Hi,
I have a in-house production material, which may need to be manufactured as following 3 operations:
operation 10    (opitonal operation)
operation 20    (opitonal operation)
operation 30    (<b>mandatory</b> operation)
Current situation is, if the machines are good, only one operation 30 is enough;
but if there's a little problem with the machine, operation 10 and 20 are needed
individually or both after operation 30.
so  how to solve this kind of problem?
Thanks and best regards.

Hi,
Thank you all very much for your expertise.
If these  3 operations are all needed for some time, how to
perform production order confirmation?
<b>Does it  need 1 time for each operation individually as follows:</b>
e.g.
        1st time    CO11N  +operation 10  --- collect manfacturing costing
        2nd time   CO11N  +operation 20  --- collect manfacturing costing
        3td time    CO11N  +operation 30(milestone) --- collect manfacturing costing & GR
<b>         or only perform once for the last milestone opertion 30?</b>
e.g.
                        Only 1 time    CO11N  + operation 30 (milestone)
Thanks and best regards.

Similar Messages

  • OPERATION DETAILS IN ROUTING

    Hi Experts
                  In the operation details of routing- CA01 there is control -either based on time or Quantity for every operation. What it mean. If time based is it denoting the time for the particular operation. What it mean if "quantity based " is preferred.Can I have details please.
    Also will you give a scenario with some operations mentioned where I can use routing.
    Pranav

    Hi Gajesh, Thanks
    I take your case - "Suppose you have 4 operation. Forming, lathing , quality checks and painting. Normaly in production system you will have a quality check in between the process".
    here check necessary in 3rd step - quality check. So am I to select time based / quantity based for operation -3 only ( because only it will have MIC ). Can I go without selecting time based / quantity based option also (if so how - what option i need select in the operation details for the 3rd operation). 
    Next, in CO11N. I confirm operation -1 ( here what option I hav to select - either partial confirmation / final confirmation). As per my logic, only partial confirmation need to be selected (what quantity I hav to enter here for yield- is it the total production order quantity = total target quantity).
    similarly, 2nd operation- lathing- I select partial confirmation- enter yield/scrap etc
    3rd operation is qc check- is it possible that production person will confirm this step in co11n itself without waiting for the qc person to confirm using QA32. ( here what yield to be entered and how if we use QA32 )
    4th -painting - finally ( as my logic goes -final confirmation selected and operation confirmed for the total production order quantity)
    Tell me if right. I noticed that if final confirmation option selected in the first operation itself, all the 4 operations can be confirmed in the co11n itself ( by selecting final confirmation option for all 4 operations)by the production department. Am i wrong somewhere. If this is so, how Qc person has control over the process.
    Also what yield /scrap quantity will be entered for each 4 operations in co11n ( is it mean the wastage occuring in each step =scrap and remaining quantity =yield). If so the final yield by operation -4 will be surely less than the production order quantity ( if wastage occurs during lathing/forming)
    regards,Pranav

  • Problems with router pc and mac

    I have installed a wifi router in a pc, coaxial cable plus ethernet. Recently I bought a McBook and I have some problems with internet conexions. I can run explorer in pc or in mac but I can use the explorer with the two machines at the same time. I can work with the mac restarting the router and doing the airport configuration, then internet don´t work in the pc; if I want work with the pc I do the same operation: restart the router and detect configuration with pc.
    Anybody know what is the problem and posible solutions?
    Thank you for your help.

    See if this helps you.
    http://docs.info.apple.com/article.html?artnum=19652

  • Rework operation in the routing

    Hi All,
    We are in the REM process,  We plan to change the existing Routing so that need to include the rework as the operation in the routing.
    we are not going to do rework for finished product (i.e after the confirmation). if any problem , we make it as the scrab.
    we need to do the rework for the product before final stage of inspection itself  . ie. we have a inprocess inspection .
    i.e we have a operation called soldering, if this is not done properly, we remove the soldering and do it again as a rework.
    1.how to mapp this operation as rework in the routing
    2. whether  we need to create the separate routing for rework or we can add this rework operation in the same existing routing itself ?
    3. if we do rework for the assembly, we can do create the rework, but in the component stage itself
    we need to do the rework.
    Edited by: raj on Jun 5, 2009 7:37 AM

