Non stock material and quality inspection

Hi All,
We are using a material short text for a material procurement. System allows me to post the goods receipt with mvt type 101 into quality inspection stock.
However once posted to QI stock, we can not enter 321 movement with reference to GR document.
But i can enter rejection for full or partial quantity using movement type 122,with reference to GR document.
Can any one suggest the method to transfer the stock from QI stock to consumption. SAP doesnot allow consumption from QI stock. How to handle the process.
Prashant

Hi,
When you do GR at that time only system books the consumption of material quantity and value immediately. Since there is not any material master (Material text purchase)
The quality lot generated is for keeping the record of the materials Usage Decision and Result Recording and to generate the COA. It is not related with Stock Posting since there is not any stock after GR.

Similar Messages

  • Non-stock material and service material

    What is
    1) The difference between non-stock material and service material? and
    2) The difference between text material and service material?
    Give the example and how to configure it into sap.

    hi
    1) The difference between non-stock material and service material?
    1.A.  non stoc material goes with NLAG Eg: Office supplies such as stationary & service materials goes with DIEN material type
    2) The difference between text material and service material?
    2.A. there is no any text material as a seperate master data in MMR &  DIEN (services).
    please chec the sap liabrary in it SAP has explained it very well.
    regards
    balajia.
    Edited by: balaji timmampalli achari on Nov 14, 2010 3:10 PM

  • Storage location extension for Blocked and Quality inspection stocks

    Hi All,
    Could any one explain how to extend a Storage location (which is actually maintained for the Returns) to make use for the Blocked and Quality inspection stocks. Does this require any config settings.
    Thanks in advance.
    Kalyan

    Hi,
    Thanks for the Reply.
    Let me be more clear,in describing my requirement. Actually the present Storage location is maintained for only Returns. But in addition to this I require to make use of this storage location for the purpose of the maintianing Blocked Stock or QI stock.
    Therfore to achieve above what are necessary steps or do i need to maintain any config settings for this.
    Thank You,
    Kalyan.

  • Difference between stock and non stock material

    what is the difference between stock and non stock material. example of stock and non stock material?

    Hello,
    Stock Material
    Material that is constantly kept in stock .A stock material has a material master record and is managed on a value basis in a material stock account.
    Ex: Raw Material.
    Non-stock Material
    Material that is not held in stock because it is consumed immediately.
    Ex: Office Stationary.
    You need to create purchase order and accounting document for payment but the stock balance is always zero as it is issued out immediately to the various department.
    Prase

  • Exact Difference between Non Stock NLAG and Non Valuated  UNBW Materia type

    Dear All
    What is the Exact Difference between Non Stock NLAG and Non Valuated  UNBW Materia type?
    I tried creating Purchase Order and found that accouting doc got created at both times and stock was not updated in MMBE for both material types.
    Regards

    Hi,
    non-valuated material (Material Type UNBW):
    This type of material is managed on a quantity basis, but not on a value basis. This makes sense for materials of low value, stocks of which nevertheless have to be monitored (for example, operating manuals).
    Non-stock material (NLAG) (Material Type NLAG):
    Inventory management is not possible for these materials either on a quantity or value basis. For frequently required consumables, the use of this material type nevertheless enables you to store the information required to create
    purchasing documents (such as texts and units of measure).
    When a material is procured directly for consumption, no material master record is necessary. In connection with consumable materials, you can distinguish between the following cases:
    • Consumable material without material master record
    • Consumable material with material master record that is not subject to
    inventory management (on either a quantity or value basis)
    • Consumable material with material master record that is subject to inventory management on a quantity, but not a value, basis
    Regards,
    Pardeep malik

  • Problem in BAPI for stock posting from quality inspection  to unrestricted usage

    Hi all,
    I am using BAPI_GOODSMVT_CREATE for  stock posting from quality inspection  to unrestricted usage Stock against quality inspection lot(not by MB1B) using mvt type 321.The material doc gets created by the BAPI,but actual stock posting is not taking place ie.the stock doesn’t get reflected in QA33/32 and QA11 also .Can any one suggest what must be wrong?The inputs given are as follows:
    GOODSMVT_HEADER:
    PSTNG_DATE =30/07/2014, DOC_DATE = 30/07/2014, REF_DOC_NO = INSP LOT NO.
    GOODSMVT_CODE:
    GM_CODE:  ‘04’ .
    GOODSMVT_ITEM:
    MATERIAL = MATERIAL NO
    PLANT = PLANTCODE
    STGE_LOC = ‘WIP’
    BATCH = BATCHNO
    MOVE_TYPE   = ‘321’
    ENTRY_QNT = 100
    ENTRY_UOM =  ‘EA’
    ORDERID =  Prd ord no.
    After executing this I used BAPI_TRANSACTION_COMMIT also. I am able to see the posted qty in MMBE,but it is not reflecting in QA11/33/32.
    Kindly help me.

