Movement type specific to Order Type
HI
I have created new movement type Z01 instead of 101 and I want to use this Z01 for specific order type and for Others system should take into account standard 101 movement.
I have checked movement type setting in PP but it client level setting and is applicable to all order types if i change it.
Please let me know if its possible.
Regards,
Anand
Anand,
GR Movement types are specific to package area(PP, PP-PI, REM etc..), so it is not possible to have it defined for specific order type within a package.
What I mean is that you can have GR for PP(Production orders) as 131 and for PP-PI(Process orders) as 101 but within PP you cannot have diffferent movement types defined.
Regards,
Prasobh
Similar Messages
-
Ugent: How to restrict a Material Type for a Specific Process Order Type
Hi All
Can any one please tell me how to restrict material type for specific process order type
We have Process Order type ZPBS for finished materials but while creating process order
if i give the material of semi finished material type the system let me create the process order
it should not as we have a separate process order type for semi finished materials that is ZPBS.
And vice versa
Please help me how to restrict these material types for specific Process Order Types.
Points ll be awarded accordingly
Bilal AtharHy Ghulam Mohammad,
Good Morning,
Pls go through below link
[http://www.sap-img.com/abap/what-is-user-exits.htm]
[http://www.sap-basis-abap.com/sapab013.htm]
Now regarding How to place your checks in User Exit, then pls explain your requirements to your Abaper , so that he or she can write it into programeble language.
Regards,
Dhaval -
Internal Batch Number for specific Production Order Type
HI PP Guru
We need to activate Internal Batch Numbers to a specific Production Order type.
We need this at order confirmation level. i.e. (CO11/CO12)
Is it possible? HOW ?
Please let me know customizing Steps.
If this is not possible then, Batch number should be internally assgisned at Order release stage. Please let me know customizaing steps for this even.
Thks.hi Siva
Thk for suggestion
However, if we do not wish to activate Internal Batch Assigment and want to remain on manual BUT still we want system should not allow duplicate BATCH NUMBER, then, is there any way to achive this.
This is because, once we manually enter batch in confirmation (CO11), we further break the material in to several part and we need to understand original batch number. For this we just take the original batch number and add further serial number like below
Orinigal Confirmation Batch Number - 100001
Batch Split of 10 - 10000101,10000102,..............10000110.
So, what we want is system should check that same batch number is exist or not in confirmation. Is it possible or how it can be handle.
thk in adv.
SK -
REG Mvt type related to order types
Hi
For our Prod orders , goods receipt will done with mvt type 101. i need to create a new order type for which i need a new mvt type have to be used for goods receipt for those orders. is it possible to change the mvt type as required for goods receipts.
Regards,
PradeepM.Hi,
Such type of changes should not be preferred because it imapct alot.
As you see that it depends upon package & package not depend upon any field value, it depends upon table & fileld, so PP order type package should be same, so you can't give seperate package for a specific order type.
Order type package depends upon order category which u can check in OPJH, but u can't creat any new order category .
because it has alot of technical settings so SAP not allow it.
Now there is two way to resolve ur issue.
1. Brief why you want seperate movement type, if u want it for information then there were alot of fields u can use in place making so big changes.
If u want seperate GL then you can easily made it by introducing new valuvation class etc. so check ur original requirement.
2. If you hard & fast want to change Movement type then take it under process order category, and u can give seperate movement type for this order type, you can easily avoid control recipy in process order so it become very much similar to discrete order.
Thanks........Rakesh -
Document Type specific to Application Type
Dear All,
Can any one guide me how to configure Document Type specific to Application Type in DMS.
What I mean, Doc Type 'DRW' should be used only ACAD Drawings, user should not able to attach or check in word document to it.
same time Doc Type 'DOC' should be used only word document , user should not able to attach or check in ACAD Drawings to it.
Thanks & Rgds,
Sukan
[email protected]Hi Sukan,
Go to Tcode<b> "DC10"</b> i.e. Define Document types
here you find the two fields <b>"Def WS Appl."</b> and <b>"Dis WS applic."</b>
these two fields are for specifying the Application you need for a particular document types.
so when you try to create a DIR and attach the Original by create or open then
by default you see the application what you have set in the DC10 for that particular document type but can be changed.
<i>So you need to put a check on field "<b>DAPPL"</b> i.e. Authorization check through Object <b>"C_DRAW_DOK"[/</b>i]
Regards
Rehman
Reward Your Points If Useful -
Settings for the relation of requirement type and planned order type
Dear Gurus
Where we maintain the settings for the relation of requirement type and planned order type?Actually I have maintained strategy 60 for a particular material (planning material) so the requirement type is vsev and along with that the planned order type is coming is vp i.e non convertible planned order.That is ok the system is behaving right.But nowhere I can find the setting of vp with vsev how the system is picking vp?
