Hi All,
After running MRp, the planned orders and Purchase requisitions are created. What should I do, to make the dates of these Proposals to not fall on saturdays and sundays..

Hi,
    Use OP03 :
            1.select plant assignment and check which calendar you used(third column)
            2.go back to OP03 and select Maintain calendar,select factory calendar..find the calendar you used and change it..(in the workdays fields:pls uncheck Saturday Sunday)
            3.rerun MRP

Similar Messages

  • Schedule lines should not change 3 weeks time from MRP date

    Hi
    Is there any specific customisation required to get following results in case of schedule lines.
    1) MRP should not change/adjust the already send delivery schedule lines  which are lying within 3 weeks time from MRP date
    2) System should not allow to book the GRN unless the messages / print out has been generated from the system in case of scheduling agreement.
    Thanking you
    Shantakumar
    09944009752

    Hi,
    There are 2 possibilities:
         1. use MRP fixing using planning time fences, this is done by putting the relevant settings in the MRP1 view of the material master
         2. use the firming options of the scheduling agreement, these are set per material number that is entered in the scheduling agreement.
    The GR can only be posted for schedule lines that have been processed aka output generated.
    Regards,

  • Costing error while change mrp data in material master

    Hi dears,
    This is Rem process. when i try to change the material master MRP data ex. ( mrp type M1 to M0)
    system not allow to change and show the error as
    Product cost collector 000000750122 is still active (assigned to PrCtr 50601-025)
    i need to change the mrp data in mm02 and i donot want to do delete the pcc .
    any process to carryover
    thanks
    Edited by: raj on May 24, 2010 12:22 PM

    Hi,
    MRP is mainly configured for a material so that tere would not be any need for manual checking of the stock so as to create a PR. 
    The parameters which you have specified for a particular material like reorder point and lot size will help in planning for a particular material.
    If you need only Qty of two (Less) then  there s no need of configuring a MRP for that material
    And lot size is also decided basing on certain other factors like
    1) Lead time
    2) Transportation costs involved in procuring the material etc
    So ifyou want to generate PR for a qty of 100 then you need ot change the lot size
    I hope this gives you clarity
    Thanks & Regards
    Pavan

  • Costing error while change the mrp data

    Hi dears,
    This is Rem process. when i try to change the material master MRP data ex. ( mrp type M1 to M0)
    system not allow to change and show the error as
    Product cost collector 000000750122 is still active (assigned to PrCtr 50601-025)
    pls give some hints to clear
    Any program is there to change the MRP data for the material master in production server directly
    thanks

    Dear ,
    Did you try MASS or MM70 Transction ?
    If you do not want to go for Deletion flag of PCC  , you need to settle the REM qty  .You need to do product cost for semi finished product and finsihed product in KKF6N and after that you have to do mark and release in CK24N .For standard cat Estimate create std Cost estimation(CK11n)  and std cost Estimation Mark & release(CK24) .
    1.Backflush (confirmation) the Planned order - MFBF. Results planned order will Reduced and GR,GI, activity cost will be posted. U need not convert the planned order to production order, Confirmation for planned order only.
    2.To see Backflushed documents MF12
    3.Then Goto KKF6n to see the Manufaturing cost.
    4.Over head calculation - (Co42)
    5. Variance calculation (KKS6)
    6.Settlement(KK87)
    Try and revert back
    Regards
    JH

  • Report MRP data - Fixed Vendor

    Hi All,
    I am trying to build a report by query, to display MRP data and related fixed vendor (if available).
    I tried joining the tables MARC, MAKT, EORD and LFA1, but did not get the output as desired. The report shows only the material with a source list.
    Please, could you help me to display all the records (with or without fixed vendor)? How can i use a outer join?
    Thanks in andvance.
    Antonio
    Edited by: Antonio Bruno on Jun 22, 2011 10:40 AM

    Can use the inner join directly in the infoset by add a table.

