Plannned Delivery time not considered while calculating delivery date

Hi PP Gurus,
We have a situation is that after MRP run system is not taking into account planned delivery time while calculating delivery dates in schedule lines
It is taking into account GR processing time.We have GR processing time of 3 days.requirment date is 13.10.2011 & delivery date created by the system is 10.10.2011.
We have maintained correct master data i.e.Materail Master , Info record & Scheduling agreement.
Please advice why it is happening & what is the significance of planned delivery time in externaly procured materail with scheduling agrement schedule lines?
Thanks & Regards,
Sandesh

Hi Sandesh,
Is this happening for particular materials or for all materials
Couple of checks -
1) Check with material master changes, might be after MRP run PDT is updated in material master etc ..
2) Check in OPPQ, for option external procurement , whether scheduling info records/agree is marked or not
Best Regards
K.Madhu Kumar

Similar Messages

  • Planned Delivery time not considered after MRP run for scheduling

    Dear All,
    After running MRP, the planned delivery time maintained in Purchase info record is not taken into consideration for calculating start date of the schedule line of externally procured material generated by the system.
    Planned delivery time is 3 days & Requirement of parent material falls on 15/02/2010. With this, system should calculate the start date for schedule line as on 12/02/2010 considering 3 days Planned Delivery time.
    Any idea as to what might have gone wrong?
    thx for your help in advance.
    Rgds,
    Ranjeet

    Hi,
    Determination of PLD from the Purchase info record is maintained in transaction code:OMDT. Planned Delivery time is also maintained in Scheduling agreement. However, it is not calculating delivery date as well as release date.
    Rgds,
    Ranjeet

  • Open Delivery is not considering in credit check in sale order

    Dear Experts,
    Please advice what setting is required for Dinamic credit check at the time Sale Order creation
    for Open Delivery & Open Billing Items should be considered at the time of new sale order creation,
    I have ticked on Dinamic check - "C" Open Items "C" and ticked on open orders and open deliveries Horizon - 2 "T" but still it is not taking the open delivery amount.
    Ragards,
    SP Shukla.

    Hi
    Pls. check your schedule line (delivery date)as you have mentioned the 2 days as the horizon period. If your delivery is falling after the specified horizon period then the credit limit will not be validated.
    Hope this will help you.
    Regards
    Aravind

  • Is planned delivery time is considered in scheduling agreement ????

    Hi experts
    problem is that the schedule lines (for external procurement) generated from MRP are not taking the "" Planned delivery time into consideration"". System is only taking the G.R processing time.
    I have mentioned the Planned delivery time in .
    1) Scheduling agreement for 1 day.
    2) In material master for one day.
    3) In info record 1 day.
    e.g Suppose req date is 13.07.2008. MRP run date 4.07.2008.
    a) Planned delivery time = 1 day . B) G .R processing time = 3 days.
    Now when i run the MRP on 4.07.2008.
    Schedule line is generated on - 10.07.2008
    Please Guide . How i can take care of that time which is requiered at vendor ends.
    Regards
    Rahul Bhardwaj

    Go to OPPQ for that plant
    Click on "External Procurement " tab and check if you have maintained any planned delivery time?
    Tick indicator " Scheduling info record/agreement " (This will take Planned del time specified in scheduling info rec or agreement)

  • FTP Delivery Destination Not visible while scheduling a report.

    Hi All,
    We are implementing BI Publisher 11g (As part of OBIEE 11g).
    In BI Pub administration we have defined FTP and Email Delivery Destinations.
    But while Scheduling a report, under Destinations we see only Email option, we are not seeing FTP option.
    Is this happening due to any of the missing configuration or any privileges are missing?, please clarify.
    Thanks,
    Aditya

    Do you have "Use Secure FTP" checked?
    I tried adding a source with that checked and the FTP option didn't show up either, but when I unchecked that box I was able to see the FTP option.

  • GR Processing Time and Delivery Time not coming in CS11 Output screen

    Hi,
    I am executing a BOM explosion report using CS11.
    In the CS11 report output I added columns for GR Time and Delivery Time using change layout option.
    After changing layout when I see the details in columns of GR Time and Delivery Time all the values are ZERO '0' for all the components in BOM.
    I checked the material master for component items and find that in MRP view values are maintained in GR Time and Planned Delivery Time field which are also seen in MARC table.
    I do not know from where CS11 is fetching the values for display of GR Time and Del. Time.
    How can we populate the values in CS11 report out put for GR Time and Delivery Time? Am I missing some master data maintenance apart from Material Master?
    Regards...

