Dear Experts,
  Material A is Semi Finished goods, in-house produced in plant 1000
  Material B is Raw Material, externally procured from  vendors and stored in Plant 2000
  Material B is the component required to produce Material A, and this has been created as part of the master data in the BOM in plant 1000.
  A plant to plant transfer is done for material B when it is needed for production of material A in plant 1000 from plant 2000.
On creating my Process Order for material A, a reservation is created containing the required quantity of material B. This same quantity i can see on displaying the Materials List of the Process Order ( in the Requirement Quantity column).
Material B is only to be transferred  to Plant 1000 based on the requirement quantity of the Process order.
How do I automatically get the MRP controller of Plant 2000 notified of this Requirement Quantity immediately a Process Order in plant1000  is released?
I mean how does the MRP controller in plant 2000 gets to know that there is a need of Raw Materials in Plant 1000 as specified in the Process Order created & released in plant1000?
Thanks for your expected responses

Bisolaaina,
Use special procurement key 40:stock transfer for material B at plant 1000. This specifies that the material B is to be procured from another plant 2000. A requirement which arises in plant 1000 is then covered by stock from plant 2000
The following happens during the planning run: on detecting a shortage in plant 1000, the system automatically creates a purchase requisition for a stock transfer in plant 1000 and a release order for the purchase requisition in plant 2000. The date of the release order is determined during scheduling. When the stock transport requisition is converted into a stock transport order, the release order in plant 2000 is automatically converted into a reservation.
Tara

Similar Messages

  • Transfer of sales orders from one plant to another

    Dear all,
    My requirement is as follows:
    I have created some 500 sales orders (open) in one sales org+plant.
    Now due to plant shifting to other area, I want to transfer all the above open sales orders to another sales org+plant.
    One option is to create them manually. But that is time consuming and prone to errors.
    Second option is to upload thru LSMW. That too is very tedious.
    Third option is to extend/assign new plant to the old sales area and change the plant in the orders. But I want in the new sales org + new plant.
    Is there any other option by which I can transfer the above sales orders from one plant to another?
    Regards
    SAPshed

    Hi SAPshed,
    The problem is not the change of plant, which is standard functionality, but the change of sales organization.
    An awful lot of information depends on the Sales Organization: Company code (!!), customers, materials, prices, profit center, etc.
    SAP does not even admit creating a sales order in a Sales Organization A with reference to a sales order with a sales organization B.
    IMHO your best option is to try to maintain the current Sales Orders with the current Sales Organization and change the Sales Order in VA02 (your third option).
    If you are absolutely sure that all materials and customers are created for the new Sales Area in the same way and that prices (discounts) are the same, you might want to do a direct update to VBAK table to change the Sales Organization (nasty!), but be prepared for the consequences (no SAP support in case of problems, you are on your own).
    Therefore if you insist on a different Sales Organization, then option 2) will be your best best.
    Best Regards,
    Franck
    P.S. IMHO it is Best Practice to have a unique Sales Organization / Company Code.

  • Reserved sales order qty based on sales order

    Dear All,
    is there any way to reserve the sales order qty in stock based on the sales order?. Actually i want to block the some qty for paticular sales order.  For example I created one sales order with 100 qty of x article and now i want to delivery of sales order with the  same qty after one month . In this case i want to reserve this qty for this sales order that should be not deliverd by another sales order.
    Thanks
    Abhi

    Hi,
    Block this qty against sales order
    MB1B >>> Use movement 413 & enter
    Speciefy sales order number & item number
    Then this qty will be permanently reserved or blocked for the perticular order.
    Kapil

  • Intercompany Text-Based Standard Purchase Order from Production Order

    We have a business scenario where a material is made in a plant and then another plant performs a service on that material.  The customer wants the purchase requisition that is created from the production order from the producing plant to apply a vendor that is an intercompany vendor.
    The issue is, these purchase orders are text based purchase orders.  This process works perfectly when there is a material master.
    Scenario:
    Plant X = Production Order to make Material A
    Plant X = Production Order creates a purchase requisition in Plant X; Intercompany Vendor is assigned
    Buyer = Creates the purchase order from the purchase requisition
    Error Message: SAP issues an error message that this vendor cannot be used.
    We are looking for a way to create a text based purchase order (that represents a service) and assign to a intercompany vendor.

