i kept the same port and same PWA name then bulk project site option worked.
    Question is, Do i need to keep the same PWA name and same port for the new upgraded PWA??,  one more issue regarding this is that if don't keep the same PWA name and i open the project site and click on the "Project web app" back link, it
    redirects me to old PWA site which doesn't exist and give me page not found error (Obviously).
    Below, you can see the both scenarios.
    my previous PWA 2007 site, say  - http://epm2007:2222/PWA
    When  -  migrated PWA 2010 site, say  - http://epm2010:3000/NewPWA    (Bulk project site update just doesn't work)
    When -  migrated PWA 2010 site, say  - http://epm2010:2222/PWA    (Bulk project site update worked)
    Whats the solution of this problem. is there any utility or query to link all project sites correctly?
    Will i face the same problem while migrating PS 2010 to PS 2013??
    Thank you.
    sandeep

    Hi,
    I would say it is easier to keep the same PWA name between 2007 and 2010 (no need to have the same port).
    If you want to move to a new PWA URL maybe you can use stsadm backup/restore as detailed in this article?
    http://technet.microsoft.com/en-gb/library/ee662500(v=office.14).aspx
    Hope this helps
    Paul

  • How to configure Https in Project server 2010.

    HI,
    Can i any one help me,
    How to configure Https in Project server 2010.
    My server farm is 1.Test1(App & Wfe) 2. Test2(App & Wfe) 
    Both are load balanced  wit NLB as abc.hyd.in
    DO i need to Install certificate in two servers   Test1 & Test2 or one server is enough ?
    Can any one please provide me a link to configure Https for project server 2010 for Two  Farms Servers.
    Thank You, Kumar KSV

    There is no special configuration for Project Server to have the IIS enabled, it follows the typical sharepoint SSL enablement, we might need some mor edetails on how your NLB is done is it hardware based, software based ? it all depends how you want
    to architecht the system, you can enable the Https either on NLB or WFE, again depending upon how you want to enable it, you will need to install the certificates on both WFE or on NLB
    Follow the blog below to configure the SSL:
    http://epmxperts.wordpress.com/2011/03/05/extend-same-project-web-app-instance-for-different-protocol-authentication-mechanism/
    http://blogs.msdn.com/b/sowmyancs/archive/2010/02/12/how-to-enable-ssl-on-a-sharepoint-web-application.aspx 
    http://www.sharepointconfig.com/2010/03/configuring-a-sharepoint-website-to-allow-ssl-connections/ 
    Thanks | epmXperts | http://epmxperts.wordpress.com

  • After Migrating to project server 2013 some of my Mpp are not opening in project professional

    After migrating to project server 2013 from 2010. my some of mpp are not opening in project professional. 
    project professional taking some time and then showing checkin error. There are no logs on project server to this issue.
    but you can see these project in project server 2013 without issue. I have also tried the EditLink function. but result is same project professional not able to open. Check in error.

    Hello,
    Can you try this:
    Open one of those Projects in PWA to edit in the browser
    make a slight change (new dummy task etc.)
    Save and Publish from the web
    Close and check in from the web
    Wait for the jobs to complete
    Open project professional
    try and open the same project again from there
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS

  • How to configure Time-sheet in Project server 2013 please share the doc with screen shot

    How to configure Time-sheet in Project server 2013 please share the doc with screen shot
    Thanks and Regards, Rangnath Mali

    Hi,
    Please refer to the following Youtube video and article.
    https://www.youtube.com/watch?v=lZWvg4q17JE
    https://support.office.com/en-sg/article/Set-up-timesheets-and-task-status-672fa06f-8c4b-4e43-bfbc-4c355d681605
    Please don't forget to mark it answered, if your problem resolved or helpful.

  • Project Server 2013 migration workspace error

    Project Server 2013 migration workspace error
    Hello all,
    I have just completed my Project Server 2010 to 2013 migration. All look OK until I tried using Project Professional 2013 and opening a project with about 25
    Users (Enterprise Resource) . Opening took about 7 min. I tried creating a new project with 5 users and still took longer then is should. 
    I decided to run the below command and I received a lot of errors about missing workspace.  Please help if anyone can.
    Thank you in advance !!!
    Test-SPProjectWebInstance -Identity http://XXXXXXXX.XXXXXX | Format-Table -Wrap -AutoSize | Out-File -FilePath c:\
    Rule                                                                        
                     TimeStamp             Message                          
    Microsoft.Office.Project.Server.HealthRules.ProjectBICenterExistenceHealthRule                4/16/2014 12:05:57 AM                              
                                              The following ProjectBICenters   
                                              have missing lists:              
                                              (/projectserver/ProjectBICenter, 
                                              Reports).                        
    Microsoft.Office.Project.Server.HealthRules.ProjectWorkspacesExistenceHealthRule              4/16/2014 12:05:58 AM The following projects are       
                                              missing the workspace webs: 'cf8f
                                              0345-c4b5-e311-a4d0-0019b93bec52'
                                              , '52babaa6-c4b5-e311-a4d0-0019b9
                                              3bec52', '37ff2ac5-37bc-e311-b0a9
                                              -0019b93bec52', '17fe20c2-38bc-e3
                                              11-b0a9-0019b93bec52', 'b7faad6a-
                                              39bc-e311-b0a9-0019b93bec52', 'c9
                                              a70e95-a3b3-e311-b36f-0019b93bec5
                                              2', 'fdf3c3f9-86ba-e311-b3d2-0019
                                              b93bec52', 'ee95175e-f4bc-43f6-a9
                                              c9-02837b5791bc', '5e2cbc54-4114-
                                              4f24-af05-03e024c85046', 'bfd9e49
                                              5-2a42-405c-9035-04e51f4afb2b', '
                                              e381d24d-e82d-452b-b1ae-04f74e215
                                              fd8', 'b85dc99a-0989-4fe1-af0a-05
                                              c6b9448991', 'f2e1c579-2493-4ffd-
                                              99a0-072b7f5f527f'