  • MRP Date in MRP List

    Hello All,
    While accessing the MRP List (collective access MD06). There is a selection option for MRP Date. SAP Help tells that "Date: for example, all MRP lists that were created or processed within the last two weeks".
    But I could not understand what this means. Please clarify this.
    Regards
    Mahesh

    Hi
    It means that, the MRP list will be displayed only for those materials that were created in that time frame. There might be materials for which MRP is not run and processed within that time frame. they will not be displayed. This is one of the parameters for filtering the list.
    Hope this is clear and helpful. If so please reward
    Chandra

  • MRP Data Tables

    Dear Experts
    Pl tell about the MRP Data Table Where the Data Is stored .
    Like Requirement qty , Plant Stock,Open Purchase order, STO,subcontracting , Shortage qty.
    tables which will help me out to get the data from table .
    Rgds
    Pankaj Agarwal

    Dear use the following function module to get the details of what you are asking
    MD_STOCK_REQUIREMENTS_LIST_API
    Give plant and material number and execute...you will get all the data.

  • MRP Data in BW Has anyone did this before?

    Folks, I am trying to get the MRP data into BW and found that I could use the 2LIS_03_S194 extractor.....but here are a few things I am struggling with:
    1. It cannot support Delta...
    2. I am getting an error message when I extract the data or even do a RSA3 on the data source, the message reads "Faulty DataSource 2LIS_03_S194 or error in LIS environment for S194"
    Here is what I did
    1. Install data source from RSA5
    2. LBW0 (This gives an error "Generation not possible in SAP name Range" so I guess we do not need to generate the data source at all.
    3. If I look at the generation Log, it says this information strucutre cannot be used for SAP BW
    4. I used the program RMCBMRP2 and filled the S194 table and dsaw that it has data in it
    5. Next when I did a RSA3 it fails with the message I gave earlier "Faulty DataSource 2LIS_03_S194 or error in LIS environment for S194"
    also is it recommended to go for full loads everyday ? or can we just do a date based selective load every daya after the first full load?

    Ram,
    Try this:
    1. Delete the data in S194 table using transaction LBW2
    2. Fill the table S194 by running program RMBCMRP2 with transaction SE38
    3. Fill the following parameters for the initial load
    From Data: Some date in the past
    To Data: Current Date – 1
    4.After filling the table, log in to BW and run the full package which will load all the records into the cube.
    5.For delta, schedule the job in R/3 by setting up a variant for the program.
    a.Variant for the program should be set as specified below
    b.Do the same setting for ‘From’ and ‘To’ dates
    6.After saving the variant, schedule the job on R/3 side.
    7.Info Package configuration for daily loads on BW side.
    Use the package with above configuration in the process chain so as to get yesterdays data.
    Note: One important things to keep in mind is that R/3 job should be scheduled after 24:00 hours so it picks ‘yesterdays’ date and the same holds true for the BW package.
    For some reason if anytime you have to drop the data in the cube, then you will have to perform the setup from step 1 to get complete data.
    also check this thread:
    MRP list
    assign points if helpful
    kalyan

  • MRP Data from Live Cache

    Hi
    Please let me know the FM/BAPI which will get me the MRP data from Live cache.
    My requirement is to get the date and quantity for each element, MRP elements to be used are VC,VE,LF based on the plant and material
    Thanks in advance
    Amit

    Hello Sebastian,
    FM '/SAPAPO/OM_PEG_CAT_GET_ORDERS' seems to cover my requirements and I'm happy I found out about it here. Unfortunately I have some problems testing with SE37:
    Specifying only PEGID together with needed categories was not successful. Searching for calling programs of this FM I found FM '/SAPAPO/ATP_DISP_LC_SINGLE' which additionally sets parameter IS_GEN_PARAMS-SIMVERSION to '000' and receives the correct values.
    Now I have the problem that with setting the same input values I still receive exception 'LC_APPL_ERROR' and don't know why. Since I'm new to APO it could be some basic setting, still I'm wondering why this could be. Hopefully you can provide some helpful information, otherwise I think I'm lost
    Thanks in advance,
    eddy

  • Table of WBS MRP Date Data

    I want to know all MRP Run Dates for a WBS Elements i.e all the dates in which MRP is carried out for that particular wbs. Please Reply ASAP.
    Thanks

    Dear,
    Yor question is not clear. Are you looking for the PS driven MRP data?
    You will get the data in MD4c...enter the Project or WBS..you will get the required data
    This data is not comming from one table
    Try using FM-  MD_STOCK_REQUIREMENTS_LIST_API

  • Extracting MRP Data by GR date instead of AV date

    For reporting purposes I  have a requirement to extract the MRP data by GR date, not the default AV date. I have looked at all the FM's and the BAPI's I could find and cannot seem to get the data as required.  I see that in MD04 you can change your user setting to default to GR date, so I assumed that there is a similar configuration or FM parameter that can do the same.  So far I have not found a solutoin. Short of writing a custom ABAP that mimics the MD04 GR button for every plant/material I'm  hoping someone has a better suggestion.