    Hi Naveen,
    Thanks for the reply. Even after using FM QAVE_PROCESS_AUTO_UD,when i execute
    BAPI_GOODSMVT_CREATE, the same thing is happening.I am unable to see the stock deducted in QA33.
    Is there any input in the goods mvt bapi where we can provide inspection lot no since i believe that the goods mvt has to get connected with the inspection lot.

  • How to consider sample qty of raw material's quality inspection during mrp.

    hi expert.
    i have to consider sample qty of raw material's quality inspection during mrp.
    i am wondering how to implement it.
    is this possible?
    thank you~~!!

    Hi Seung Hyun,
    I think it depends on the sample quantity, whether it is a fixed quantity or it depends to the raw material quantity or requirement from the orders. If it is not fixed, then you can use scrap percentage as suggested by Vivek.
    If it is fixed quantity, then there are several alternatives to follow:
    Include the sample quantity to your safety stock
    Create another material number to distinguish the sample from the original raw material number and include it in the BOM
    Regards,
    Julian

  • Stock Type X Quality Inspection in Production Orders

    Hello,
    I have the material 123EDFXXX that the Production order has set the Stock Type =X (Quality Inspection)...
    We don´t know how was that set!! since that material has not active the QM Views in the material master.
    There is another master data (prod version, route) or something else that is coping that value??

    Hi Marco,
    1.Pl check if QM was active before the creation of order.If so you need to delete all Material and accounting documents
    2. Check in the work scheduling view in material master if the inspection stock is active box is active.then this could be the reason.
    Regards
    George

  • QM- Material in quality inspection

    Hi Gurús,
                  Hi Gurús,
                   We have some materials in quality inspection. For each material exist an inspection lot but not an inspection plan.
    I would like to know if there is a way to move the material from quality inspection to unrestricted use, but without creating an inspection plan and recording a use decision
    Regards
    Enzo

    Hi,
    There are 2 possibilities -
    1) If you have activated QM at material master & due to this the material is placed in the inspection lot, then you can transfer the same in QM only.
    2) If you have not activated QM for material, but selected Inspection Lot stock at PO, then you can transfer the material in MB1B by movement 321
    Regards,
    Prashant

  • In case of Non Stock Material - Different GL for projects from WRX

    Hi Gurus,
    While doing MIGO for non stock material in case of projects, system is crediting account from WRX in OBYC with blank valuation class. but how can we give different GL for projects in this case.
    Please revert asap.
    Thank you

    >
    sapmm99 wrote:
    > For non valuated material, material  master is required or?
    >
    > As per my knowledge material master is mandatory only for stock materials. not for not valuated and non stock materials usually we never maintain master data for non stock and non valuated materials
    >
    > if i am wrong please advise me
    Its upto you if you want maintain material master record or not for non valuated material. With material master you have a material code to input in the field of PO, without material master you put in short text.

  • PP-MM-FI integration for Non-Stock material consumption

    The client is expecting a simple solution for a Std SAP process which is LIKE subcontracting....but actually not.
    The requirement is to set up a process of external operations using a NonStock (NLAG) material ( which will have no physical stock updation when GR is done). This material is a part of BOM with item category N. The material will have S price control. ( Must from business requirements). PR gets created from process order --> converted to PO --> then 101 and simultaneous automatic consumption gets debited to order. (with a price = PO price). PO has a account assignment F and item category blank Standard).
    Question - This behaviour is not desired. The "Std cost" should be used in posting a consumption posting..& the rest ( PO price less Std price) should be shown as purchase price variance in a different acount. How to customise this break up ? Is there way in MM pricing conditions or something else ?.
    Pl note that there is no stock entry...only consumption will be debited with GR offset at PO price. Also at invoice verification, the price if different should be posted to price difference account ( which is not assigned to process order...it is directly going to COPA).
    Might be a very simple SAP solutions / answers from MM /PP......so that we avoid the ABAP development for reposting..
    Could somebody help pls ?
    Regards
    Ram