    Hi Ramaling,
    my scenario is like , we have 10 operation, after the 3rd operation, we have the inspection as the 4th one.
    if any qty have rework , we have done the rework manually .
    so client need us to create the WC for rework and they need to find the cost inoccur for the rework
    after rework was done ,all the other operation will continue  for the reworked materials.
    how to include this rework WC in the routing what we used.
    is it advisable or not
    if it is not how to mapp my scenario ?
    Edited by: raj on Jun 5, 2009 12:52 PM

  • WRV200 multi SSID problem

    Hi. now i'm using WRV200 Router model.(use Multi SSID)
    - first and second SSID and encryption method is WPA-PSK, working well and no problem.
    - third SSID is working well first day, but next day, can be search SSID, but not getting a IP and connection failed.
      (if appear this enter administrator mode, not changed any other information, just click to save settings, then i use third SSID in oneday)
    - third SSID encryption method is WEP
    - Channels are used to channel 6
    - in this case, how can i fixed it?
      is this problem, SSID's problems? or channel's proble?
      why occur to multi SSID problem?
    pls help me

    The goal is to create one WLAN (wifi) with wpa2 and mac filtering that connect direcly to the physical network with server access, and the other WLAN (public) with only wpa2 protection and in isolated VLAN, for the guest.
    Suppose to have two SSID wifi and public (the second in the router web ui), both WPA2 Personal w/o MAC Filtering and w/o VLAN.
    I use only PC.
    With my laptop (windows 7) and two other laptop (win XP, win 7), I can see both SSID in wireless list, can connect to the first SSID.
    When I try to connect to the second SSID, the connection fail
    In the attachment you can see the actual router configuration.
    In the page Status -> Wireless LAN, ONLY one SSID is displayed (but is this web ui bug?).
    Thanks in advance

  • Difference between parallel sequence and parallel operation in a routing.

    Hi Experts,
    Can any one explain me with example the difference between parallel sequence and parallel operation in a routing? wHEN CAN WE USE PARALLEL OPEARTION AND PARALLEL SEQUNCE WITH COMPONENT ALLOCATION.
    Regards
    Deepak sharma

    I think u need to modify ur quest... i think u r asking about Parallel sequence and alternate seq. Below are the details from SAP site.
    A parallel sequence enables you to process several operations at the same time.
    You use an alternative sequence for example, if
    --The production flow is different for certain lot-size ranges
    For instance you can machine a work piece on conventional machine or on NC machines. A NC machine has a longer set-up time than a conventional machine. However the machining costs are considerably less. Therefore whether you use NC machines will depend on the lot size.
    ---The production flow changes under certain business conditions.
    For instance, if you have a capacity problem, you have some production steps performed externally by a vendor.

  • What is MULTI Operator in PCR

    Dear Experts,
    Can anyone please brief me regarding the function MULTI  Operator in PCR from where the values are captures in the field AMT,RTE,NUM.It is Payroll Operator.Thanks well in advance.
    With Regards
    Shaik

    MULTI: Multiply
       Object
         Operation
       Use
         This operation multiplies two fields of the current entry of table OT
         and stores the result in a third field.
       Input
         The operation processed the following wage type fields:
         o   NUM (Number)
         o   RTE (Rate)
         o   AMT (Amount)
       Syntax
         OOOOO xyz
         OOOOO       MULTI       Operation name
         x                       first  factor
         y                       second factor
         z                       product
         For x, y, and z you can use the following parameters:
         o   N for the Number field (see operation NUM)
         o   R for the Rate field (see operation RTE)
       o   A for the Amount field (see operation AMT)
    Processing
       In theory each field can by multiplied with any field. However, not all
       the possible multiplications are useful.
       For example, you can multiply the Amount field by the Rate field.
       However, both fields are linked to the payroll currency, for example
       10000 ESP and 5000 ESP/h. The result in this case is ESP squared/h. This
       value cannot be mapped usefully in any of the fields Amount , Rate or
       Number.
       This peculiarity should be taken into account particularly for
       currencies with more or fewer than 2 decimal places. The number field is
       interpreted differently from the fields amount and rate, which are
       always seen together with the payroll currency. Currencies, that have
       more or fewer than two decimal places cannot be stored directly in the
       number field.
       Possible multiplications