    Hi Prasobh,
    I looked at the note 101262 and it seems that it is suggesting us to create a new Z report by copying existing report and then modify the WRITE Bloack in new report to display GR Time and Del. Time.
    Is my understanding correct? If yes can you share with me the steps in some more details then mentioned in note 101262 that I need to follow for addressing this requirement.
    If no can you suggest any solution that you know by which it is possible to include GR Time and Del. Time in CS11 output without Z development.
    Regards,

  • Planned delivery time not updating real time in apo

    Hi,
    I have a location product which is part of the active integration model.
    The location and product are both available in ECC and APO.
    When i change the value of Planned delivery time in ECC, the changes do not get transfered to APO even after RIMODINI.
    For e.g. the planned delivery time currently is 1 day and it is changed to 3 days, even after doing RIMODINI the changes are not reflected in APO.
    Kindly suggest if somebody has come across this issue earlier.
    Thanks & Regards.
    Santosh Joshi

    Hi Santosh,
    Please check by tcode CFM5 weather material is there in IM or not .
    Also check CFG1 log on R/3 and SLG1 or /SAPAPO/C3 or /SAPAPO/CQ in APO.
    Please confirm.
    Manish

  • Delivery Schdule not cosidering while doing GR

    Dear All,
    I have raised a PO in ME21N, in that under delivery schdule tab I have maintianed schdule lines say for an example
    D     06.07.2009     10          06.07.2009
    D     07.07.2009     10          07.07.2009
    After filling these details by saving PO number generated.
    If I am trying to GR on 06.07.2009 it should allow me to take only 10 Nos.  Kindly tell me the settings where can I control this.
    Rgds
    Srini

    Pls set Message M7 254 into Error in OMCQ trxn..
    It will not allow GR before Delivery date

  • Set up time not considered

    Hello ,
    I am using PP-PI.
    The resource category is '001' machine and having std formulas 'sap001' for setup and sap002 for processing and other formula 'sap006'
    The recipe has setup time and processing time .When i run MRP the planned orders are created  but no set up time is considered in it.
    I tested the formula in resource and it calculates set up time.
    What settings i need to check ?
    Also, for the planned order , in det.scheduling tab system shows 'capacty requirments'(in min).
    But this does not match with production dates.
    Example  - prod dates-  10.06.09 ( 14:00:00) to 24.06.2009(24:00:00) = 10*1440(days avlb capacity) + 14:00 =  14410 mins.
    But the capacity req shown is 15000 mins( opr qty *processing time). 
    What settings i need to chk  ? kindly advise
    Regards
    ShankarR

    Shankar,
    Have you maiantained the scheduling parameters  for planned order in OPU5?
    If not then execute the same & under 'Detailed scheduling mark 'Scheduling' & 'Generate capacity requiremnt'.
    Regarding the differnce in capacity requirement & scheduling, make sure you use similar formulas in scheduling as well as capacity tab page.
    Hope this helps you.
    SmanS

  • Delivery qty not correct for partial delivery

    Hi, I met some issues need your help!
    1) Create a sales order base on the sales bom.
    2) Current stock and supply is not available for the required delivery date.
    3) According to the current stock or supply qty.only confirm partial qty for the components.
        eg.
        the structure of this sales bom as below:
        Material: A 1PC --> B  1PC
        Material: A 1PC --> C  1PC
        After ATP check ,the result as below.  
        item 10   mateiral A (Header)          100PC   ( not relevent for inventory)
        item 20   mateiral B(component)     100PC   confirmed  30PC
        item 30   material C(component)     100PC.  confirmed  10PC
    4) Create delivery(partial delivery) with the selection date.
    5) We can find the component quantity is correct but the header quantity is incorrect.

    Hi
    Configure the field 'Create Delivery Group' in the item category of BOM (VOV7) in the Bill of Material/Configuration area. Please go thro the F1 help details of that field..
    Form delivery group and correlate BOM components
    Here you can determine whether sub-items that belong to a main item, and which resulted from a BOM explosion, are to be combined in a delivery group.
    Use
    You use a delivery group to determine a common delivery date for all the items that it contains. If you double the quantity ordered for the main item, then the order quantity for the sub-item will also be doubled.
    Indicator X means that a delivery date is created for the delivery group. The system uses the last date (chronologically) of an item in this group to create the schedule line date.
    Indicator A means that the system generates correlated schedule lines. If no complete delivery is required, as soon as all the items in a bill of material are available, the system creates a correlated schedule line. On the first date, when all items in a bill of material are available, a confirmed quantity is issued.
    Thanks,
    Ravi

  • Infotype 0008 wage types are not considered while payroll

    Hi Experts,
    When i am running the payroll, all the wage types of infotype 0008 is not considered. Neither it is being stored in RT. But all the wage types of infotype 0014 and 0015 are correctly being considered in the payroll. Plz help
    Regards
    Tarun