    Hi,
    Since Material is Non-Stock Material so it is must to maintain the Account Assignment Category in PR or PO for this Material. And once you maintain the Account Assignment Category in PO and do GR w.r.t. this PO then it will not consider the Material Master Price (Standard Price) since there is not any Stock Account Entry during GR, it will hit the Expense Account. And Price Difference Account will get debited only if Stock Account will come in picture.
    So following Accounting Entry will get generated;
    During GR (MIGO);
    Expense Account - Dr
    GR/IR Clearing A/c - Cr
    During LIV (MIRO);
    Vendor Account - Cr
    GR/IR Clearing A/c - Dr

  • During creation of NON stock material PO from where system will pick price

    Hello All,
    While creating PO for non stock material from where system will pick the price?
    If info record is there from where it will pick, if info record is not there then from where it will pick like that...
    If existing PO is there or not
    if existing contract is there or not
    For non stock material should we maintain the material master or ?
    Please advise me
    Thanks in advance

    >
    sapmm99 wrote:
    > For non valuated material, material  master is required or?
    >
    > As per my knowledge material master is mandatory only for stock materials. not for not valuated and non stock materials usually we never maintain master data for non stock and non valuated materials
    >
    > if i am wrong please advise me
    Its upto you if you want maintain material master record or not for non valuated material. With material master you have a material code to input in the field of PO, without material master you put in short text.

  • Unit Cost of non stock material - Hubwoo Catalogue

    Hi Team,
    There is one requirement to transfer the the cost of matrial from SAP PM to ArcFM. Here the materials are assigned to the operations in the PM order. Here we want to transfer the service cost and material cost of the particular operation to the ArcFM ( ie an external design tool) to estmate the total cost involved for the particular operation.
    Here the unit cost of the stock material can be get from the material master. But for nonstock material, a hubwoo catalogue is maitained. How do we get the unit cost for the this material?
    There is an interfece we have to develop to transfer the service cost and material cost from the SAP to ArcFM. Hence we have to get the unit cost of the non stock material here.
    Thanks in advance.
    Regards,
    Shyjith

    Hi,
    Yes, you are right but in material master price is not updating, many times I have been assigned the same material as a non stock and at every time I have maintained the planned price on order level but it is still maintained as "0" value in material master,
    what is the standard process?
    what settings need to be made to get automatically planned price or last purchased price for a non stock material?

  • Automatic PR to PO conversion for non stock material

    Hi,
    Can  Automatic PR to PO conversion be done for non stock material (with account assignment category and no material master).
    We are presently doing only for stock material with transaction ME59N.
    Thanks and Regards,
    Pratap

    Some of the pre-requisites for automatic generation of PO from PR are
    1. The system selects only those requisitions for automatic PO generation for which the indicator Automatic purchase order has been set for both the material and the vendor.
    2. It can only generate purchase orders from requisitions to which a unique source of supply has already been assigned.
    So material master is mandatory if you want to create PO automatically from PR and you need to activate this option both at vendor and material master.

  • Subcontracting with external service / non-stock material

    Hi,
    I have a scenarion in subcontracting when i provided the components / raw materials to the in-house workshop (workshop treated as an internal vendor) and further more our workshop required some external services / non-stok material from third party... now how i will incured this service / non-stock material cost on finished product.
    (PP moudule is not implemented on project)
    Regards,
    Ali

    Hi,
    Please refer the following links ..it may help you...
    Subcontracting service to a FERT material.
    http://books.google.co.in/books?id=LDyarcerUu0C&pg=PA571&lpg=PA571&dq=Subcontractingwithexternalservice/non-stockmaterialinsap+mm&source=bl&ots=vj5kUO9dto&sig=vrlCpSZ0-V0BseN96Qw9rTVhsQ0&hl=en&ei=cJKRTs5_0MmsB6rrgIsB&sa=X&oi=book_result&ct=result&resnum=10&ved=0CG4Q6AEwCQ#v=onepage&q&f=false
    Regards,
    Udaya