Hi Experts,
Could you some guide me about the scenarios when Plant woul d hold the Excise Resistration as Dealer.
1.Import Purchase in Plant (Dealer) - How to pass on CVD to customer while selling those import Product. Is there any need to introduce new CVD condition in Sales pricing ? and how the accouting impact will be?
2.Dealer Purchase in Plant (Dealer ) i.e second stage Dealer - how to handle?
3.Third Party - Plant (Dealer ) purchase from Vendor and directly ship to customer - How to handle and accounting impact?

1-Since you are  a Dealer yourself, your Plant will be registered as a Depot i.e. using  RG23D Register.
Since you are  a trader (Depot) ,  All the duties (including CVD) should get Inventorised.   If We want Duties To be Inventorised, we need to mantain it as "Non Cenvatable" in J1ID  and also  add the  Non Cenvatable option in Movement type  assignment for 101.
The Depot Sales procedure  , should be able to handle the Sales part i.e. picking of  teh CVD values  in the Pricing procedure from teh RG23D entry.
2- Dealer:
Again, here  the Duties should be Inventorised. But you cannot show actual Duties at time of PO.
In FV11 , maintain 0% for Inventory Duty conditions  JMIP,JEC1 and JSE1  ,  maintain 100% for Ivnentory Total conditions   : JMX2,JEX2,JHX2.
In MIGO Base will default as PO Price,We will change it to Actual as per vendors Invoice also Enter BED,Ecs,Seces as per Invoice.  Do NOT tick MRP indicator
The total PO Price+ Excise will be posted to Inventory.( Since there is no concept of  Part 2 posting in Depot).
I worked on this 4 years ago,  and the clients requirement was that in their Trading depot, all Duties /excise should be Inventorised,  because they were not a manufacturing unit so  there was no "cenvat" as such.

Similar Messages

  • Plant is subcontractor with excise

    Hi,
    We are having only Plant 1000(mfg Plant),  we are dealing with so many vendors but one of our vendor 9000.
    Our Vendor 9000 taking our plant service, He is sending some material for champ ring, we need to take that material in our plant , done the job wok and send that material back to Vendor, How to deal in SAP with Excise.
    if he( our 9000 Vendor) send that material with F4 challan to our plant , then how to map?
    Plant 1000's responsibility is to take the material and send them back after job work.
    sapman man

    HI,
    As per my understanding either i can receive Non Valuated Material (Through Dummy PO).  But how to deal with excise ( Vendor treated our Plant is subcontractor, so, i,e reason Vendor sent their material with subcontracting challan)
    Is their any Provision in SAP so how to deal with this scenario, Bcz we are created Dummy PO and doing GRN  then what abt excise capture?. is it feasible if vendor sends their material with challan then how to treat that challan in our premises, bcz we are created STD Dummy PO means , as per Basic SAP we need to capture excise Part1 and Part2.
    After completion of Jobwork how to issue that Material to Vendor, ( in His view our plant is subcontractor).
    Is their necessary to create outgoing excise invoice while issue or sale of material to vendor.?
    sapman man

  • Batch at Packing Stage with mutiple prices

    SAP : ECC 6.0
    Module : Production and MM
    Issue : 1 Batch with multiple MRP.
    Domain : Chemicals
    Let me say I am very new to SAP and this forum. I could not find the exact place where to post my query so posting here. Help me where to post the query if this is wrong place.
    We are in the process of Moving from a Legacy system to SAP R/-3
    Our Process is as follows.
    1. Batch Transaction : Batch production how we are going to produce for a batch will be declared. Batch No as follows.
    YYMMPR0023  > YY -> Year MM- > MONTH PR> PRODUCT 0023 --> running batch.
    so batch transaction we will declare how much quantity we will produce. ex : 2000KL (kilo lt)
    2 Stage 2 : Packing while packing as per the market requirements we will pack this material in different packs not continue.
    ie. we do not pack whole material one time as per the market requirements the material will consume as per the size of the pack in demand.
    Due to this our Pricing strategy is also keep changing. ie packed material will be in 2 or 3 prices at different prices.
    when we dispatch the material will be identified with the price as sub field to categorize them.
    Current legacy system we are following this.
    Sales
    Packing --> Dispatch from plant ---> Dept. --> Dealer ---> Customer
    Return
    Customer --> Dealer --> Dept --> Plant
    this process is running. At all the places we are able to identify the stck batch level and even at MRP(price) level also.
    Implementor says in the R-3/ SAP standard this feature is not available. It is not possible with standard mechanism
    I would like to know what is the mechanism to be followed to address this.?
    Kindly inform us.

