MRP in Background (MTOs)

Hi All,
I have two types of strategy groups MTO and MTS. But i need the background JOB for MTOs only. I have done the settings in MDBT (Variant) and SM36 (Setting up of Background Job). But the system is running the background job for MTS and MTO also.
I only need the background job for MTOs only  not for MTS materials. As i have checked bu8t unable to find a link to set the background job only for MTOs.
How can I do this?
Please advice me for the same.

Hi Neeraj,
According to SAP online help the following options are possible via user exit M61X0001:
- only materials planned using MRP or
- only materials for a particular MRP controller or
- only materials procured externally or in-house
http://help.sap.com/erp2005_ehp_04/helpdata/EN/b4/d2e0d6a31411d3b52b0004ac160649/frameset.htm
Regards,
Csaba

Similar Messages

  • MRP IN BACKGROUND

    Hi Gurus,
    How to set MRP at multiple level (MD02) in background? Which program is used to set it in background?
    Please provide me step by step details.
    Regards,
    Pradeep

    Dear Pradeep,
    RMMRP000 is the program that will be used for running MRP in background.
    This can be scheduled via SM36 or else by creating a variant and scheduling through T code MDBT or else you use the variant
    created in MDBT and schedule using SM36.
    Results can be checked using SM37.
    Regards
    Mangalraj.S

  • MRP in Background for MTOs

    Hi All,
    I have two types of strategy groups MTO and MTS. But i need the background JOB for MTOs only. I have done the settings in MDBT (Variant) and SM36 (Setting up of Background Job). But the system is running the background job for MTS and MTO also.
    I only need the background job for MTOs only  not for MTS materials. As i have checked bu8t unable to find a link to set the background job only for MTOs.
    How can I do this?
    Please advice me for the same.

    Suresh,
    You can activate user exit for MRP run. Once the user exit is activated you need to define the user exit key in SPRO as what that key is(In this case Planning strategy), and in the user exit you can ask the ABAP person to select materials based on the user exit key which should be MARC-(strategy group-field name).
    Now you can create a variant with user exit key and value "20"- for MTO. with this the MRP would be run for only materials which have planning strategy 20.
    Regards,
    Prasobh

  • Error in MRP Run- Background Job.

    Hi PP Gurus,
    I defined scope of planning for two plants and defined counter too. And set background job through Transaction code MDBT taking 24Hrs as Schedule selection parameter.
    When I'm accessing MDBT after 24Hrs system is throwing following messages in Scheduling log:
    1. Please check the destination for Parallel MRP (message no. MD251)
    Diagnosis of Message:
    No destination have been entered in Customizing or none of the destinations (application server) entered are active. In Customizing for MRP, you define the logical destinations (servers) to be used for parallel processing.
    2. Job cancelled after system exception ERROR_MESSAGE (Message no. 00564)
    Though I tried to enter to Customization through Message no. 1 but system is not allowing for it.
    What could be the problem. No help is available through any OSS note also.
    Please suggest the required solution in terms of Configuration or any other changes?
    Thanks & Regards,
    Abu Arbab

    Hi,
    Two more queries:
    1. If I don't want to go for Parallel Processing MRP, I don't have to select 'Parallel Processing' in Transaction code MDBT variant. But when I'm trying to change it system is not allowing me. It's not allowing me to go further without selection of it. What could be the reason behind it? Either Customization problem or any other?
    2. If set 'Parallel Processing destination' through Customization, system is giving only Development server as available destination and also Customization Request is getting generated. But the request is going to be transported to Production server. Since Parallel Processing destination was selected 'Development server' earlier and now MRP will run on 'Production server', it has to be changed to 'Production server'. But as already mentioned Customization Request will be getting generated and further it is freeze for Customization. How could get rid of these issues?
    Please come back with prompt comments.
    Thanks & Regards,
    Abu Arbab

  • MRP run for MTO

    hi gurus
    I have a finished product and I have two level BOM for this and I maintained strategy group for the finished and semifinished as 20 and in MRP4 view in the field BOM explosion I have'nt maintained any indicator.When I run mrp in MD02 transaction two planned orders are getting generated for the same item one is for subreq for finished product and one is for sales order.
    Please clarify on this.
    thanks
    ravi

    Hi
    To generate Procurement proposal as per Strategy 20. System requires Sale order. See how many sale orders are there for Fert in MD04 .
    Do not use Strategy for Dependent requirements and otherwise if you pass PIR to this level. Always use strategy for header material.
    Regards
    J.Saravan