    All,
    Bulk update and post up gradation tasks was completed at time of migration.
    I did notice that when opening Project Professional 2013 and unselecting
    Load Resource Assignments, everything opens and runs as it should. Not sure why ? So I think for now, I'll run Project Professional 2013 without Load Resource Assignments until I find a fix.
    As for (The following projects are missing the workspace webs) error, still getting them.
    Thanks all for the Quick Reply's.
    JBAE

  • Falied "Configure OLAP cubes for Project Web App" in Project Server 2013

    Hi
    I'm trying to use the PS2013's capability for generate SSAS Cubes; but after I execute
    the steps described on “Configure OLAP cubes for Project Web App (http://technet.microsoft.com/en-us/library/jj943761.asp)”  the only thing
    achieved is that the state being "Processing…" and the log:
    ===== Initiating OLAP database build process =====
    [10/11/2013 2:48 PM] Cube build request message has been added to the Project Server queue
    When I check the jobs, the one who is associated with the cube creation is on "Succeeded" state but the OLAP database is never created. There is no evidence I think on the Sharepoint log.
    For notice:
    10/11/2013 14:36:24.41 w3wp.exe (0x1A70)                       0x1848 
    Project Server                   Analysis Cube Building                       
    8ida        Information        Standard Information:PSI Entry Point:   Project User: PROJECTSERVER\system  Correlation Id: 0cea4e03-a432-e311-9401-001cc094718e  PWA Site
    URL: http://<server-name>/sites/Walkthroughs  SA Name: Project Server Service Application  PSError: NoError (0) Cube build request was placed on the Project Server Queue.  afaf4b9c-57d6-7004-2661-c95edeacab11
    10/11/2013 14:36:24.43 w3wp.exe (0x1A70)                       0x1848 
    Project Server                   Analysis Cube Building                       
    8swo     Medium               PWA:http://<server-name>/sites/Walkthroughs, ServiceApp:Project Server Service Application,
    User:PROJECTSERVER\system, PSI: [CBS] Status message: Cube build request message has been added to the Project Server queue,
    LogLevelManager Warning-ulsID:0x3873776F has no entities explicitly specified.                afaf4b9c-57d6-7004-2661-c95edeacab11

    Seems like an error occurred during site collection provisioning with the project server features. The provisioning process was interrupted from a system error and doesn't recovered after system restart.
    I just created and provisioned a new site collection and everything is working now.
    ===== Initiating OLAP database build process =====
    [10/16/2013 5:57 PM] Cube build request message has been added to the Project Server queue
    ===== Verifying and running pre-build server event handler =====
    [10/16/2013 5:57 PM] Verifying and running pre-build server event handler
    ===== Determining database and OLAP database structure =====
    [10/16/2013 5:57 PM] Cube build initialization started
    ===== Building database and cubes =====
    [10/16/2013 5:57 PM] Cube build session started
    ===== Verifying and running post-build server event handler =====
    [10/16/2013 5:58 PM] Verifying and running post-build server event handler
    ===== Processing OLAP database =====
    [10/16/2013 5:58 PM] Process OLAP database session started
    ===== Verifying and running post-process server event handler =====
    [10/16/2013 5:59 PM] Verifying and running post-process server event handler
    ===== Process Completed =====
    [10/16/2013 5:59 PM] Cube build request completed successfully.

Maybe you are looking for

  • Installation of SRM MDM Catalog

    Hi SAP Mentors, We are installing SRM MDM Catalog. I needed some clarification regarding the same. The version for SRM MDM Catalog is 7.02. Do I need a SRM 7.02 server with MDM 7.1 installed on it , on which I will be putting SRM MDM Catalog? Please

  • Issues connecting to Iomega StorCenter network harddrive with Mac OS 10.4.x

    I am having difficulties connecting to an Iomega StorCenter harddrive under Mac OS X 10.4.10: The drive is visible within the network but whenever I click the "Connect..."-button the mouse pointer changes to the spinning beach ball and I have to rest

  • Identity Server 6.1 problem in appserver 7.0

    Hi, I am trying to install ID6.1 on Appserver 7.0.They are all part of JES03Q4Sparc bits. After installing the ID6.1 on Appserver7.0 ,i am not able to bring the amconsole.It says "page cannot be found". I looked into the log file and there are visibl

  • Having trouble with Imaging with an Answer File

    I would like to create an image for Multiple machines; however, I am not sure if I should install the drivers for all machines on one machine and then use the Microsoft-Windows-Pnp Sysprep_Neutral switch in my answer file to keep all drivers that are

  • Photoshop Elements 9 - Help!

    My daughter's laptop became faulty and had to be returned.  I thought I had removed photoshop elements 9 before returning it but now feel I must have messed up de-activation because I cannot use it on my desktop due to licence restrictions.  I have e