    Hi
    I'm not sure I understand you...please define your question...
    1)
    As I understand here question is:
    - batch number assignment
    - amount of the material that belongs to that batch
    In SAP you can use automatic batch number assignment, and you can also define the logic /rule based on which system has to generate it.
    When you make confirmation against a production order or goods receipt w/o PrdOrd refernce in REM (repetitive manufacturing), you define the produced quantity --> SAP will allocate the batch number
    2)
    As I understand here you have two questions:
    - how to solve pricing based on packaging
    - how to track the material (traceability)
    If you use different material numbers for different packaging (different packaging may mean diffenerent SKU), there's no problem. If you want to use the same material number for different packaging, it's very likely you have to go to developemnt - generally, batch is given / determined at the time of delivery creation. But in your case the batch should have information on the packaging and you should define it (batch) in the SO to solve pricing.
    When you sell the material (as I understand you sell it to the distributor), the material won't be in your system any more that's why you cannot track the goods from distributor to customer).
    Is Depot yours? Does the ownership of the goods change when you give them to the distributor? If not, you can map the process:
    Plant --> STO (stock transport order) --> Depot --> Consignment fill-up --> Distributor --> Consignment GI --> Customer
    Please give more explanation if my answer is not ok.
    Regards,
    Csaba

  • Capture of excise invoice nfrom dealer in depot plant

    Hi,
      I have one scenario,  we have depot plant generally we capture the excise invocie with J1IG  and one custom transaction ZJ1IG,  one  our vendor  who is a dealer  has given  the price as below
    Material Price  :  100 (inclusive  of excise duties)
    Vat                     12.5
    so I have created the PO with base amount 100  and with vat 12.5 tax code,  also setting for capture of excise invoice in MIGO  is done now when we are trying to do MGIO and rg23d entry in MIGO  as we want that total  100 amount should be debited to material account  so there is no need for selecting the MRP indicator  but for RG23D  regsiter entry  in excise item tab at item level  we are spliting  the base amount  and BED, AED, ECESS, and SECES  so the total material account is debited with amount 100  and aslo RG23D register is updated  as per splited amount.
        The problem which we are facing is some times the MRP indicator is not coming in header in that case it works OK  and some times MRP indicator comes at header in that case system gives the error message  please maintain the gl account for RG23AAED  also in such case along with excise duty and excise amount tab at item level  additional data tab is also coming at item level,
    what can be the problem.
    regards,
    zafar

    Hi,
    Please maintain Gl Account for RG23A AED
    LG> Tax on goods Movment > India > Account detrmination > Specify gl account per Excise transaction
    Regards
    AKM

  • How to deal with the change in address of plant,

    how to deal with the change in address of plant,companycode,sales org etc.?

    Hi,
    Do you want to change the address of Company code, Plant and Sales org?
    Follow the menu path in SPRO.
    SPRO >> Enterprise structure >> Definition >> Financial accounting >> Define Company code >> Edit company code >> Click on address and change.
    .. Definition >> Sales and Distribution >>  Define ...sales org >> select the sales org and click on address and change.
    ... Definition >> Logistics - general >> Plant >>>> Click on address and change.
    Regards,
    K Bharathi

  • Dealer purhcase for Manufacturing Plant

    Hi Gurus,
    We are trying to create PO for Trading Vendor
    We can able to enter the Base Amount as per Vendor notification( Like Quotation), Excise amount we came to know at the time of Goods Receipt so we activated MRP indicator in the mics tab of GR screen. then i entered exact Excise amount and Base amount as per vendor excise invoice still i am getting the below  problem. I am using tax code which is having zero values for BED, Cess, SHcess and it is calculating VAT 12.5% and 1% of surcharge of VAT as per our requirement.
    We are having a problem while posting manual excise invoice for a dealer. While posting the invoice in MIRO the system debit the inventory account for the excise value instead of the CENVAT clearing account.
    Can you please guide us.
    Thanks in advance.
    with regard,
    Sudir.

    Dear MM Gurus!
    Dealer Purchasing  is still pending , i did the process like this note only( Note No:1104456)
    but in my case we having both Excise(14.42%VAT 12.5%1% surcharge On Vat)
    exicse values are not flowing i.e CENVAT account values are not coming in simulation of invoice.
    as per fourm result i tried everything.
    Pls give solution !
    with regards
    Sudir.

