Missing parts for Process orders

Hi Experts,
We are trying to find out the Transaction to faciltate the Missing parts list for the process order even after the order has been completed having the Status TECO, CLSD. This is to understand whether proper enough materials are consumed for the order or not. Based on that Production incharge can ensure the component consumption is made as per the Process order requirement.
We are trying with CO24, this is showing the missing parts list if order does not contain TECO and CLSD status.
Also we are checking with COOISPI, COID, but could find the correct feature out of them.
Do we need to develop any customized report with the help ABAPers.If yes please guide us the method.
Please help us in acheiving the list of components which are not consumed as per the Process order requirement.
Also guide us to identify the list of materials which are excess consumed for the Process order.
Thanks in advance..

Hi Jiaul,
Thank you very much for your reply.
So we need to develop the program to flag the missing parts and its qty even after the Order has the status TECO or CLSD.
Can you please provide logic to develop the Program.
I am thinking to take the inputs from process order required qty Vs withdrwan qty. if the Qty difference is positve, which should come under missing parts. if the difference is still negative means excess qty consumed.
Waiting for suggestions
Thanks in advance

Similar Messages

  • Missing part in process order

    Dear ALL ,
    I ahve one issue ....in process order , when I check material availaility , its showing missing part list even though there is sufficinet stock , at MMBE its showing resarvation . For this I have checked folloing possibilities
    1) I did Techo to all Process order which are open .
    2) material master record for any block .
    but still my prolem is not solved .
    Please help me .
    Regards
    P Verma.

    Dear
    Couple checks  for you
    1.Where this stocks are appearing in MMBE ? Block stock ?? Sales Order Stock ? Stock in Transit etc ..please review once again
    2.Check wether any Sales Order /STO or any special stock already reserved this items
    3.Check you availability check control key assinged in MRP view in details OMJJ.
    4.If all those stpes are correctly in place , please look into SAP Note 699407 : ATP shows missing parts eventhough stock is available.
    Hope this will address the issue
    Regards
    JH

  • Missing Parts for all Orders

    Is there a single report which gives missing parts list for all orders with due allocation of components as per the order dates?

    Dear,
    Missing parts information we can see in CO24 tcode.
    In COHV or COMAC.
    in mass processing gtab page
    select function = material availability check, execute it.
    In selection tab page
    Plant
    Order type
    System status - MSPT.
    Or,
    COOIS : Production Order Information System
    Under this transaction you need to Select in List option as Components and then go on Selection Tab
    Regards,
    R.Brahmankar

  • Missing Parts in Process Order

    Hi Gurus,
    I was created process order, in that some materials are shortage, System showing what are the missing parts.
    it is also not allowing to release.
    But, it is allowing to save without release.
    My problem is System should not allow to save, if there is missing parts.
    How to restrict this.
    Can anybody help me in this.

    Hi Anand,
    Check the customization of "scope of check" in the availability check section. Availability check may take into consideration not only unrestricted stock.
    Transaction OPJJ.
    Pay attention to the resolution of this definition - checking group from material master and checking rule from your activity.
    Thanks and reagards
    E.Rambabu

  • Missing part for planned order-reg

    Hi,
    I want to see missing parts list against planned orders. I checked through MDVP but it shows all components as missing parts eventhough stock is available.
    Is there any way to see this.
    Regards
    Karthik

    Dear Karthikeyan,
    In general Availability check is done at production order level and rarely in REM scenario's this check is
    carried out at planned order level.
    Because planned order's are a proposal,which may/may not be converted into a production order.
    At planned order level you carry out an ATP check and its based on the checking group,checking
    rule,and the scope of check.
    So check the config settings in OPJJ particularly for the scope of check.
    Here the check box -->check without RLT plays a vital role.
    once after carrying out ATP,the system shows the committed quantity,say if the order is for 100 and
    suppose if the raw materials are available only for making 20 means then after making ATP check in the
    planned order header you can see an additonal field called commited quantity below the order quantity.
    Check in MD12 for an individual planned order and it works based on the availability check value
    assigned in the material master.
    Regards
    Mangalraj.S

  • How to calculate missing parts for production orders?