Regards
Sandip SarkarHi!,
That is an inbuilt sytem setting and you can't change that.
Regards,
Uday -
SAP QM Inprocess Inspection for a specific Process order type
Dear All,
There is a requirement. As no QM type is maintained for FG material in a plant. Now the requirement is there is a specific order type for which Inprocess Inspection is to be activated for all the FG materials. But at the same tie for all other order types there won't be any inspection for the same set of FG material.
I tried creation Z03 by copying 03 inspection type. But the problem is source inspection is from Production. So Z03 is not confined to only the specific process order but instead it is generating inspection lot for other Process order also.
Is it possible to create a scenario where we can attach inprocess inspection to a specific order type only.
Regards,
RahulHi,
You can assign the in process inspection to Order type in SPRO as shown below in the process order type dependent parameters in Planning tab in COR4.
Check and revert..
Thanks
Kumar -
Hello Gurus,
Can we restrict a specific order type of sales order in getting collected during the data collection, or is that the only way is customization, like remove all the sales orders with a specific order type after the data collection.
can somebody help me on this.
Thanx & RegardsYou can try defaulting rules to default the demand class so that you can exclude these demand classes during MDS..
-
Create Specific Invoice Document Type against Specific Sales Order Type
Hi,
the sales order types are
1) "ZORR" (copy of "OR")
2) "ZORS" (Copy of "OR")
both have different number ranges
the delivery Type is "LF"
invoice document type is
1) ZINR (Copy of F1)
2) ZINS (Copy of F1)
boht have different number ranges
now i want that when sales order "ZORR" is used, then invoice type ZINR should be created (when creating invoice w.r.t LF)
and when sales order "ZORS" is used, then invoice type "ZINS" shoudl be created.
right now, the system creates invoice "F2" whenever i create invoice w.r.t. to delivery order in VF01
dear experts...please sort this issue..thanksAssign Billing type in VOV8 .
ZORR" (copy of "OR") == LF== ZINR
ZORS" (copy of "OR") == LF== ZINS
So that when you create invoice with VF01 system will trigger invoice type ZINR for ZORR, and ZINS for order type ZORS.
Regards,
Ramesh -
Inspection type in OPL8 (order type dependent parameters)
HI,
Inspection type we are giving in material master in inspection type field, why we need inspection type field in OPL8 transaction. Is there any specific reason the field having in OPL8. Please advise me if any one knows the reason.
SriniHi,
Lets see it with the help of an example.
Lets say there is a material - X, which is supplied to two customers - A & B.
Customer A requires a quality certificate, while the customer B does not need any Quality Certificate or Quality Control. In such case, you can not assign the inspection type at material level.
Here, in this case, you would have 2 order types, one with Inspection Type assigned and the other order type without any Inspection type to meet such requirements. And that looks more practical in terms of monitoring the specific orders, costs incurred for specific order etc.
Revert for more clarifications.
Regards,
Rohit. -
Default PM Notification type to PM Order type
HI All,
Please any one let me know where I need to make setting to obtain the default Notification type from PM Order creation or change mode.
I have done some analysis i.e. I am able to obtain the default Order type for Notification i.e. when I click on create Order button in Notification creation or change mode (IW21 / 22). The pop-up window appears with default PM order type. To obtain the default value , we need make settings in SPRO i.e. Maintenance and Service Processing > Maintenance and Service Notifications > Notification Creation > Notification Types > Assign Notification Types to Order Types.
I required vice verse i.e. Default Notification type from PM Order creation or change mode. To obtain this I have checked any SPRO settings to make. Example: Maintenance and Service Processing > Maintenance and Service Orders > Functions and Settings for Order Types > Define Notification and Order Integration. But here the notification is immediately created, when we save the PM order. This is happening since the automatic creation check box (3 rd column) is checked in SPRO settings i.e. Define Notification and Order Integration.
I need the system to display the pop-window with default notification type, when I clicked on create Notification button in PM order create or change mode (Iw31/32). Please let me know where I need to make settings for this?
Regards
RamuHi Ramu,
Goto SPRO ->Maintenance and service processing ->Maintenance and service orders ->Functions and settings for order type ->Define notification and order integration.
Goto specific order type remove the check box in the third column.
Result:When ever you create the service order, notification is not created automatically.You have to goto IW32 goto create notification click on the icon then pop-up appears for the notification.Hope this solution resolve your problem.
Regards
Suman Kumar -
REM profile Product Type - Cost Collector Order Type
Hi all,
I am trying to create a Repetitive Manufacturing Profile, at that time standard Production Type PKMN is automatically arriving from table V_T437S_GES.
and I would like to assign the cost collector order type (self defined) to the REM profile which I am going to create.
where I need to assign the cost collector order type for production type "PKMN" while creating REM profile.