  • Plant Determination for Third Party Material as Child Item in Sales Order

    Hi All,
    We have an issue with the Plant Determination for Third Party Material as Child Item in a Sales Order.
    Even when a Delivering Plant is maintained for the child item which is a Third Party Material, the plant of the Parent Item is only populated as the Default plant in the Sales Order
    Can someone explain the reason behiind this determination.
    P.S.- For all non -Third PartyChild Items (with non-Third Party Item Catefory & Material Type), the Plant is population correctly as per Delivering plant in Material Master.
    TIA.
    Regards,
    Sridhar

    Hi,
    Thanks everyone for the feedback.I agree with Samir Danish.It is a standard functionality of SAP which does not allow free goods for BOM material.
    However, can someone suggest work around to deal with this issue.I mean if any one has been doing any work around for this issue then please let me know.It s becoming critical for me.
    Regards,
    BM

  • In Depot Plant while Doing MIGO MRP indicator not found

    Dear All,
    We have one depot plant. for capturing of excise duty while doing MIGO
    I have not found the MRP indicator check box in excise ->misc. Tab.
    But for doing this same process for other manufacturing plant means non Depot plant I have found the MRP check box in excise ->misc. Tab.
    Is there any process to capture the MRP check box indicator in excise ->misc. Tab while doing MIGO for Depot plant or is there any process to book excise duty while doing MIGO for Depot Plant

    Please go through the Scenario #: Dealer Procurement in Excisable Depot scenario in the below link.
    http://scn.sap.com/docs/DOC-45855

  • Third party with sto from supplying plant

    Hi,
    When i am trying to convert Third party purchase requisition NB created through Sales order
    to Stock transport order to transfer the material from other plant i am getting following error
    Error Message
    Third-party not defined in the case of vendor with plant assignment
       essage no. 06769
        You are entering a purchase transaction involving a vendor to whom a
        plant has been assigned. Normally, this will involve the transfer of
        materials from one plant to another.
        This process necessitates a delivery and a billing document in the SD
        system. The PO appears directly in the delivery due list of the issuing
        plant (vendor) and therefore does not need to be transmitted.
        However, an item with the procurement form "third-party" (triangular
        business deal) cannot appear in the delivery due list.
        An item with the procurement form "third-party" can only be ordered from
        vendors without a plant assignment.
    Anybody has any suggestions on this scenario
    Diwakar

    Hi Niel,
    You don't need to create an STO. If you create a normal sales order with delivering plant B, they will see it in their delivery due list or MD04 or whatever. And it doesn't matter for this purpose that the plants belong to different comp. codes. This will only matter after the delivery to the customer - VF01 (or VF04) with reference to the delivery will bill the customer (comp. code A is billing); then another VF01 will generate inter-company billing document where company B charges comp. A.
    So why do you insist on having a STO?
    BR
    Raf

  • Third-party not defined in the case of vendor with plant assignment ?

    We use a Third-Party Vendor to direct-ship some products directly to our Customers.
    When transfers third party order form's PR STO PO, prompts the following information
    Third-party not defined in the case of vendor with plant assignment
    Message no. 06769
    Diagnosis
    You are entering a purchase transaction involving a vendor to whom a plant has been assigned. Normally, this will involve the transfer of materials from one plant to another.
    This process necessitates a delivery and a billing document in the SD system. The PO appears directly in the delivery due list of the issuing plant (vendor) and therefore does not need to be transmitted.
    However, an item with the procurement form "third-party" (triangular business deal) cannot appear in the delivery due list.
    Procedure
    An item with the procurement form "third-party" can only be ordered from vendors without a plant assignment.
    how should solve?
    Many thanks,  Adny.
    Edited by: Andy Yao on Feb 8, 2010 3:58 AM

    Hi Andy
    Why u doing stock transfer order,in third party sales there is no stock transfer
    Follow below procees for third party sales( Vendor ship materials directly to customer)
    Create Sales order(Use item category TAS) >>> Purachase requisition(Automatically from order) >>> Purchase order >>> Vendor Invoice Verification >>> Invoice to customer
    Kapil

  • Sales Order stock transfer between plants

    Hi,
    I'm dealing with a problem in a folding cartons packaging industry.
    Finished Goods are very specific and they are produced in plant "A" using Make-to-order scenario. After production the finished goods enters plant "A" as Special Sales Order Stock (Type E).
    This stock is sold to end customer from plant "B", so in some point the special stock must be transfered from plant "A" to plant "B". Material is shipped so we need to have a delivery for this transfer.
    Do you know any process/transaction to do this?
    Thank you,
    Sebastián Ligueros