    Dear All,
    I have this scenario i'm using collective orders\direct production method in my industry which means that sub assemblies don't enter any warehouses but transferdd directly to its superior order as a component , my problem is i want to know the missing raw material for the finished product , knowing that the FP has a 6 level BOM i want during ATP for production order the sustem checks only for the lowest level of material and takes only the CURRENT STOCK IN WAREHOUSES , what checking group should be used for the FP, Subassemblies and raw materials.
    plz help
    Ahmed Sobhi

    HI,
    If no Av. Check is to be done at all, then specify checking group as KP. But be informed, this will be impactive across all business processes meaning if you plan to sell the SFG & you place a SO for that item, an Av. Check will confirm it immediately as it has av. checking group as KP.
    Now for the checking group maintained for raw mtl, go to OPJJ & check the details of the checking rule to know which receipts/ issues are considered & you may modify the same as per your need.
    I would suggest do a test in your sandbox & if it meets your need, then adopt the same.
    Regards,
    Vivek

  • How to find Missing Parts for a particular Process Order?

    Hi,
    How to find Missing Parts  for a particular Process Order ?
    Is there any function module or Table ??
    Thnx in Advance.

    Hi prince roy
    you can use the T-code = <b>CO24 - Missing Parts Info System</b>
    if helpful PLEASE REWARD YOUR POINTS
    thanks
    chakri

  • Standard Report for missing parts at production order operation level?

    Hi PP Gurus,
                We have standard report for missing parts at production orders level.
    For our client, they need a report for missing parts analysis at production order operation level. Do we have any such standard report in the SAP?
    Please help.
    Thanks,
    Reddy.

    Hi Arvind,
          Thanks for for your response.
    1. List: Components,  Layout: Standard layout          set the Missing part
           It shows the component requirement/withdrawn  quantity for each operation of production order. It is not showing the commit quantity.
    2. List: Components,  Layout: Pick list          set the Missing part
           It shows the component requirement/withdrawn  quantity for each production order.
    3. List: Components,  Layout: Missing Parts List-Material View          set the Missing part
           It shows the component requirement/commit quantity for each production order. It is not showing the commit quantity at opertion level.
    4. List: Components,  Layout: Missing Parts List-Order View          set the Missing part
           It shows the component requirement/commit quantity for each production order. It is not showing the commit quantity at opertion level.
          We are unable to get the solution from all these 1 to 4 reports from COOIS.
    Do we have any option to change the existing layout (ex: 3 ) to get the commit quantity for operation with missing parts indicator?
    If avilable, what is the procedure to be followed?
    Thanks,
    Reddy.

  • GR Cost not updating as Target Cost for process orders

    Dear SAPians,
    We are facing an issue in Target Vs Actual cost reporting for process orders. We are creating a process order after cost estimate of that material and doing the confirmations for activity cost. After that, GR has been done for the finished goods of that process order. That GR entry is updating the Actuals values but not updating the Target cost. When I am checking the standard report KKBC_ORD, I am getting the following figures.
    Cost Elemnt Text     |     Target Cost     |     Actual Cost     |     Target Vs Act
    Inventory Chnge FG     |     0     |     1,472,205.60-     |     1,472,205.60-
    Packing Matrl Cons.     |     1,148,142.37     |     1,252,752.68     |     104,610.31
    Raw Material Cons.     |     60,463.91     |     50,688.29     |     224.38
    Semi-Fin Matrl Cns.     |     181,934.68     |     367,959.56     |     186,024.88
    Labour Cost Activity     |     39,735.36     |     39,862.80     |     127.44
    Machine Cst Activty     |     41,611.75     |     43,153.01     |     1,541.26
    That 'Inventory Change FG' entry is showing the GR posting updating actuals and not target cost. This is causing huge difference in target vs actual cost that will affect the profit and loss figures ultimately.
    What am I missing here? What should I do to update the GR amount in Target cost as well.
    Shirazi

    Dear,
    Target Cost on Production Order or Process Order is shown only when Variance is Calculated.
    So please calculate the Variance, system will show the Total Target Cost.
    Br,Vivek

  • Issues during Component Batch Determination for Process Orders

    Hi,
    I am encountering a strange issue during component batch determination of process order.
    1. During creation of process order, when I execute batch determination, systems does determination based on strategies we have set and when I click on Copy it gives an error
    "Log cannot be saved: Object/subobject not specified"
    Message no. BL201
    *Diagnosis
    Log save cancelled because at least one log contains no object or subobject.
    Object and subobject are needed to classify application logs because there are several log types. Only a few logs are managed in main memory at runtime, so this classification is not needed.
    If the logs are to be saved in the database, object/subobject must be specified for later retrieval.
    Procedure for System Administration
    Object/sub object can be passed when a log is created (function module BAL_LOG_CREATE) and changed with BAL_LOG_CHANGE.
    The possible values for object and sub object must be configured in transaction SLG0.*
    If I save the order with CRTD status and come back again in change mode and do determination, It works fine.
    Again when the order is in REL status and do the determination, It gives the same error.
    This happens only for a specific plant, In other plants batch determination works in all scenarios.
    I checked for all plant related Config for batch determination and coudn't find any discrepancies.
    Please advise how to resolve this issue. Thanks in advance for your help
    Regards,
    Aheesh