    The exact error message we receive is:
    Diagnosis
    You are entering an ordering transaction involving a vendor to whom a plant has been assigned. Normally, materials would be supplied by one plant to another in such a transaction.
    This process involves a delivery and billing document in the SD system. The PO for this appears directly in the delivery due list of the issuing plant (vendor) and therefore does not need to be transmitted.
    However, items without a material master record cannot appear in the delivery due list.
    Procedure
    Items without a material master record can only be ordered from vendors without a plant assignment.
    The point is if we create a vendor without a plant assignment, how can the inter-company posting be accommodated.

  • BAPI for displaying materian/description/Bin storage/ qty based on producti

    Hii All,
    please gv which bapi we use to display Bin storage, Material n qty based on production order number
    its very urgent

    Hi,
         You can try with user exit MWMBAP02
    <b>Reward points</b>
    Regards

  • MRP Generating Purchase Reqs for Materials Needed in 2013

    Hi, all.  We're running MRP and it's generating a massive amount of purchase requisitions (18,310 to be exact).
    The following is a typical part setup:
    Lot size = EX
    Planned delivery time = 5 days
    GR processing time = 2 days
    Individual/collective requirements = 1
    MRP profile = BTO
    We have one existing sales order with a delivery date in 2014.
    With a lead time of roughly a week, why is MRP generating purchase requisitions out into 2013 for this material??
    Thanks!
    Sarah

    Sarah,
    MRP Profile doesn't mean much to us, they are all created individually during each implementation, and they are all different.  However, I will guess that BTO is some type of Make-to-order profile.
    You mention 18K of PRs.  Are these all being created in a single run, or is it possible that they may have been accumulating for a while?   To find out, run MRP, but using the parameter for Planning mode 'Delete and Recreate planning data'.  It will delete all the unfirmed PRs and then regenerate new ones based on the current situation.  I will assume for the moment that all these 'future' PRs are unfirmed, please let me know if they are not.
    Since it appears to be a MTO environment (if not, let me know) then you should be able to see in the planning segment which requirement (sales order) is driving the purchase reqs.  Depending on your MRP type, this could give you understanding of why MRP is proposing so many PRs.
    One thing that will generate a large number of purch reqs is an unrealistic value in Maximum Lot size (MRP1 page of material master).  For instance, for a requirement of 1000 widgets, and a max lot size of , say, 2, it would generate 500 PRs for 2 widgets each.
    If my suggestions don't help you, please specify MRP Type, Lot Size, max lot size, rounding value, Safety stock, reorder point, Strategy group,   From these values we can begin to understand your problem a little better.
    Rgds,
    DB49

  • MRP Control Parameters

    Hi All,
    Pl. let me know where we define the MRP Control Parameters that gets displayed ,when we execute MRP(MD02), like
    Create purchase req
    1. purchase requisitions
    2.purchase requisitions in opening period
    3.planned orders
    etc.
    Normally we select these parameters while execution only.
    I want to know where these parameters are defined.
    best regards,
    Kumar.

    Hi kumaran
    As Mr.Prashob said these are internal SAP setting. like this many settings are there. For example order type category is 10 for prod order. This also you cannot change, This will execute many functions internally in SAP.
    If you want to set the indicators with respect to MRP group. you can ssign in MRP group setting.
    Regards
    J. Saravan

  • MRP Control parameters(MD02)-Regarding.

    Hi,
    Can anyone explain me what values(MRP control parameters)should i use for MRP run.
    For Eg for an 1.Inhouse produced material(FERT),
                        2.For externally procured (HALB) materials,
                        3.For Sub-Contracted items,etc
    So that i'm getting proper planned orders or Purchase requistions.
    what's the meaning for "Purchase Req.in opening Period"what's the meaning for opening period.
    Thanks & Regards
    Raj.S

