Planned cost of PO vs. actual cost of GR

Hi all,
I want to view the planned cost of a purchase order and the actual cost incurred by GR of this PO, where can I see these 2 different types of cost? Thanks.
Regards,
Michael

In purchase order history of PO ,you can view

Similar Messages

  • Report for extracting the actual and planned cost from service orders

    HI all
    we are creating a report in BI for Module - Customer service . LIke , the report is all about how many complaints created in the system and how many completed technically and what is the cost involved for each complaint .
    Like we want the comparision between the planned cost and the actual cost .
    Now to give the logic to the BI Team for planned cost and actual cost , please suggest the flow of logic or table flow to arrive the planned and actual cost
    thanks in advance

    Hi Marthand,
    I am not sure which datasource your are using. In this case, you can use the 0VALUETYPE to differencitae between th eplan and actuals. Normally Plan which is budget will have value 050 and for actuals will have 010. For costs, you will have one key figure and at the reporting level, you will have the costs restricted by the value type for plan and actual to make comparisons.
    Hope this helps.
    Regards,
    Srinivas

  • In which table production order planned cost and actual cost i can see?

    Dear PP Guru,s,
    from which table i can see productuion order planned and actaul cost. i checked following tables AUFK, AFVC, AFVV, CAUFV, AFRU, AFKO, AFPO. but i did not found planned cost and actual cost field. is there any other way to get this data with respect production order?
    Regards,
    sree

    Dear,
    Planned and actual costs of prod order from COEP, COSS, COSP  S027 tables
    production order shows the planned cost based on the quantity structure.
    Please refer my reply in this thread for details,
    Re: Actual Halb Material Cost
    Regards,
    R.Brahmankar

  • Planned cost & actual cost are same in process order.

    hi,
    I have created new order type for process order.
    when i made process order & i  going for  confirmation in cor6n , on screen fixed & variable overheads values are coming which system had taken from receipe.
    when i did changes in that values which are in hrs & confirm & settle the order, in cost analysis plan cost & Actual cost was seem to be same.
    I dont get why this is happen ? is there any config in order type.
    thanks in advance.
    regard
    sanjay.

    Check in cost analysis, IN plan VS actual Is activity is available?
    I feel U haven't maintain activity type in costing view of workcenter

  • Wrong planned cost calculation while actual is calculating correct for internal activities

    Dear all,
    I am facing an issue in which when i am doing network costing with work center, activity type, cost center and giving per hour rate in KP26. System is calculating correct actual cost but every time its calculating wrong planned cost. For example: If i have given per hour rate 60 usd when planning for 100 hrs in cj20n its showing 2500 while confirmation is working correct and for 10 hrs its showing actual cost of 600.
    I have checked work kp26 also report KBST to make sure about rate. Also i have checked configuration related costing variant planned and actual and its standard PS02 and PS03.
    I will really appreciate suggestions or some one face similar issue and got it resoved.
    Thanks.

    Dear All, this issue is resloved. I didnt give quantity in KP26. However i am more curious that most of the time i dont give any quantity in kp26 and always system works fine and calculate correct cost than why this time its calculating wrong planned cost.
    Thanks all.

  • Tables & Table relationship to find ACTUAL & PLANNED COST for ACTIVITY ELEM

    Hi Guys,
    I have to create a report for Project, WBS, Network, Activity and Activity Element to show :
    Reporting period: March 1,2007 to March 25, 2007
    Planned cost   ( (from March 1, 2007 to March 26, 2007)
    Current reporting period   (from March 1, 2007 to March 26, 2007)
    YTD Actual Cost   (from Jan 1, 2007 to March 26, 2007)
    Kindly let me know the table to get the ACTUAL COSTS and PLANNED COST with relationships.

    Hi,
    Refer to the BLOG
    SAP Project System - A ready Reference ( Part 2 )
    Hope it will help full
    Regards,

  • Function Module to find Planned Costs and Actual Costs against WBS element

    Dear All,
    We have a requirement where we need to find out the Planned Costs and Actual Costs booked against a WBS element, in a year. The costs can be against all the plan versions or on individual plan version.
    Are there any function modules to retrieve this value?
    Thanks for the help.
    Warm Regards,
    Judith

    Hi,
    The easiest way would be to get the OBJNR for all WBS elements from PRPS and look up RPSCO and summarize for Value type (RPSCO-WRTTP) 1 for planned cost and 4 for Actual cost.
    Please let me know if this helps.
    jibat

  • IW32  needed Plan Cost and Actual Cost table name

    Hello ,
    In IW32 transaction Plan Cost and Actual cost in cost tab ---Table Name.
    Req: needed  plan cost & actual cost table names  for particular order number.( For New Report )
    Can you please let me know where Plan cost & actual cost get stored in IW32 in Cost tab ( table name / function module name ) or how its get calcualted for particular order number.
    Thanks in advance !
    Regards
    Rahul

    hi ,
    i too had same issue , i wrote following FS for that :
    Actual and planned cost  from PMCO-WRT00 to WRT12(the sum of values should be considered for actual as well as planned ) for  PMCO-OBJNR taken from CAUFV -OBJNR for order number  AFIH-AUFNR  and also currency from CAUFV-WAERS .
    Actual cost will have valuation type PMCO-WRTTP = 4 and planned cost will have valuation type  PMCO-WRTTP = 1 , which will be placed in different column
    hope this helps
    regards
    satish