  • Standard test key in operation overview in routing

    Iam not able to see standard text key in operation overview in routing beside control key column. Any setting for it .

    hi,
       I dont think that that the STK is dispalayed in the operation overview.
    so first ensure that the STK is defined in the WORK centre basic data view. Then goback to the operation view of u r routing.
    Double click on the operation ,then u will find in the OPERATION details view that u r STK is diplayed just below your CONTROL key.
    GURUS pls correct me if i am wrong,
    PLs update on this
    THNX
    HKR

  • Mass change for QM at operation level in routing

    Dear Experts,
    I have to carry out mass change for Quality Management at operation level in routing. The steps that I am carrying out for an individual record are as follows.
    1.     CA02
    2.     Inspection point 100 is maintained at header level
    3.     Go to operation level
    4.     At operation level work center and control key have been maintained
    5.     Double click on operation
    6.     When I scroll down here I go to Quality Management: Inspection Points view.
    7.     There by default in Insp.pointCompletion system shows the option as u201CQuantity, valuation (production) and radio button selected default indicates u201CQty-relatedu201D
    8.     I want to change these options as only u201CValuationu201D and u201CNo relationu201D respectively
    My queries are,
    1.     Is there any T-code available to carry out these changes in mass?
    2.     Is it possible to do this without any Z development?
    I am doubtful about using LSMW here. I would be highly grateful to you if someone can help me step by step.
    Thanking you,
    Anand Rao

    Hi Sujit,
    Thanks for your reply!
    I tried CWBQM. Unfortunately could not succeed. I think may not be feasible through CWBQM.
    But I came across T-Code CEWB . There I opted "SAP_OPERATION" as working area and it worked. Its quite useful T-Code.
    Thanks again for your input.
    Regards,
    Anand Rao

  • How to call a previous operation in the routing in the backend?

    (We have a requirement to call a previous operation in the routing in the backend and create-assemble-complete the SFC.)
    Routing would be u2013 OPERATION_1 -> OPERATION_2 -> OPERATION_3
    The SFC has not been create and we are using u201CCreate SFC On Demandu201D.
    The production operator is given the SFC value to use, however, the POD is configured to START the SFC at OPERATION_2
    The desire is to process the SFC at OPERATION_1 as a u201Cblindu201D operation to production.
    The question: If we use a PRE_START activity, is it possible to launch the PRE_START activity at OPERATION_2 and have the activity:
    1) Create the SFC,
    2) Start the SFC at OPERATION_1,
    3) Assemble a child SFC (part of the activity information),
    4) Complete the SFC at OPERATION_1,
    5) Upon completion of the SFC at OPERATION_1 finalize the activity and allow the SFC to start at OPERATION_2 normally?
    Thanks and Regards,
    Avinash
    Edited by: Avinash Fernandes on Feb 16, 2012 3:30 AM

    Hi,
    a managed property only gives you a anlde to a bean or property, it doesn't execute it. To execute a bean, you can use a custom JSF PhaseListener that calls a bean method. The reference to the bean is achieve through value binding
    ValueBinding vb = FacesContect.getCurrentInstance().getApplication().createValueBinding("Name of Managed Bean);
    TypeOfBean theBean =(TypeOfBean) vb.getValue(FacesContext.getCurrentInstance());
    .... theBean.theMethod() ...
    Frank

  • Operation scrap in routing

    Hi All,
    I want to know,what is the effect of maintaining operation scrap in routing?It does not effect the component qty allocated to that operation(as it dus in case of maintaining operation scrap in BOM).
    Pls guide

    Hi Gautam,
    Operation Scrap In the Routing  is the amount of scrap (in percent) for the operation.
    The  effect of operation Scrap in the Routing :
    The scrap in the operation causes a decrease in quantity in the next  operation because the quantity to be processed is reduced by the scrap  quantity.
    The reduction of quantity is taken into account in scheduling  and costing.
    Hope you understood the point.
    Thanks,
    Srinivas

  • Tables to see operations of a routing that are already confirmed?

