Hi All,
The scenario is that the user needs to transfer material from unrestricted to quality stock type. while doing so the storage type is different than the actual storage type for the material. Meaning if the material is normally stored in high rack storage type, when it is found that the material is damaged or expired it need to be moved to the quality storage type. For this the user will first create  material document in IM with movement type 322 transferring material from unrestricted stock to qualtiy stock. A PCN will be created in back ground which will in turn be converted manually by the user to a TO. while doing so the user will pick the quant manually from the required storage type and select the destination storage type as the quality or quanranntine area.
The issue here is that system creates one PCN for each material document line item. The requirement is that the system should create only one PCN with multiple lines for one Material document.
The setting in the movememnt type clearly says that it will behave as it is behaving.
Is there any other way or setting by which we can create one PCN with multiple line items for a material document.
Would look forward to your replies.
Regards,
Jeetendra

Thanks and Sorry for the delayed reply. We have now convinced the users that the system behaviour is standard and we cannot change the same.
To your question about the need to have one PCN with multiple lines please note that the setup is such that when material document is created for transferring material from unrestricted to quality and vice versa this document is created with multiple materials in one go. Now when the PCN is to be converted to TO then the user ends up in creating number of TO's equal to the number of lines in the Material Document. We wanted to avoid this and hence this was posted in SDN.

Similar Messages

  • ICal multiple duplicates of events created for one

    Please help. I created AN event in iCal for my work calendar.  Repeats M-F, 0730-1600 thru March 2014.  I've changed the "hours" of some of the "events" as needed (for example, vacation time, other time-off, etc.)  Instead of ONE event, each DAY is showing more than 100 views of the same event. Viewing the calendar is especially useless on my iPhone 4S - it's solid green (work cal), takes forever to load and, as I mentioned, useless.  I'd delete the entire calendar, but I have to be careful not to delete "views" that may show the amended work hours.  Please, offer some hope ... and HELP!
    Bill

    I am not sure, but check the Material Master data Views, In Warehouse management Tab.
    Check the field "Loading equipment quantity 1: LE quantity"
    parameter in this field may cause such system behaviour

  • Create TO from material document automatically

    Hi Experts,
    I'd like to ask for a solution about Create TO from material document automatically.
    Business Scenario:
    Normally, user will create TO from material document by LT06, then confirm it by LT12. If there is no stock on the shelf at the time when user confirms it, user will put quantity zero when confirmation by LT12, then user will create a new TO according to same material document.
    Requirement:
    According to scenario above, if there is no stock on the shelf, user wants to create a TO from material document automatically when he confirms the first TO.
    here I'd like to ask if there is any solution on it?
    We tried to use user exit: EXIT_SAPLL03T_002, and call transaction in it.
    but result is: first TO is not confirmed with zero quantity yet, so new TO can not be created.
    Please tell if there is any other solution, many thanks.
    Best Regards,
    H.B

    Hi
    To my understanding at the first time when TO is created for the material document and stock is not available using the available user exit in TO confirmation u can forcibly confirm the TO but for the second time TO creation and confirmation there wont be any trigger point( as bcz we have config to create TO immediately ony when mat doc is created) so for that u need to schedule a job for creation and confirm of TO's for the open mat documents.
    Regards
    Amarnatha

  • No quants exist for posting changes. Creating TOu00B4s in LU04.

    When creating transfer orders in LU04, we get an error message "No quants exist for posting changes'. We are using batch managed and serialized materials. Using QM interface, so, inspection lots are created at Goods Receipt. When QM team "accepts" batch materials during inspection lot, there is no problem, but when "accepts" serialized materials, the system creates posting changes notices but can not create transfer orders sending the message before described. This is because after receiving the serialized materials, we receive one piece at a time in order to create one inspection lot for every serial number. But when we put away the materials, we put them away in the same bin. so, system assigns one quant and one inspection lot to the bin, updating the last one every time we put away one serial number. When system tries to look for the inspection lot number selected in QA32, is not finding it in the bin at WM level because the bin only contains the last inspection lot that was put it away.
    With batch managed numbers there is no problem since SAP divides the bin in different quants with the correspondent batches assigning an inspection lot to each quant.
    Is there any alternative to solve the issue with the serialized materials? We are using SAP ECC 6.0.
    Thanks for any help.

    Hi,
    The reason why we put away serialized materials into the same bin is because materials are physically small and they fit more than one in each bin. The warehouse is structured in this way and we plan to use it like that because it wouldn´t be feasible to create one bin for each serialized material. Is there any other way to manage this situation?
    Thanks in advance.