If I copy the exisiting REM profile and I am able to get the cost collector order type that I am able to see in TABLE : T437S (Repetitive Manufacturing Profile Table). If I create the REM profile newly, I am unable to get the cost collector order type in the table T437S.
So please guide to the self defined cost collector order type for newly creating REM profile.
Thanks in AdvanceMadhan,
Order type "PKMN", is internally defined by SAP. Forr all cost accounting purpose, we would be using standard order type "RM01" when creating a new product cost collector for material. If required you can create your own order type say "ZM02" using transaction KOT2, please remmember you need to create with order category "05"- Product Cost Collectors.
This new Order type can be used when we are creating product cost collectors for a material.
I really dont find a reason why a new Order type is required to be created. Can you explain why?
Regards,
Prasobh -
Assign PO Condition Type to Purchase Order Type
Dear Gurus,
I'm trying to assign a condition type which is currently not assigned to a specific PO type. Could anyone give me the flow of configuring PO Condition Types. Thank you VM
Regards,
Jinuu need to assign ur condition type to the procedure and then assign calculation schema to the vendor the procedure u define flows through the vendor master not directly according to the document type except stock transport order
-
Stoping Sales Order types from specific plant
Dear Friends,
My client want to stop creation of specific sales order types from a specific plant. Means if that specific plant entered in sales order then system should not process that sales order further.
Note : Material transference must not be affected while implementing above requirement.
Kindly suggest the solution in this matter.
Thanks & Regards,
SaviThe best way would be to prevent this through your organizational design (Enterprise Structure)
You can limit which plants can be used for each combination of sales org/distribution channel & you can define which order types can be used for a given sales area.
You can use exclusion procedure and records to stop the combination of orders type and plant. This is not a use fiendly solution as the user doesn't receive a very useful error message.
You can use the user exit as mentioned before. -
New internal order type--need help
Dear all:
i have a case need help.
now i want to create a new internal order type ,and assign a new number range and a default settlement rule to it .
the settlement rule is that the actual costs of this internal order type need to be
sent to a cost element .
what should i do step by step?
thanks!
best regards!Hi,
2. Order Master Data
2.1 Define Order types (KOT2_OPA)
IMG Controlling  Internal Orders Order Master Data  Define Order Types
An Internal order is created under an Order type. An order type is used for storing various control parameters and various defaults while creating an internal order. It is used for classifying various types of internal orders according to usage for e.g. Real orders for trade fairs, real orders for Capital investment measure, Statistical orders for motor vehicle expenses.
The order type is client-specific, which means that every order type can be used in all controlling areas. A number range is assigned to the internal order type.
Click on New Entries
Take a drop in the field Order category and select 01
Enter
Update the following
Give Order Type :- Z810
Description :- Traders First Real order type
Object Class :- OCOST overhead
Reference Order :- Collective order without automatic goods movement
Residence time 1 :- 12 months
Residence time 2 :- 1 month
Check Commit Management and Check Integrated Planning
Activate CO Partner Updating -You activate this so that allocations between orders and other CO objects (cost centers, projects, etc.), the partner information is retained and whether for each order a totals record should be written.
Save
Click on Field Selection
Here you can hide the various fields or make it as required entry or only display or available for input. Thus while creating internal order only those fields are displayed and available for input.
Click Save
2.2 Maintain Number Ranges for Orders (KONK)
IMG Controlling  Internal Orders  Order Master Data Maintain Number Ranges for Orders
Number Range needs to be assigned to the internal order type. Number range can be internal or external. In Internal numbering system automatically assigns a number from the given number range. In external numbering the user has to manually assign the number from the given number range.
We will configure internal number range for our internal order type Trade Fair
Click on Group Maintain (From the menu bar)
Click on Group  Insert (From the menu bar)
Update the following
From Number: - 910000000000
To Number: - 919999999999
Click in plus icon at the left bottom of the screen
Click Save
You will find internal order type Z810 in not assigned
You need to assign the order type to the group we created above. Proceed as follows:-
Position the cursor on: - Z810 Trade Fair real order type
Click on Arrow Z810 Trade Fair real order type note it turns blue
Select Check mark Z810 A ltd India fair real order
Click Element Group
The internal order type Z910 moves under the group which can be seen as follows:-
Z810: A Ltd India Trade fair real order / Z810 Trader Fair real order type.
Click Save
Select: - Z810: A Ltd India Trade fair real order / Z810 Trader Fair real order type.
Click on Pencil icon.
Click Back arrow.
2.3 Define Model Orders
IMG Controlling Internal Orders Order Master Data Screen Layout
Define Model Orders
Model orders are not orders in the commercial sense, but serve merely as references for creating "normal" orders. Model orders contain default values for the orders in an order type. The Model order is assigned as the reference order in the order type.
When you create a new order, all the fields active in the relevant order type are copied from the model order to the new order.