    For all materials type you can run withfollowing control parameters from MD02.
    1) Processing key: NETCH
    2) Create purchase requisations: Keep 1...by doing this for F parts MRP creates PR and for all E parts MRP creates Planned orders...This will work according to procurement type. If you keep 3 "created planned orders: then MRP created only Planned orders..no PR will be created.
    3) Create scheule lines: Keep 3...if schedule lines are mainatin then scheudle lines will be created..otherwise no impact.
    4) Create MRp list: 1... to see the MRp results.
    5) Planning Mode: 1..This is better to improve the system performance . if you new data eevrytime then keep planning mode 3.
    6) scheduling type: 1...Basis dates scheduling if you are not working with capacity planning.
    If you are maintaining scheudle margin key in MRp2 view with opening period for example 10 days and in MRP control parameters :create PR in opening period" then MRP creates PRs only in the opening periods of the schsdule margin key if the opening dates of the PRs are falls within these 10 days. Otherwise MRP creates planned orders..later you can convert these Planned orders into PRs.
    If helpful rewards your points.
    Regards
    TAJUDDIN

  • Mrp control parametrs

    Hi, Pls advise what are control parameters need to maintain in mdbt variant for running mrp immeadietly after golive. pls note cutover data is uploaded and using strategy 20. pls advise.

    Dear ,
    Few Inputs regarding MRP run at Go Live and Post Golive situation :
    1.Go Live time MRP run : Based on WIP posting , open orders (PR,PO,SO,STPR,STO) , Stock , you will run MRP for the frist time with Process Indicator -NEUPL,2,1,3,3,2 in MD02/MD03
    2.After that you need to analysis the planning result -Net Rquerement (+/-) and lead time analysis , safety stock , replensihment pattern -weekly , month as per your business requirement
    3.Basically , frequency of MRP run depends on the material lead time and order fullfill ment (Sales Order ,Independent Order ) .
    4.It depends on the planning situtation -Demand Pattern and replenshment set up.For example , you have central plant-supplying plan and having 6 DC.The lead time of DC is 7 days from suppling plant and Vendor to Suppling plant 90 days .In thsi case , i hope u need to run MRP every month for DCs if you want to repleish monthly basis .Where as in Supplying plant every three months besaue of lead time .It depends on order fullfill ment and LT
    Few parameters :
    1.Stockable or non stockable material
    2.Lead Time
    3.Replishment strategy and RLT
    4.Demand pattern -Order /In dependent
    5.Safety Stock
    6.Planning Structure
    7.Validity of the Fcatory calander
    8.WIP posting or WIP should cleared .
    9.All the stock are updated or not .
    Hope this will give you an idea on your requirement
    Regards
    JH

  • MRP RUN for increased qty of SODS PR for complete qty instead of increase

    While doing MRP RUN for increased qty of SO No line item 10 to 20,System is making PR for complete qty instead of increased qty.
    Sales order  - 0001
    Line item - 10 Qty - 10
    Line item - 20 Qty - 15
    MRP run against the sales order for line item 10 & 20 PR / PO raised for qty 10 & 15 respectively.
    After that qty has increased in sales order.Again we run MRP system generates totla no of PR insted of Increased qty .
    Sales order  - 0001
    Line item - 10 Qty - 10 + 5 = 15
    Line item - 20 Qty - 15 + 5 = 20
    Plz help

    There are few questons here:
    - when you increase the amount of the sales order item, is the newly added amount confirmed with the same date / schedule line? You can check the schedule lines for that SO item.
    - have the purchase requisitions, which were generated after the first MRP run (before the modification of the SO items), been modified manually (are they firmed?) / processed? In this case MRP cannot modify (delete) them (and create new ones)...
    - did you check the MRP control settings in material master
    Remark: even if you get several PRs, you can create one PO from them.

  • MRP splitting the reservation qty to multiple purchase requisitions

    Hi SAP gurus,
    We currently have an issue with our MRP splitting the total reservation qty into two purchase requsitions.
    For example: Res A = 100. After MRP run, 2 Pur Reqs will be generated with PR 1 = 60 and PR 2 = 40.
    We checked the source list, info records for minimum order qty but we are not maintaining it at all. We also tried entering the max lot size to 10,000 but still it didn't work.
    Any advice on how we could resolve this, please?
    Thanks in advance.
    Cheers,
    Christine