    Hi,
    Plz see the XVAL log that i am getting while running payroll. Do let me know if you need any other information. I can call you now if you say.
    PIT   XVAL P10            Valuate pay elements
        Input
            IT
    Table IT
    PCRlGr Wage salary type               WC  C1 C2 C3  Assign: AltPa  CA  BT Abs.
    Var s. Unit    Rate                      Number       Amount
    3      /806 Partial period factor 6   01
                             100,000.00
    3      2000 BASIC SALARY-NEW          01
                                                                      8,000.00
    3      3000 BUS DEDUCTION-HPL         01
                                                                      1,000.00-
    Processing
         /806 Partial period factor 6
    /806 Partial period factor 6
    Rule   ESGPCR VaKey    Operation
    XVAL      3            VWTCL 10
    XVAL      3   0        ADDWT *
    2000 BASIC SALARY-NEW
    2000 BASIC SALARY-NEW
    Rule   ESGPCR VaKey    Operation
    XVAL      3            VWTCL 10
    XVAL      3   1        ELIMI *
    XVAL      3   1        RESET RA
    XVAL      3   1        RTE=  /801
    XVAL      3   1        RESET *
    XVAL      3   1        MULTI RAA
    XVAL      3   1        AMT/KGENAU
    XVAL      3   1        ZERO= R
    XVAL      3   1        ADDWT *
    3000 BUS DEDUCTION-HPL
    3000 BUS DEDUCTION-HPL
    Rule   ESGPCR VaKey    Operation
    XVAL      3            VWTCL 10
    XVAL      3   0        ADDWT *
    Output
    IT
    Table IT
      PCRlGr Wage salary type               WC  C1 C2 C3  Assign: AltPa  CA  BT Abs.
      Var s. Unit    Rate                      Number       Amount
      3      /806 Partial period factor 6   01
                              100,000.00
      3      3000 BUS DEDUCTION-HPL         01
                                                                       1,000.00-

  • In-house production time not considered in scheduling

    i have a material, with an in-house production time of 7. requirements date is today, May 23. as a sap standard, using backward scheduling, it shall see that the start day lies in the past, and should switch to forward scheduling, with May 23 as the start date, and may 30 as the finish date. however, the system only proposes a finish date of may 27. why is the system behaving this way?

    Hi,
    Please let us explain, where u have carried out  scheduling  ie  during the MRP or in Production order.
    I hope ur asking about Production order scheduling , inthat case system will not consider the Inhouse production time. Because lead time scheduling is carried in production order.
    Scheduling will be done for routing times not for In-house  production time.
    Pradeep

  • Timer not expired while running process

    Dear All
    I'm using timer to blink the text message in 6i forms.Its working fine.
    But the problem is while running process timer not expired.
    If there is any solution to expire timer while running process, please let me know
    Thanking you

    As I understood you want to expire the timer in a specific time.
    you can call SET-TIMER with NO_REPEAT Indicates that the timer should not repeat upon expiration, but is to be used once only, until explicitly called again.
    You can call it every time that you want

  • STOCK OF FINISHED PRODUCT BY PIR NOT CONSIDERING WHILE TAKING MRP RUN

    DEAR SAPGURUS,
           I have finished product stock of 50 nos through planned independent requairement. now i am creating sales order for finished product but mrp run generate the planned order for finished product. I dont have planned order for finished product because material already have stock. what can i do please give solution.
    thanks.
    Regards
    Atul

    Hi Atul,
    Please describe your problem better, it's not easy to understand...
    Strategy 10 is net reqirement planning:
    - SAP considers only PIRs as requirements, SOs are not considered
    - SAP considers stock levels
    - requirements should be LSF (check in MD04)
    If you input sales order SAP won't create PldOrd for it. If you have stock and you want to create more to fulfil you SO, you have to input PIR accordingly and run MRP.
    Please clarify your problem...in a way that we may understand it.
    http://help.sap.com/saphelp_47x200/helpdata/en/60/9ea1536fbd11d191820000e8a5f6e6/frameset.htm
    http://help.sap.com/saphelp_47x200/helpdata/en/e0/71bb199c9f11d191920000e8a5f6e6/frameset.htm
    Thanks,
    Csaba

  • On Order Stock not considering while Replenishment planning in IS-Retail

    Hi SAP Gurus,
    I am running Replenishment planning in IS -Retail system, but it's not considering On order Stock (e.g  Purchase order - schedule receipts). could you please tell me the config where system can consider on order stock.
    Thanks in Advance.
    Sagar.

    Hi Mayank,
    I had already done the steps that you have mentioned. i.e. Changing the error processed records to
    "Not Processed" and running the initial load again, but it does not help as the exception still continue to be the same i.e. No Product or Location can be found in the database" whereas these details are already present in the system i.e.if you check /FRE/MASS_LOC or for product.
    After checking the help (F1) for TEMPRPFROM, it clearly specifies that if a date is mentioned in the field, it will activate the blocking on the date and if no value is present in the field, then the temporary blocking will not be enabled.
    Also, a surprising fact is that whenevr I transfer the product or location details on a particular date, the TEMPRPFROM reflects that particular date even in the interface tables. So wondering whether some customizing field is present in IS-Retail side which is causing this issue
    Best regards
    Prashant Kedare

Maybe you are looking for