  • Target cost, planned cost, actual cost difference

    Hi!
    As per my understanding , the target cost, planned cost, actual will be calculated like blow:
    Actual cost = Actual quanity * Actual price ( standard price or moving average price) existed at the time of goods movement.
    Planned cost = Planned quantity * Planned price ( standard price or moving average price) existed at the time of production order release based on valuation variant strategy.
    Target cost = Planned Quantity * Actual price ( standard price or moving average price) when calculating variances.
    whether above formulas are correct?
    I have one scenario, where in process order, I am not seeing Planned quanity for compoenent/raw material, but target quanity is existed. How it is possible. When I have checked the BOM in process order, the BOM does not contain the componenet.
    regs,
    ramesh

    Hi,
    Target Cost = Costs as per the standard cost estimate * Actual Qty delivered.
    For e.g. Std cost for one unit of material-x is as follows.
    RM 1 - 10kg * 10 /-  = 100
    Activity 1 - 5 Hr * 50 /-  = 250
    If the actual delivery from the production is 2 units, then target cost will update as
    Under Goods Issue, RM 1 - (10kg*2units) * 10 /- = 200
    Under Confirmations, Activity 1 - (5 Hr*2units) * 50/- = 500
    Total = 200+500 = 700
    Target cost for goods issue/confirmation of activities will update only when the Goods receipt has been done but not at the time of goods issue or Confirmation of activities.
    Target cost for Goods Receipt will update only when the variance has been calculated for the order.
    Regards
    MadhuSekhar Gupta G

  • Planned Cost is taken from Actual Cost even through there is Baseline Cost

    Hi All,
    Responsibility: Project Super User
    Create Project with fully shared structure
    Enter planned cost for 25000 against Task (Define Project scope in detail) with Financial Element as Resource and baseline the work plan.
    Now enter the actual cost for 15000 against Task (Define Project scope in detail) and system is computing 15000 in Actual Column along with planned cost as 15000 in planned cost column instead of showing 25000 in planned cost column.
    Why system is showing planned cost as 15,000 in planned cost column instead of 25000?
    Please help.

    Hi
    I'm not sure I understand the steps you were taking.
    Actual costs should be summary of expenditure items. Those could be labor hours entered on time cards, supplier invoices etc. Those are entered on Project Costing, Distribute and summarize there
    I couldn't understand your statement about entering 15000 actual cost on the same page as entering the planned cost for the workplan.
    Dina

  • Differentiate Planned Cost, Actual Cost & Targeted Cost

    Hello Friends,
    I am searching for job and went for interview in Wipro. They asked me the difference between Planned, Actual and target cost..... I tried to search on Google and SAP Blog's but couldn't find the appropriate or understandable answer yet, So it would be great if you you can guide me a bit on this......
    Thank You,

    Hi,
    Any PP related queries you can search in Forum ERP: Manufacturing.
    Pls refer the link.
    planned cost and actual cost
    Thanks,
    nandha

  • PM Order: Plan cost is Zero where as Actual cost is having value

    Dear Experts,
    I wanted to know why Plan cost is comming zero in the Maintenance order, where as Actual cost is having value.
    Please guide me where it is going wroung
    Regards

    Dear PeteA/Manish,
    I have assigned two components, and agaist which Reservation created since i had mentioned Stock item.
    Then I have issued material against Reservation, then done TECO and processed for Settlement.
    This what i have done, after seeing my settlement i have come to knwo that Plan cost was Zero.
    Thanks for your suggestion.

  • Actual or plan cost take as an account

    hi
    plz tell me answer
    In the CK11N ,we just find for one finished product cost, here we will estimate machine cost and labor cost but during production order ,here which one we will take estimate cost or really incurred cost  or plan cost estimated in ck11n, generally we donu2019t take actual cost. in the real time what will happen
    thank you
    soumya

    Dear Sowmya,
    Plan price is entered in KP26 but actual price is entered in KBK6. After entering the actual price in KBK6, you can do actual price calculation. This activity brings in extra debit or credit into the production order in order to get the actual cost of the product.
    Trust this answers to your query and helps much in resolving your problem!
    Regards,
    Ashok SINGH

  • Actual costs and Planned Costs

    HI Friends
      I want to know the Main Tables from which i can get the <b>Actual costs and Planned    Costs</b>     for the given Cost element or object number
         I tried with table COEP and i got actual costs up to all cost elements in the given controlling area and in given cost center , but for some cost elements, this tables does not have any entries...
    So is there any other way to get these Actual costs and
    from where i can find the Planned Costs
    Reagrds Rk

    Hi
      I already checked these tables but i didn't get the exact data
      for actual costs i checked COEP but some costs are missing there
      and i could n't find the field BENKZ in coep table
         I am comparing these values with the standard transaction <b>S_ALR_87013611 </b>
      but not getting exact details  in my program
    can you please help me in this regard..
    Does anybody worked on this transaction <b>S_ALR_87013611 </b>, then please explain me the logic how it is getting the actual and planned costs
    Regards Rk
    Message was edited by:
            Rk Pasupuleti

  • Actual Costs , Planned Costs and Variance

    Hi,
    I know that there is a standard function module that gives the actual costs , tha target costs and variance, K_KKB_KKBCS_ORDER_REPORT. But is there any Funcion Module  for calculating the Actual and planned costs and variance?  or could the same FM be used for the purpose?

    OK

  • Table of planned cost & actual cost

    Dear PP experts,
    I want to create Zreport. for that I want the table & field of planned cost & actual cost. Please tell me.
    Thanks
    Jayesh
    SAP PP

    Dear.
    Planned and actual costs of prod order from COEP, COSS, COSP S027 tables
    production order shows the planned cost based on the quantity structure.
    Please refer my reply in this thread for details,
    Re: Actual Halb Material Cost
    Regards,
    R.Brahmankar

Maybe you are looking for