  • Maintain number range interval 01 for posting change notices

    Hi,
    I am doing transfer posting using movement type 321 (quality to unrestricted) for one material.While posting i am getting error"Maintain number range interval 01 for posting change notices" Message no. L0015
    WM is active for this material and doing this movement for one plant which is newly created in system.Wil you please advice for which document type i had to maintain number range.Please inform SPRO path / Transaction to be used to make required changes.
    Thanks & Regards
    Atharva

    Maintain number range for posting change in tcode  OMLW

  • Production order from sales order with multiple line item(for one material)

    Dear Gurus,
    I am working in MTO scenarios. If there is several line item in a sales order for one material, multiple production order( same as no. of sales order line item) is getting created against each of the line item.My requirement is,since the material code is same in each line item and sales order is one, one production order should be generated for all line item. please tell me how to do it.
    (Here for one material, multiple line item is required for some specific reason)
    Regards
    Rajib Pathak

    Hi,
    This is not possible.
    In Std SAP will create one production order for one sales order. The stock is also allocated to thet particular sales order only. Because each and every sales order may vary in any one of the parameters. Considering this, SAP has designed like this.
    Regards,
    V. Suresh

  • Creating Transfer Order for a Material document

    Hi,
    I am transferring the Unrestricted stock from one material to another material through Movement type 309.
    I am creating a material document through BAPI_GOODSMVT_CREATE. Once the Material document is created and if the stock is in multiple storage types or storage bins, then I need to perform LT06. Instead of doing BDC recording I am using L_TO_CREATE_MULTIPLE function module for creating the TO. I am passing all the necessary values to this FM. TO is getting created but the Material document is not reflecting in that TO.
    As per the configuration, movement type 309 will create the posting change only not the Transfer Requirement.
    Does anybody have encountered the same problem?. If so please let me know how you have resolved the issue.
    Regards,
    Kishore.

    Hello Kirankumar,
    It is possible to assign external number ranges for Storage unit, so maintain storage unit number range to assign SU number externally.
    Now when you create Transfer order for material document at that time you can assign SU number externally.
    Hope this helps.
    regards,
    Arif Mansuri

  • Posting change notices

    Hi
    process for purchased material is to have it come into Storage Location XXX. Once the usage decision is done in QA32 the materials are then transferred to the correct location as defined in material master. but They do this using MB1B 311 and they are always getting the 922 issues.
    Please asssit

    Hi
    Negative stocks are there in Storage type 922 because you have transfered the material through 311 mvmt before completing the posting change.
    As per process, usage decision have to be made in QA32 and stock to be transfered to Unrestricted from Quality stock in same QA32. Here system will generate one posting change notice. Transfer this Posting change in to TO and confirm the same. Then make 311 mvmt to transfer the material say for example from receiving Storage Location to Warehouse storage location
    Regards
    Shantha Kumar

  • How to clear open posting change notices (Movt type 309)

    Hi,
    I want to clear the open PCN's created with mov type 309 (Posting change, general) being shown in LL01.
    All these posting change quantity are positive. I am not able to nullify them because there is no stock of those materials.
    Whenever I try to create a TO from LU04, the system is unable to take a storage type because of no stock.
    Whenever I try to change the PCN;s status to :U", the system says that the souce data and dest data is same (both sloc's are same).
    Please suggest an alternative to clear these PCN's.
    Thanks in advance.
    Regards
    Gaurav

    Hi,
    Pls check the below.
    -Any open transfer orders for the posting change notice exists,once they confirmed the PCN will be cleared.
    -Use LU02 to set a deletion status on the PCN.
    Posting change notices can be created for same sloc's but the stock category of the source and destination will be different i.e. unretstirced to quality, unrestriced to blocked etc ....
    Hope this helps you.
    Rgds,
    Kris.

  • Clearing posting change notices

    Hi All,
    I'm trying to close out posting change notices manually by marking the status as U through LU02. Not able to create TO and clear this as the stock is no longer available and these are very old ones.
    The problem is that the source and destination data are the same and its throwing an error.
    Can you suggest any ways to clear these open posting changes
    Regards,
    Ashwin

    Sap provided corrrection program to clear the posting change notices.Develop this program in your system then check.We are using 4.6c version.
    To set the posting change in question to processed (U), please
    implement the following correction program in your system.
    1) Create program 'ZLTEST00' with type '1' and application 'L' with the
    following code:
    report zltest00.
    tables: lubu.
    parameters: w-no like lubu-lgnum, "warehouse number
    post-no like lubu-ubnum, "posting change notice
    status like lubu-statu, "status
    update. "update
    select single * from lubu where lgnum = w-no
    and ubnum = post-no.
    write: / lubu-lgnum,
    lubu-ubnum,
    'Status old >', lubu-statu,
    'Status new >', status.
    if update ne space.
    update lubu set statu = status
    where lgnum = w-no
    and ubnum = post-no.
    if sy-subrc = 0.
    write: / 'Update posting change notice'.
    else.
    write: / 'No update posting change notice'.
    endif.
    else.
    write: / 'No update posting change notice'.
    endif.
    To run above correction program:
    1) You have to indicate warehouse number, posting change number and the
    status which you want to set in the posting change.
    2) Without including the UPDATE-parameter, the program only shows the
    posting change, or
    3) When you mark the parameter UPDATE then the posting change will be
    changed.