  • In MRP for changing MTO to MTS for raw materials

    Hi guys,
    I am getting one problem that i have changed for raw materials fron individual indiactor to clollective indicator to get its Purchase requistion for MTS. But in MD02 or IN MD04 it is still showing PR for individaul sales order in some cases.Can you pl.tell me why it is so.
    regards

    Please check the following..as Mat.master settings may be overrided as per below..
    You can maintain this indicator in the following places:
    In the material master record
    For the explosion type of the BOM item (in Customizing for Basic Data in Define Explosion Types)
    The setting for the explosion type overrides that in the material master record.
    Dependencies
    If the material is assigned to a material type that does not allow quantity-based inventory management in this plant, you can set the indicator to individual requirements only.
    If the stock is to be managed in sales order stock or project stock, the indicator must be set to one of the following options:
    Individual and collective requirements
    Individual requirements only
    If a material managed in project stock is to be procured from another plant using a cross-company-code stock transport order, the indicator must be set to 2 (collective requirements) in the issuing plant because, in this specific context, individual project stock management is not possible in both plants.

  • Background mrp in mdbt

    i want to run mrp in background for my new plant.
    i created variant for that plant and sched weekly and also i defined parallel processing in MRP. but mrp happened without selection of material???
    there is no error msg in list of scheduled request...

    Hi Prakash,
    In MDBT transacton choose the variant & then click the "Display scheduling" tab. Check the status against the date, if it is "Finished". Then choose this row & click results.
    Now choose the ABAP List icon under "Type". Here the MRP run result will be displayed.
    Check the processing key used, If this is the first time then use NEUPL, else set as NETCH & then run.
    If MRP is active for the plant & planning file entries exist, then the materials in the plant are to be considered during MRP run.
    You can check the MRP run results for a single material using transaction MD02/MD03.
    Regards,
    Senthilkumar

  • How to stop Background MRP ?

    Dear All,
    I have run Plant MRP in background by MDBT for every minute.
    that's why  system is taking MRP run at every minute.
    I have tried to stop it but it doesn't stop & caring out the MRP in background for every minute.
    Please give me valuable input to stop it.
    Thanks in advance.
    Vijay Mankar

    Vijay,
    Use transaction SM37, in the intial screen input the program name and job name and execute the transtion with "Scheduled" status check box active. Once you get the scheduled job go to change mode from menu bar Job--->Change or Ctrl+F11. In the change job screen hit the "start condition" function button and here you change the frequency of this the periodic job.
    Regards,
    Prasobh

  • Foreground transaction will affect Background run of MRP

    Hai PP Gurus,
                          When we run MRP in background- does foreground transaction will affect.
    Regards,
    Mohanraju

    Thanks for your information Tajuddin,
                 If i carry out transaction like (Confirmation of Production, creation of purchase requistion, Delivery to Customer). Does it effect on MRP which is running at background.
    Regards,
    Mohanraju

  • Auto MRP run in SAP R/3

    Hi all,
    My query is that , how can I run MRP automatically on a daily basis in SAP R/3. Is there definite settings for it?
    Thanks

    Hi,
    Automatic MRP can be schedule at plant level only and from MDBT (MRP in background) and MD01 (MRP in foreground..this is not advisable) transactions.
    You can schedule this either from MDBT transaction or from SM36. You first have to create variant for MRP program RMMRP000 for your plant with MRP controlling parameters from SE38 transaction if you want to schedule from SM36 and schedule as per your requirement like daywise, weekly or monthly.
    rewards for all useful answers.
    Regards
    TAJUDDIN

  • Back ground job for automatic MRP run

    Hi pp guru,
    my client want for a particularly  material no XXXXXX ,there should be automatic MRP rum daily at 8:00 pm.
    kindly suggest me how i will map  back ground job in sap..
    regards
    Aqueel

    Dear Aqueel,
    1.Either make a copy of the MRP type say PD and assign the new MRP type to that paticular material.
    2.Or else assign one MRP controller sepecifically for this material.
    3.Activate the User Exit M61X0001 which allows to run the MRP in background based on MRP type or
    a MRP controller.
    4.Create the varaint for running MRP in MDBT.Schedule from here.
    or else use SM36 select the program RMMRP000 and select the variant and go to scehduling and
    select the time and execute.
    Regards
    Mangalraj.S