    Christine,
    For the purposes of troubleshooting, you should ensure that both purchase reqs are unfirmed, then use "3 delete/recreate" planning mode for your MRP runs to minimize possible confusion.  So, 1-3-1-3-1 until this is fixed.  Also, run regen one time NETUPL.
    What is your Strategy group?
    And to confirm and reiterate, your Material master stuff is
    Quota arrangement usage = blank
    Min lot = 0
    max lot = 10000
    max stock = 0
    rounding = 0
    Rounding profile= blank
    No entries whatsoever in the Safety stock block
    Planned delivery time 154
    No entries whatsoever in the 'Storage Location MRP' block
    Your reservation creation date is Nov 11 and your reservations reqment date is Nov 11.  You have no other supply elements (purchase orders/purchase reqs/stock/production orders/planned orders etc) and you have no other requirements elements (sales orders/deliveries/other reservations/dependent rqments, etc).
    Are your purchase reqs sourced?  Are the sources different? If so, can you give me the standard qty and maximum qty and planned delivery time from each of the Purchase info records?  Or, are you using a Contract or a Scheduling agreement?
    Rgds,
    DB49

  • Sales order qty vs Billing Req qty

    Dear Gurus,
    I created a Sales order for qty 100. with reference to this sales order i created a billing request for qty 70.
    Now while i creating one more Billing request with respect to tha same sales order it is showing the open qty as 30, but when i try to change the open qty from 30 to 70 the system is allowing me give mor qty against to the respective sales order.
    in this i want to restrict to the system to allow more qty against the sales order, how can i restrict?
    Cheers,
    Sumith

    Hi sumith
    Check weather the billing relevance feild is C in for the item category VOV7.
    check the copy controls in VTFA for OR and F2. for that item category and check weather the document flow is positive or not
    But sumith if the item category is TAN in the sales order then it will take N number of qunatity in F2 ,as the item category TAN  is relavent for delivery. so copy controls wont be there for TAN. in VTFA.
    Reward if useful
    Regards
    Srinath

  • Dangerous Goods checks in transfer order (based on purchase order)

    Dear,
    We have defined a process to transfer products from one plant of our company to another plant of our company based on a purchase order (Transfer order), a delivery and a shipment.
    Problem: the delivery and shipment could be checked in a Dangerous Goods standpoint but nothing seems to be available in standard to check the process at the first step : at purchase order step.
    My question is : do you know if a standard feature exist on purchase order to ensure a "non frustating process" as soon as possible ?
    Many thanks for your help
    Best regards, Jérôme

    Dear Jerome
    DG Set up is only related to SAP SD process (e.g. check SAP EHS online help), Therefore DG checks are not available in the purchase part. And your scenario it quite standard; Normally the DG check part starts in Sales process, then in delivery and then in shipment. If you use SAP TM again you can use DG checks there.
    C.B.
    PS: e.g. SAP GTS and SAP EHS SVT are integrated in purchase process by standard. But is is not a good idea to "misuse" these modules for DG perspectives in MM process.
    PPS. may be check: Blocking Hazardous Materials for Purchasing with HSM,
    System-Internal Stock Transfer Using Stock Transport Orders - Integration of Transaction Data - SAP Library

  • Calculation of po qty based on material in  Reuse_alv_grid_dispay report

    Hi friends,
    This is the requirement
    I need to calculate the total Quantity(ekpo-menge) on open stores orders(doc type) with today's delivery date + (today's date + 1).
    help me out in giving the mandatory fields that need to be taken and  the code to calculate the total quantity based on material.say there are 3line items for one purchase order then how to calculate the total qty based on material.
    thanks in advance,
    meghna

    thanks for your replies
    I have already seen tcode gral but my requirement is simpler
    When we execute any ALV Report, the report is displayed in ALV Grid by defalut and then we can change the view using Grapcial View option in the menu bar
    I want to display this graphical view by default instead of that in the report form when the report is executed
    I hope my requirement is clear
    Ur valuable suggestions will definately be appriciated
    Thanks in advance

  • Order qty Based on ROH qty

    Hi I want to round off my order qty based on ROH. Say ROH is available multiples of 0.6 TONS.My Fert is need to plan so to that it consumes  0.6 ,1.2 , 1.8 etc TONS.
    Without using Material-Qty calculatiuon is it possible?? Because I am using Discrete Mfg.

    Hi,
    You must be having the Lot-size as EX.
    In this situation, For your lot size : EX, in OPI4, Activate the MTO Lot size as "1" (Lot-for-lot with Rounding).
    Maintain the Rounding Value in MRP1 View.
    Now the Order will be created with Multiples of your rounding Value.
    Hope this helps..