    There Is no direct solution for your requirement just try this work around.
    While defining the batch determination search strategy for process order in COB1, there is one column Quantity proposal where you can attach the Routines (This is written in ABAB code )  make use of this, define New Routines with ABAB help to fulfill your requirement. Try this if found useful award full points.
    Regards,
    Ajay Nikte

  • Reverse Goods Receipt for Process Order

    Dear All,
    Please tell me how to reverse the Goods Receipt for Process Order for which already QM is cleared for that Particular Lot.
    But Confirmation is still yet Pending.
    I tried MIGO - Cancel - Material Document. But it is showing a message "Process Order already processed".
    Regards
    buss

    Hi,
    Use t code MB31
    Movement type 102
    Stock type = Unristricted use.
    Reverse by entering above information then you have to manually cancel the inspection lot.
    Regards,
    Vishal

  • BAPI for Process order change

    Hi,
    Can any buddy tell me the Bapi used for Process order change
    with following scenarios:
    Quantity change
    Resource change
    Rescheduling
    Control key change
    RM Change
    Recipe change
    TECO
    REVOKE
    Material shortage check
    Best Regards,
    Sheetal.

    Hi,
    BAPI_PROCORD_CREATE for process order create
    BAPI_PROCORD_CHANGE - Change Process Order
    BAPI_PROCORD_CLOSE - Close Process Order
    BAPI_PROCORDCONF_CANCEL for Cancel Process Order
    Confirmation.
    BAPI_PROCORD_COMPLETE_TECH - Complete Technically
    BAPI_PROCORD_RELEASE - Release Process order
    BAPI_PROCORD_SET_DELETION_FLAG - Deletion Flag
    BAPI_PROCORD_REVOKEUSERSTATUS - Cancel User Status
    BAPI_PROCORD_SCHEDULE - Carry Out Scheduling
    pls refer below link
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/200dd1cc-589e-2910-98a9-bb2c48b78dfa
    http://help.sap.com/saphelp_nw04/helpdata/en/e0/9eb2370f9cbe68e10000009b38f8cf/frameset.htm
    Regards,
    Sankaran

  • BAPI For Process Order Confirmation

    Hi,
    For Process Order Confirmation we are using the following tcode. COR6N. in the t-code we are include a new field (Shift Field) with help of CONFPP07. and we made the field as mandatory also. in cor6n it is working fine.
    now we are using the bapi for same Process Order Confirmation. here the new field is not available. we want to include the new  ( Shift ) Field also. we are using the following
    BAPI Fm: BAPI_PROCORDCONF_CREATE_TT .
    Regards
    Sathis

    BAPI_PRODORDCONF_CREATE_TT to confirm a production Order
    Erwan

  • Order type dependent parameters for process order

    Hello friends,
    In Order type dependent parameters for process order (T.C COR4), there is subscreen for Process data documentation.Inside it we have three options :a) Batch Record Required
                                                                        b) Order Record Required
                                                                        c) No Process Data Documentation Reqd.
    Through F1 help whatever information i have got regarding them, is not cleared.
    According to it, if i select Order Record Reqd, than first of all i will have to delete (archieve) the order record than only i can delete (archieve) the process order.The same is with Batch Record Required.
    So according to it if i want to delete the  process order than first i will have to delete order record.So guys may i know which order record firstly i have to delete?Than only the system status for process order will not have the status ORRQ (Order Record Reqd).
    And one more thing friends,if i select the third option No Process Data Documentation Reqd than which process data documentation system will not create?Or what will happen if  i select this third option?
    Thankingy you guys in advance.

    HI
    For process data documentaion pls check the following link:
    http://help.sap.com/saphelp_47x200/helpdata/en/89/a43ea8461e11d182b50000e829fbfe/frameset.htm
    Thanks

  • For process order matrix

    Hi All PP Gurus,
    Scenario from production client:
    Issue:
    For process order number 6300355; material code 15010163 the assay calculation is not correct.
    Process in use:
    Process order is created through tcode COR1 and Transaction code ZACOR2 is used for update of requirement quantity, i.e. assay calculation. The quantity calculated against batch no. 0001004480 is not correct. The correct value is 14.013.
    can u please help me regarding this issue?????

    your question looks to be very vague as you are giving order no/material no/ batch no which no member can view. explain more detail about your scenario and issue so that somebody may try to help. sorry for putting my view in direct manner.
    Thanks
    JK

Maybe you are looking for