  • MRP in Mode 3 not running

    Hello All,
    While running MRP in background with mode 3 the proposals are not deleted & recreated or even not rescheduled with the changed lead time in the master recipe.
    But with the same parameters MD02 is perfectly behaving as expected.
    I have even ran the Planning file entry & consistency , Still not solved.
    Please help me...
    Regards
    Mahesh

    Hi Mahesh
    I think the material does not have planning file entry flag...
    Different from MD02, MD01 or MRP background job (MDBT) always require planning file entry flag to schedule certain material.
    (In MD02, it does not require planning file entry flag to carry out MRP.
    So even you delete planning file entry flag that exist in table MDVM / DBVM<In
      case of MRP area is used>, you can still carry out MRP to material).
    However MD01 and MDBT (program RMMRP000) always require planning file entry flag. So if certain material does not have any flag, this material is not scheduled during MRP.
    Planning file entry flag is set when certain action is carried out.
    -Creating Sales order
    -Adjust PIR
    -BOM change
    -Material master change (but not all field change. Only MRP relevant area change)
    *If you change routing or Master Recipe change, this does not update planning file entry flag.  So in this case, this material have to wait other action that trigger MRP or schedule this material from MD02 or carry out MRP with NEUPL mode.
    (For this behavior please check SAP Note  88669)
    Best Regards
    Keiji

  • MRP run for requirement plan

    Hi Experts,
    Please tell me following.
    I have created one requirement plan in MD61. I want to run MRP for that. As I know we can run MRP for Material & product group in MD02. So please tell me how to run MRP for requirement plan.
    Regards,

    Hi Raja,
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/62/32b8371a2c9912e10000009b38f889/frameset.htm
    You can run MRP:
    - at plant level (total planning)
    - single material, multilevel
    - singel material, single level
    - run MRP for SO (MTO envirinment)
    - run MRP for project
    You can use user exit if you want to give further selection criteria for toatl planning run:
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/b4/d2e0d6a31411d352b0004ac160649/frameset.htm
    But as for your question:
    Based on your setting (config + master data) MRP will consider IndReqs inputted in MD61. There's no further selection criteria to make MRP understand you want to run it foer IndReqs.
    Just use MD01, MD02, MD03 and if your settings are proper system will consider them.
    Regards,
    Csaba

  • Mix Planning (MTO + MTS)

    Hi...
           I have Stock of One raw material (Trading Material) of Quantity 10.
    Now i created Sales order for Quantity of 50 qty...Now my requirement is that after MRP run, system should consider the the available stock (10 nos.) also after generating requirement PR of qnty 40 should have reference of Sales Order,Customer Specific PR.
    How to map this , which strategy i have to use for this material, as it mix of Make to Order & Make To Stock kind of Scenario.
    Expecting Positive reply Soon

    I'm afraid you are waiting for positive reply for vain.
    As per my best knowledge there's no mix MTS / MTO scenario in SAP. Whether you use MTO or MTS but you cannot mix them.
    You can maintain two planning strategies for your planning strategy group (that is assigned to your material in MRP3 view of material master) and use one of them in the SOs according to your wish...
    SPRO > Production > Production Planning > Demand Management > PIR > Plannng Strategy > Define Strategy Group (V_T461P) - you can give a main startegy and some alternatives for the same strategy group...
    ...but even though you define one MTO and one MTS strategy for your strategy group MRP will consider MTO SO as MTO SO and MTS PIRs as MTS PIRs. I mean you cannot consider normal (not-assigned stock) for MTO SOs (for which MRP plans in the SO special stock segment). And you cannot create PR with SO reference by MRP for MTS requirements.
    Strategy 40 is mix of MTS and MTO (you can consider SOs) but it also can't fulfill your requirements.
    Just my opinion...
    Regards,
    Csaba

  • List of materials planned in a MRP Run

    Hi,
    We are running MRP through background job...after completion of MRP Run how to see the list of materials planned in that particular MRP Run...
    plz help
    Thanks
    Kumar

    Hi ,
    If you goto  BG job logs in SM37-Enter Job name or user name -Execute  and then Hit the Spool  and Mark the Spool chek box against the spool number generated after the job finished  and click on detail ( magnifying glass)- Here you will get the list of materials for BG run of MRP.
    Regards
    JH