Example
You want to settle all your marketing orders to the same sales cost center. Stipulate the cost center as the default value in the model order for marketing orders.
When you create a new marketing order, the system defaults this cost center. If you want to settle the order to a different cost center, you can overwrite the default cost center in the orders.
We will create a model order with some defaults and assign it to the Trade fair internal order type
Click Create CO Model Order
Press F4 and select ($$) 03 model order
Click on the master data and update the following
Order: - $$$ Z81000001
Description text: - A Limited Trade affair
Click Save
Assign this model order to the order type Z810
Update the reference order with the model order number $$$Z81000001 in the reference order field
Click on save.
3 Planning
3.1 Maintain User-Defined Planner Profiles
IMGControllingInternal OrdersPlanningManual PlanningMaintain User-Defined Planner Profiles
Check the User defined planner profile ZOCM91 created by us contains the layouts for internal orders.
Double click on General controlling
Planning area: Cost element/activity inputs.
Cost Center: Activities/Prices
CCtr Statistical key figures
Orders: Cost Element/Activity inputs
Ord: Statistical key figures
Select :- Orders: Cost element/activity inputs
Double Click on Layouts for control
3.2 Maintain Planner Profile for Overall Planning (OKOS)
IMG  ControllingInternal OrdersPlanningManual PlanningMaintain Planner Profile for Overall Planning
Here you can specify the time frame for which values are to be planned for Internal order. Further you can also default the number of decimal places and the display factor. Default cost element group while planning.
Double click on Define planning profile for overall planning
Click on New Entries
Select 05 Planned Total
Profile: 810000 General Plan Profile A Ltd
Click Save
Select back arrow
Double click maintain planning profile for order type
Give: - Z810 Trader Fairs Real order type
Give Plan profile: - 910000
Click Save
4 Settlement
4.1 Maintain Allocation structure
IMG ControllingInternal OrdersActual PostingsSettlement Maintain Allocation Structures
An Allocation structure comprises one or several settlement assignments. An assignment shows which costs (origin: cost element groups) are to be settled to which receiver type (e.g. cost center, order and so on)
You have 2 options:- You can settle to a settlement cost element or settle by cost element i.e. settle using the original cost element.
We will use settle by cost element.
Click on New Entries
Allocation stru :- Z8
A Ltd : Internal order settlement structure
Click Save
Select Z8 Internal order settlement structure
Double click on Assignments
Click on New Entries
Assignment :- 10 Settlement Primary cost Element
Click Save
Select 10 Settlement Primary cost Element
Double Click on Source
Give From Cost Element To Cost Element
Save
Click back arrow
Note:-The color has become green
Select: Settlement primary cost element
Double click on Settlement cost
Click New Entries
Select CTR Cost Center
By Cost Element Check
Save
4.2 Maintain Settlement Profile
IMG Controlling Internal Orders Actual Postings SettlementMaintain Settlement Profile
Here we define a range of control parameters for settlement.
Double Click on Maintain Settlement Profiles
Click on New Entries
Select Settlement not allowed
Assign the allocation structure Z9 created earlier in the settlement profile.
Click on Save.
Select Back Arrow
Double Click on Enter Settlement Profile in order types
Give Settlement Profile Z9100
Click on Save.
4.3 Maintain Number Ranges for Settlement Documents
IMG Controlling Internal Orders Actual Postings SettlementMaintain Number Ranges for Settlement Documents
You should define separate number range intervals for settlement documents for each controlling area.
Click Group  Maintain
Click Group Insert
Update the following:-
Give From Number 1000000000- To Number 1999999999
Click on + at the bottom left side.
Click 8100
Click on Arrow icon.
Select Settlement documents for A limited Check box
Click Element group button
Click SAVE
Assign Points
Zia
Maybe you are looking for
-
Database 8i OS wndows 2000 server RAM 1.5 GB SGA 1136617500 bytes getting error ORA-04030: Out of process memory when running dbms_stats.gather_schema_stats procedure. after reducing e size of sort_area_size from 40 M to 10 M above procedure has been
-
My default out-of-the-box Oracle Portal's On the WEB currently says "No external applications have been selected for display. To select applications to display, click "Customize"." When I click the customize link I get the following error. Error: The
-
How to create the Transport of copies programatically
Hello, I am using a BAPI - BAPI_CTREQUEST_CREATE to create a Transport Request, But it creates a Local Transport Request (without destination), While i want ot create a tranport of copies with destination, is there any way i can do that thr this bapi
-
Work flow for Rejections in Quality- Usage decision
Dear all We are in the process of activating work flow for Quality Inspection, During Usage decision there may be rejections for which we need to trigger a mail to the Internal department , stating the Remarks, description, rejected quantity etc , If
-
How do you change a read only file?
I copied a document to my email address but it's in the read only format and I need to make some changes but I can't. What do I need to do?