    Hi,
    You can try using t.code ME21 or ME21N.
    Use document type UB- stock transport order.
    Enter the supplying plant as (A) and receiving plant as B at line item.
    In the line item(s), under account assignment category, enter value as C-sales order.
    At the bottom line item details, in the account assignment tab, enter the sales order number. Then save the STO.
    Create the delivery with respect to this STO using t.code VL10D. Do the PGI.
    Receive the goods in plant B using transaction code MIGO. Select goods receipt and outbound delivery as criteria.
    Regards

  • Dealer Invocie -MIRO is not picking excise value from MIGO it takes from PO

    Hi all,
          I have a issue in dealer invoice.
         I have raised a PO., made goods receipt against that PO. Entered the excise duties, education cess and Higher education cess manually in MIGO. Automatic posting is done for that excise invoice. When MIRO is raised it picks the value from PO.
       It is a new plant. The issue is in this plant only. The dealer invoice works fine for all the other plants.
      Kindly help to resolve this issue.
    Regards.

    Hi ,
    please refee below
         Creating a Purchase order with Zero Tax code
         Capturing of Excise invoice in J1IEX/MIGO.
         Activation of MRP indicator during capturing
         Posting the Excise Invoice captured.
         Invoice processing for the Purchase order
    In the MIGO screen, you can find that the excise base value is defaulted as the PO price and the excise duties are zero.
    Now manually enter the respective excise rates for Basic excise duty (BED), Educational cess (ECS) and Higher Educational cess (SECESS).
    The excise base is changed such that the sum of the excise base value and the excise duties remain the same as the PO price. The excise base is reduced by the excise duty value and the differential amount is split amongst the relevant excise duty components.
    In the miro screen change the base value as same that you have maintained in MIGO.
    also refer the note which i am insisting so that you can able to meet your req.
    Regards,
    velu

  • Plants inventory at Vendor Location

    Hi All,
    This is something interesting I came to know from my client. Here is the current business process
    There is a vendor who we subcontract work to but all the parts are inventoried at the vendor location even before the contract work begins. Until then, the inventory is owned by the plant and the vendor need to cut a Purchase Order everytime they want to consume
    This can be well explained as an opposite scenario for vendor consignment. In vendor consignment scenario, plant stocks material that belongs to vendor and cut a PO when required to consume.
    Can someone please explain if you ever faced a scenario(underlined above) and how to deal with it in SAP?
    Thanks in Advance,
    MG

    Hi Sridhar,
    Thanks for replying. I didn't quite understand your answer. May be my question is not clear.
    There is only one plant and one vendor. This vendor is setup to do subcontracting work. But, the materials required for performing the work is already stocked at vendor's own site. This stock is owned by the plant not by the vendor.
    Once the plant gets a request to make a product from a customer, the materials stored at the vendor location are then sold to vendor (then those materials are owned by vendor and taken off the ledger in the plant).
    How can we set this up in SAP?
    Thanks,
    MG

  • Consignment process - change of delivering plant (consignor)

    Hi Gurus,
    Our organisation has decided to change the Plant from PL01 to PL02 for the consignment process hence needs all the consignment stock move to PL02 and the future processing of consignment fill ups, issues , returns and pick up should be done through PL02.
    I need your suggestion on how to deal with this change and please help me with what all config changes do I need to do to deal with this change.
    Thanks in advance!
    Regards
    Bawa

    1)  You have to extend those materials in plant PL01 to PL02
    2)  From there you can process consignment fillup
    3)  For already despatches made from PL01 and stored as a special stock, client has to decide as to whether he will retain the same plant in case of returns at a later date.  Else, he will have to do the process of consignment pickup for those special stocks and redo the fillup order creation.  This exercise is only to set right the things / datas in SAP. 
    thanks
    G. Lakshmipathi

  • Plants abroad - WIA billing document

    Hello,
    I have customized plants abroad as explain in note 506588, but when I try to bill the delivery document to obtain the WIA billing document, the system displays an error saying that the document is not relevant for billing.
    The billing relevance of the item type used in the
    delivery document is "Relevant for deliveries across EU countries". The plants used in the process flow are from Spain and from Denmark, so we need the billing document for the EU report in both countries.
    The used flow is the following
    Purchasign order: UB
    Delivery document: NL
    Sales document: NL
    Item category: NLN
    Billing document: WIA
    Plants abroad are activated and the VAT Registration Number for Plants Abroad is entered. Does anyone know why the delivery is not relevant for billing if the item category is marked as relevant?
    Thanks in advance, best regards.

    Hi
    Can you let me know ,
    Is it the triangular deal you are speaking
    Because from your flow , I could not see any delivery against the sales order.
    Can you let me know .
    Hope to help you.
    regards
    KRSNA

Maybe you are looking for