    Hi everyone,
    I would be very grateful if someone could tell which tables should I access in order to know if an operation in a routing has or hasn't been already confirmed.
    Thanks in advance and best regards.
    Ben.

    If you are doing confirmation by operation wise by CO11N,change the confirmation type from partial to Final conf in the screen.
    If you are doing by CO15, indicate radio button final confirmation when doing conf.
    If you want automatic selection of final confirmation goto SPRO>SFC>DEFINE CONFIRMATION PARAMETER.
    U can check in table AFRU table Order Confirmations.
    Completion confirmation number for the operation.
    Kevin

  • Costing of the operation in the routing

    Hai gurus,
    I have  5 sets of operation in the routing.
    a) Operation 10/20/30/40 and 50
    b)  In Operation 10/20 and 30 the , costing is active in  control key PP01
    c) In operation 40/50 the costing is in active in the control key zp01
    If that is so, whether operation 40 and 50 will be considered for costing during confirmation or not
    regards,
    sekar chand

    Hi,
    If the costing relevancy is ticked in control key & in operation. Along with the relevant prices maintained in KP26, system will do the costing. To double confirm, run CK11n for that material & verify the same.
    Revert if you face any issues.
    Regards,
    Vivek

  • Can I simply reinstall CS4 to resolve my operation problems?

    Can I simply reinstall Adobe CS4 (design std) on my Mac OS X to resolve my operation problems, such as "Unknown error" messges while using Ai and ID. My software has been trouble free for about a yr and half and suddenly several odd problems popped up in the last few months. If you think reinstalling will help, please give me a general direction for doing so. Thanks in advance!

    Hello,
    I heard that holding CMD+Option+r at bootup connects to Apple's servers & Lion download, hasn't been confirmed yet.

  • Multi-room DVR and router location

    My multi-room DVR was working fine and so was the Internet, but the only problem was that the wireless Internet signal was too weak for my computer's location.  I was told by 2 different Verizon tech support people that I could move the router upstairs and the multi-room DVR would still work, even though the actual multi-room DVR is still downstairs. 
    So far, the multi-room DVR is not working, but the Internet is and the wireless signal is much stronger for my computer. 
    Does anybody know if there is a way to move the router and not have it directly connected to the multi-room DVR?

    I had a similar problem recently with my MR-DVR.  I made some changes to my Routers Configuration which required a power cycle.  Afterwards my STB and DVR still worked fine, but the STB could not find the MR-DVR.  I had to reboot the MRDVR and STB to get everything back in sync.
    If you are the original poster (OP) and your issue is solved, please remember to click the "Solution?" button so that others can more easily find it.
    If anyone has been helpful to you, please show your appreciation by clicking the "Kudos" button.

Maybe you are looking for

  • Problems with sending SMS from adress book

    Hi all, I have a new Kotorola MOTOKRZR K1 here. The Bluetooth connection with iMac is ok. I can send data to phone and I can receive data from phone, but I can't send SMS from adress book v4.0.5 (487) to the phone. The bluetooth button in adress book

  • How do I find out what is causing a random black screen on iMac?

    Hello I get random black screen on a iMac and I haven't made any hardware changes. How can I find out what is causing this? Thanks Jer iMac 2.66 core 2 duo with Snow Leopard 10.6.8

  • Set text on status bar

    Hi all. I need help with Text on status bar. It was working well with IE6. here is the link http://www.aubryaubry.com/index.htm thank you

  • CRS not starting after reboot

    Hi, I have just installed RAC in a test environment using vmware server 2. I have Oracle Enterprise Linux 5 and used oracle 11g (11.2.0.1). I have not installed database software yet and just installed oracle grid infrastructure. When i restart any o

  • Error:Invalid reference to variable 'PARTS1.PNUM%TYPE' - how to resolve

    error: ERROR at line 29: ORA-06550: line 29, column 39: PLS-00487: Invalid reference to variable 'PARTS1.PNUM%TYPE' ORA-06550: line 29, column 4: PL/SQL: SQL Statement ignored DECLARE cursor c1 is select pnum from parts1; TYPE NumTab IS TABLE OF part