    For reporting purposes I  have a requirement to extract the MRP data by GR date, not the default AV date. I have looked at all the FM's and the BAPI's I could find and cannot seem to get the data as required.  I see that in MD04 you can change your user setting to default to GR date, so I assumed that there is a similar configuration or FM parameter that can do the same.  So far I have not found a solutoin. Short of writing a custom ABAP that mimics the MD04 GR button for every plant/material I'm  hoping someone has a better suggestion.

  • Past MRP data

    Dear all,
    My client want   report with comparision of 2 MRP result  like ( no planned order , purchse order before and after MRP )
    For developing a Y report : Can you suggest me from where i get resutls of past MRP ? system should store data some where even if in frontend it is deleting and creating planned orders/ PR's again
    Please guide
    Ishwar
    Edited by: Ishwar on Jul 27, 2009 4:02 PM

    Ishwar,
    Although you think the system SHOULD store historical MRP lists, it doesn't.  You can get MRP to output the lists to a spoolfile, but this data format does not lend itself to data extraction (transaction MDLD)
    You will have to create your own storage methodology. 
    MRP lists are usually stored in a cluster, which are not directly readable.  Your storage will probably be easier if you change config for MRP such that it stores the MRP lists in Transparent tables.  IMG>Production>MRP>Check of performance settings>Check storage mode for MRP lists.  Select all checkboxes that are relevant.  THERE WILL BE A PERFORMANCE TRADEOFF.
    You could then easily copy data to your own Z tables, and manage and report these data anyway you want.
    Rgds,
    DB49

  • MRP data MD04 Data Extractor (not MD05)

    Hello,
    Is there a SAP-delivered extractor for MD04 data? All the previous threads on this topic equate S194 extractor to MD04. The S194 based extractor delivers MD05 data not MD04.  MD05 will generally equal MD04 if you do a fresh MRP run.

    Hi,
    2LIS_02_SCL does not deliver MD04 data. 2LIS_03_S194 is the closest with the limitation that it is only as good as the last MRP run.

  • MD04 MRP Data Element for Production Order add Order Status

    Hi,
    Currently in MD04 when you create a production order it gives the status in MRP Element Data as 000001138145/YP01/ and once I release this is shows the following status 000001138145/YP01/Re
    I want to bring another status in how can you do this?
    Thanks
    Adeel Sarwar

    Dear,
    It is not possible in standard SAP to display the Lock production order as status 'Locked' are taking into consideration with regard to availability relevance in the MRP. MD04 display only those MRP element which are relevent for MRP calculation.
    So better check this order in COOIS with LCK (Locked Status).
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Calculate stock reach based on MRP data by date

    HI
    I have a challenge that I'm unable to solve by myself - I hope you guys can help me out:-)
    I have an ODS containing current stock and expected future movements of different types. In the ODS I have (simplified):
    1) Material
    2) Date of movement
    3) Type of movement
    4) Quantity (with +/- sign)
    I need a query that will return for each material (in the rows) either the date when the stock will reach 0 or the number of days until that movement occurs.
    My ODS could hold the following data for a material:
    Mat  date     Type      Qty:
    1                  Stock      +100
    1       01.01  Sales         -20
    1       05.01  Sales         -70
    1       10.01  Sales         -50
    In this example the query should return "10.01" (which is the date we will run out of stock) or the number of days between today and that date.
    I have experimented with the "cumulated" option and conditions in kfy definition in query designer, but since cumulation is only for display I can' use that.
    I can't build a cumulated value into the model either, because there are several movement types and sometimes the user needs to only take some of them into consideration.
    Since consumption is very non-linear I need the exact date we run out and I can't base calculations on average data (like average daily sales).
    Does anybody have an idea how to solve this?

    Post Author: Tned
    CA Forum: Desktop Intelligence Reporting
    Thanks Prashant
    However, when i add either the status or condition variables to the report all lines related to the ID are returned not just the last entery by date.
    Thanks again.Terry

Maybe you are looking for