  • Delivery number for a material document posted

    Hi experts,
    I need to delivery number for the material document number posted,
    I tried to use the field XBLNR from the table MKPF
    but i see that the feild is empty in the case of inbound delivery
    why is it so.
    How ever i can get the data from VBFA ,but can any one tell me the reason why XBLNR is empty in case of inbound delivery.
    Thanks a lot in Advance.

    Hi,
    If you do GR w.r.t. Inbound Delivery No in MIGO then it will not update "Reference" field i.e. XBLNR.
    To update same with Inbound Delivery No, you have to do "Post Goods Receipt" from Inbound Delivery Document itself in VL31N or VL32N.

  • Target costs is showing as ZERO for one material in KKBC_ORD

    Hi,
    When i execute KKBC_ORD,It is showing the Total Target Costs as ZERO for one material.Cost estimate was already executed for that material.I couldnot find out the problem for this issue.
    Kindly help me to find why it is giving the ZERO value for this Total Target Costs in KKBC_ORD transaction.
    It would be a great help if any one helps me...
    Thanks
    Supriya

    Dear,
    Have you done the GR final DEV for order?
    You need to do the variance calculation in KKS2, then when you save the variance, the target cost is calculated.
    Target cost appear after GR. I think you are checking in CO03GotoCost--Analyasis.
    Go to t.code OKEV.Select Controlling Area XXX  and create Plan / Target version
    Go to transaction OKV6 these settings control what values are used to update the target costs.
    Target Costs=Actual Quantitiy X the Standard Cost Estimate Price..
    Regards,
    R.Brahmankar

  • How do i track account posted against  PO created for cost centre

    Hi All,
    I have created PO with cost Center 'K' without material and i have entered G/L account no as well then i have done GR against PO.
    How do i track account posted against  PO created for cost center
    BR
    Govind

    hi,
    Check the table COSP - Cost centre external postings
    also check ..COEP and COBK...
    This will help you to see...
    IN COSP - See the debit / credit in BEKNZ and ledger - in the field LEDNR...Valuation type - WRTTP...
    Hope it helps...
    Regards
    Priyanka.P

  • CIN - Excise value posting for the material document

    Hi,
    We have assigned the routine 356(FV64A356) in the Pricing Procedure for Depot Sales where Service team issues components for the Service repair job through a Goods Issue(MIGO-261 Mvt Type) document.We are also able to create a excise invoice for the material document.
    The flow is Service Order - Goods Issue - through resource related billing a DMR is generated for the labour as well as the Goods Issued(MIGO-261), from DMR a debit memo is raised to invoice the Customer.
    The formula in the routing is, during the creation of Billing or Proforma document it picks up the excise value posted for the delivery if the excise has been posted,if the delivery is not found, then it continues with the excise value calculated in the sales order (DMR in this case)
    Is there any way or any other routine "to check for the excise value posted for the delivery ,if the delivery is not found, then check for the material documents if any linked to DMR(through Service Order)".
    Could anyone help in this regard.
    Thanks,
    Ramki.

    Hi,
    While creating the excise challan using J1IF01 you can see a excise invoice selection tab, Select the J1IF01 line item & click on this tab, here you can select the excise invoice from which the base amount will be determined.
    Thanks & Regards,

  • Auto To working for one material and not working for other material

    Hi,
    Hope everybody is doing fine.
    I have configured the auto TO. Its working fine for one material and not working for the other material. I checked the material master and wm 1,2 views have the same fileds / values. What could be wrong?
    I didn't setup the back ground processing job. Is that is affecting it?
    thanks for any help.
    regrads,
    KHAN

    Thnaks,
    You are right but then what could be wrong? Its working for one material and not working for otehr material? Any clue?
    Appreciate your time charlie

Maybe you are looking for

  • Unable to Boot from OSX -- Get Strange Schematic

    Hello - A friend forgot her password on her iBook. Using this forum, we found out that she can access and change the password by booting from the OSX disk (Tiger) and opening the "Utilities" on the installer. So we inserted the disk and restarted the

  • No display function on Qosmio X500-13R

    Hi everyone! I tried to connect a projektor with HDMI cable to my laptop. My problem is: I had picture only on my projektor.I tried to set it up,but i have do a failure.I dont know what.My laptop display doesn't work anymore.I reinstalled the windows

  • Billing Document not generated.....

    Hi Gurus, When i am creating a Billing Document VF01....after completion of VL01n...the system shows an error Billing Document not generated... Please help me Rewards will be given

  • Setting default application to none

    I would like to change a default application (e.g. Safari) to <none>. I don't think I should have listed Safari as the default application. How do I do this?

  • E-mail does not work

    I have read some articles on how to use SMTP and POP3 but it doesn't seem to work for me. I made a network terminal application in wich you enter the address and socket and allows for 2-way communication. Trying SMTP: Connecting to smtp.live.com at s